Anyone done a bath 'refresh'?

17 years ago

My home currently has a circa-1980s builder spec bathroom that I'd like to update. Nothing moved, no walls or plumbing to be rerouted. I'd like to put in new vanity (cab/counter/sink), tub/shower, toilet, & flooring. I don't want to call it a remodel, as I don't have the time or money for a large undertaking, so I'll call it a refresh.

Here's the catch: it's the only full bath in our house, and I can't imagine my family living without a bathroom for too long.

Has anyone been in the same situation and done the same? How long did it take? What did you do while your sole bathroom was out of commission? What's the cost range for a cosmetic update? (I can ball-park materials, but I've no clue on labor costs) Got any pix?

Thanks.

Comments (17)

  • 17 years ago

    We did something similar in our old place except we also changed the wall tile. Start to finish for majority of the work was 2 weeks (from demo to shower & toilet hooked up). Had to move out for a week to in-laws' spare bedroom. It's just not possible to live without a toilet which goes in once the floors are done which are put in after the tub. The vanity and wall cabinets were custom built so we had to wait for the walls to be done before the guy finalized the specs. I would say the most important thing is to buy all materials before you start so that there are no delays there. It's very hard to get the workers back in once they leave mid-way.

  • 17 years ago

    What kind of flooring (from/to)? What kind of tub/shower (from/to)?

    If it's vinyl and fiberglass, I don't see any reason the whole thing couldn't be finished in a couple days. Toilet changeover would be pretty quick (pull it out, lay vinyl, put it back). You might have to do a sponge bath once or twice waiting for the return of the shower.

    If you've got tile on the floor or around the tub, that's a different story.

  • 17 years ago

    You can paint a chicken any color you want, but in the end, you still have a chicken. In otherwords it is what it is, and you don't have to change the footprint or plumbing to call it that. :c)

    That said, national average for what your bathroom *refresh* on the scale your talking about is 10,000-13,000. You can do it for less, but it really depends on the materials you choose and/or what labor runs in your area. And if planned well, turn key should take about 4-5 weeks again on average.

    Labor costs can also vary but that's depends on if you do your own contracting or if you hire someone to run the job for you. There's also the option of DIYing the parts you know you can handle to save some $$.

    "I don't want to call it a remodel, as I don't have the time or money for a large undertaking"

    Fact: Changing EVERYTHING out in a bathroom is a big job.

    If your current situation doesn't allow for time to research and make educated decisions about what you're going to do and how you're going to do it, maybe this isn't the best time to start a project of this size and you should wait. No matter how you go about it, a project like this DOES require time and money. Unfortunately, unless you're willing to dedicate the time and effort needed, the results will be probably be mediocre at best and could in the long term even be a waste of money.
    Since you're not going to change the foot print, maybe you can try to figure out what products you want to use, get 3 quotes and then maybe try to do the project in sections. It may take longer in the end to finish it, but at least you would not have this big expensive project to get done all at one time.

  • 17 years ago

    Oicu812 - reading my post after posting it, I'm sure it can be read as harsh, but that's not the intent at all.

    When starting out with our "remodel" we got shell shocked a few times because we didn't understand the full magnitude of the project. If you're on a budget (as were we) and you go into this with blinders you risk having problems that can be avoided by doing your research first and realizing up front what will be required.

  • 17 years ago

    I have to agree with lukkiirish--once you throw changing out the tub into the mix, it's a full scale remodel, no matter what you call it.

  • 17 years ago

    you can do the vanity, sink, and toilet as a diy...even the flooring...tub removal isn't that bad either. we went to walk-in shower so did that too, but i do have 3 6'4" guys in the house and a sil whose very willing...

    now our upstairs bath, i am considering having it the new tub installed (old pipes) in anticipation to that we have installed a "temp" cailing in the bath downstairs. we'll have to have access.

    the best up-grade we did was the hi-rise toilet...loved it so much we already installed one upstairs...

  • 17 years ago

    weedy (et al.): It's currently got a 1-piece tub/shower combo (fiberglass, I presume) and vinyl sheet flooring. I'd probably update it to mid-grade versions of the same.

    lukki: $10k is a good estimate for this 'cheap' upgrade. I really just want it to look current/marketable. I can't imagine it'd take 4-5 weeks. I had my entire kitchen gutted and redone in about 3 weeks. A 6x9 bathroom couldn't take twice as long.

    We've got a half bath downstairs. What I really need to know is how long a family of 5 would be without a shower. I'm hoping it'd be 1-2 days of demo and 2-3 days of install. If the new shower is installed and functioning first, then it'd only be about 3 days w/o a shower.

  • 17 years ago

    You can wash your hair and sponge bath in the kitchen or 1/2 bath sink. If you belong to a gym you can use their showers. The backyard hose is an option as well.

    My kids would be thrilled if they didn't have to bathe every day!

    Have you thought about keeping the tub and just changing out the showerhead and control? Maybe refinishing the tub?


  • 17 years ago

    oicu812 - Again, it depends on the materials you are using, the contractor and scheduling. There is currently an active thread that is discussing this exact issue. Maybe it will have some information to help you guess-timate your job. Link provided below. Average is however 4-5 weeks depending on what your doing. For us, moving a wall 12 inches, installing the rough plumbing for the shower, building in the shower pan, pouring cement, leveling the floor, drywalling, laying the tile, grouting, cleaning the grouted tiles, and sealing it's been since...May 18th. Oh, and we switched out and widened a window. I think you'd be hard pressed to find anyone who has done a remodel that will not agree when I say that you should always plan for delays, because inevitably, they happen. So when my contractor tells me, Wednesday, I think Friday. Sometimes he surprises me, which is nice but usually, I'm glad I mentally planned for Friday.

