dmarchuk97

How are you keeping track of selections against your allowances?

last month

I'm building a custom single-story house that's going up right now, and my builder gave me an allowance for each category, like plumbing fixtures, lighting, and tile. There are a lot of threads here from people who found out they were over when the change order showed up, some with a 20 or 25 percent charge added on top of the overage. I'd like to know where I stand before I pick anything else.


I started with a spreadsheet and then made my own tracker, which lists everything room by room and keeps a running total over or under for each allowance. It's helped, but I'm sure I'm missing things that people who've finished a build already know.


How did you keep track of what you'd picked against each allowance? Did your builder split any allowances by room, or give one number for the whole house? And what do you wish you'd started tracking earlier?

Comments (9)

  • last month

    Is your contract Fixed Price or Cost Plus?


    You can't really have a change order unless the product was already specified/picked in the contract and you changed it to something else. Did your builder pick things out in your "custom" build?

    I did a custom build and had no change orders. It was cost plus, so I paid what the product cost plus the builder markup. Did I pick products that were higher price/quality compared to what my builder guessed in the quote? Sure did, but I had remodeled a previous house and had a good idea of prices, so I knew the builder had some allowances that would be too low, so no real surprises.

    If the final price needed to be known upfront and you didn't have much flexibility with your budget, then like Millworkman said, that spreadsheet should have been done before you signed the contract.

    We were 40% over our builder's guess/quote, but it was our retirement house, we wanted what we wanted and we plan to stay here until we are very old or dead! We also built during covid, so some of that 40% was definitely due to overall rapid price increases for materials/labor and product shortages.

  • PRO
    28 days ago

    Allowances minimize change orders. Its rare people will do the selection work prior to contract. Archtects sometimes preselect but the usual client reponse is "those aren't mine"


    We do allowances by function/procuct type. It makes for a simple 3 columns spreadsheet of:

    allowance, selection, over/under


    Allowance examples:

    Appliances

    Plumbing fixtures/faucets

    Cabinets (not including install)

    Hardwood (materials only)

    LVP( (materials only)

    Tile (materials only)

    Slabs (materials only)

    light fixtures (does not include flush lights, undercabinet lights, rope lights shown in plan)

    Hardware

    Entry door

    garage doors

    Windows (sometimes)


    We specify "standard tile set square or stagered) for example. Herringbone set and/or mosaics are extra unless specified. OVersidzed tile 24x48 or larger is an install preimum. Slabs do not include porcelain. Would have to be priced seperately. Waterfall ends and tall edges are not included unless specified.

    Appliance panels are not included unless specified.


    Note that this will vary by builder and it is not uniform, but what makes the builder comfortable. IF they use a flooring store for example, the allowance may include install.


    There is no standard in creating allowances.

  • PRO
    28 days ago

    I’d organize your tracker by trade, then room/area, then individual item, with a summary tied back to the allowance categories in your builder’s budget.


    Start by confirming that you have a complete list of what’s needed. For each shower or tub, identify the exact fixture kit and components included in the allowance, including the rough-in valves and matching trim. Verify quantities, too: how many plumbing rough-ins, outlets, fixtures, and other items are actually accounted for?


    Ideally, have elevations for every wall—or at least every wall containing finishes, fixtures, or rough-ins—so you can check quantities and locations against the selections.


    Before making more selections, ask your builder to walk through one actual item, from its allowance to the final amount you would pay, including any markup. Confirm whether that markup applies only to the overage or is calculated another way. Also clarify whether unused allowances can offset overages elsewhere and how remaining credits are handled.


    For purchasing, ask whether you can benefit from your builder’s vendor accounts and trade pricing. If you get a competitive final price and the builder also benefits, that can work well for both of you. Compare that price, including applicable markup, tax, and delivery, with what you can obtain directly. Agree with the builder on how independently purchased items will be handled before ordering.


    For each approved selection, get written confirmation of the additional cost and keep a running total of approved overages. Separately identify choices you’re still considering, so you can see what you’ve committed to and what your next decisions would add.


    Once you find something that fits the design and budget, confirm compatibility and quantities with your builder and order promptly. This is especially useful for complete room packages where fixtures and hardware need matching finishes—purchase the coordinated items together where possible. Changing selections later can involve returns, replacement parts, delays, and rework, making it both costly and burdensome.

  • PRO
    28 days ago

    Cost allowances can be the most contentious part of a home building or remodeling project. Builders and remodelers are not mind readers.

    To minimize "surprises" during construction, I encourage my clients to make early selections of cabinetry, tops, plumbing fixtures, and appliances. "Early" means as soon as the conceptual plans are avaiable for trade partners to use them for take off purposes.

    It's certainly a reasonable request to ask how your builder determined each allowance included in your contract. It's not reasonable, in my opinion, to ask the builder to break down each allowance according on a room-by-room basis.

  • 27 days ago

    My builder's quote/guess was based on our detailed building plans. We had a lot of cabinets and built-ins throughout the house. My builder put in $64K as the cabinet allowance. I definitely thought is was low as I had done a kitchen a few years earlier in CA, which was more than that for the kitchen cabinets only. People kept telling us it was cheaper in FL ... maybe, but not that much cheaper!

    Once we signed the contract and I met with the cabinets maker, the bid came in for all the cabinets and built-ins, and the cost was $140K. We went ahead per the plans, but my builder should really have gotten a guesstimate from a cabinet company! We could cover the costs, but that might not have been true for all customers. It is like he just guessed the cost for a house with a simple kitchen and 2.5 bathrooms, when our house was much larger, with more details.

    I do like my builder, but I felt he missed the mark when it came to estimating costs for the initial budget, even with detailed building plans.

  • 22 days ago

    The part about building your own tracker stood out to me. It sounds like the hard part isn’t just recording what you’ve selected, but knowing the real final cost before approving it.

    Does your tracker account for builder markups, installation costs, and changes that haven’t been formally approved yet? Or are those still things you have to reconcile separately?

  • PRO
    13 days ago

    "Then give the same scope to two other licensed, insured contractors, without anyone's prices, and ask for itemized bids in the same format."

    The OP related that the home is under construction, to wit:

    "I'm building a custom single-story house that's going up right now...."

    I submit it's too late for competitive bids. The OP asked for a means of tracking spending vs. allowances.

  • 13 days ago
    last modified: 13 days ago

    We used a spreadsheet organized by category - basic but did the job


    the area that was hard for us was countertops - part of that was how the stone yard totaled costs (which was unclear), we also used remnants for baths and while a bit more economical it made pricing harder to track bc of the different levels/pricing variances