    Another thing you need to consider is what if there are problems? Mold behind the tub for example? Or the toilet has had a small leak and you need to replace some of the flooring?

    You may very well be able to get it done quicker, and I hope with your situation that's possible, but really you should have a back up plan in case issues arise.

    Here is a link that might be useful: how long does a remodel take post

  • 17 years ago

    If you break everything down into steps, have all necessary materials on-site and schedule dependable workers well in advance, it seems like it would be a relatively painless project. I would probably plan for a day in-between each task to allow for 'oops'.

    your tub situation is beyond my scope of knowledge so I'm keeping it in 'my' plan. :)

    rip out everything except tub and existing floor - 1 day

    install new light fixture and exhaust fan, anything else electric - 1 day

    install new vinyl flooring over existing vinyl (considering old is in good condition) - 1 day

    install new vanity cabinet, countertop, sink - 1 day

    install new plumbing fixtures and toilet - 1 day.

    you didn't mention doing anything to the walls... painting is a day project too... along with baseboard and other odds & ends.

    Get 3 or 4 estimates for each project.. if you're handy, do what you can yourself as it saves a TON of $$.

  • 17 years ago

    I did it.
    Lost some hair in the process.
    Took weeks cuz the contractor was beyond horrible.
    Schedule what goes in when. With careful planning, you could do it with only a few days of wash offs in the bathroom sink. Make sure the toilet goes in first!

  • 17 years ago

    Well, I dunno. I remodeled my bathroom in the spring. Actually gutted it. I kept the vanity and the mirror. Replaced tub,toilet,and put in wall tile and floor tile, not to mention all the drywall. With the tub, tile, toilet and flooring purchased in advance, it was done in a couple weeks. Would have been done sooner had not the contractor deciding to take several days off to go fishing. I did all the priming and painting, actually I installed the toilet too. All of it cost me just under 5K. It can be done...

    Teresa

  • 17 years ago

    julie: The existing shower is a 1-piece fiberglass (or something) tub/shower, and I'd replace it with the same. For the floor I'd go vinyl over vinyl. No electrical work: there's no exhaust fan, and one light fixture that I can swap out myself whenever.

    I'd expect the longest wait to be for the countertop. My kitchen project sat motionless for 9 days while the counters (Silestone) were being fabricated. My bath cabinet is 63", recessed slightly into a niche. The counter has a couple weird cutouts where it meets the corner near the toilet. It's not just a stock size that'll be off-the-shelf. If I go with some solid-surfacing, has anyone seen or used those 1-day Mobile fabrication setups?

    I suppose that when I interview contractors I'll have to specify up front that time is of the essence. I'd expect most of them in my area to have experience with the "single bath" situation, as that's what most houses around here have. (Old city. My 25yo neighborhood is still considered "new construction.")

    And I guess the shower would be the highest priority, and a floor safe enough for my kids to walk on. We have a half bath downstairs for the rest. And while the kids would love to be hosed off in the yard, I'd bet that if I tried the same myself, one of the neighbors would end up calling greenpeace. ;)

  • 17 years ago

    Measure your door and the shower/tub unit you intend to purchase. You may not be able to get the new unit through the door.

    I can't see how this job could take weeks unless you find something horrible in the walls that has to be remediated. You're not moving plumbing or changing the footprint of the floor. Julie's plan allows a day for things that only take an hour or two. Here's how I'd see it breaking down.

    Day 1: Remove mirror (15 min), vanity (1 hr), toilet (10 min), baseboards (30 min), and shower (3 hrs). May need to cut it into pieces to get it out the door. Paint the walls (1 hr).

    Day 2: Install new tub/shower in the morning (4 hrs). Install vanity (1 hr), swap out light fixture (30 min). Cut and lay vinyl (2 hrs), reinstall baseboards & caulk (1 hr). Install toilet (15 min) and mirror (15 min).

    Day X (when counters are done fabricating): Install counters, sink & faucet (2 hrs).

    You could install a temporary plywood counter and attach the sink and faucet while your counter's being fabricated. That's what we did in our kitchen while we waited for granite.

    Call me optimistic, but if you've got a crew of 2 working 8-hour days, and they don't discover surprises, this should be doable. My dad did a "replace everything but the tub" remodel for my sister in 2 days working solo, and he's a slow but steady worker.

    I will be putting my money where my mouth is soon. DH and I are going out east at the end of August and helping two sisters each construct new bathrooms in their basements. We're planning to do both in a week and a half. I'll let you know how it goes. :-)

  • 17 years ago

    I just did a minor remodel, and here's how it went for me. The "whole thing" took a month, but the room was only not usable for about 1 week. Actually, it was just the sinks that took a week, but we just didn't use the room at all b/c we have a spare bath.

    The tub was not replaced, just regrouted and redecorated to better match the vanity. The toilet was not replaced, but of course had to come out and be put back in for the flooring. Everything else was replaced, lighting and plumbing were updated, and the vanity went for having one sink to two.

    Timing:

    Demolition- few hrs
    Hired out: installing 2 new outlets, a new ceiling fan/light, 3 wall sconces, converting the plumbing from 1 sink to two, venting the new fan to the outside, tearing out old window and replaced with dual pane, then re-sheetrock everything: about 2 days.

    Then it was a weekend, so we painted, and I regrouted the tub.

    Installed new vanity- one evening.

    It then took a few days for me to coordinate with the marble guys, so it was another 5-6 days until the vanity top and sinks were templated and in. The next day, they were plumbed by my contractor. My husband and I had in the mean time installed the medicine cabinets and lights once the vanity was in.

    I had delayed picking vinyl flooring and backsplash tile until more of the room was done, so it then took a few more weeks to get that stuff shipped, delivered and done, but the room was usable the whole time. Since a lot of these little parts were DIY, I was also working around my work schedule, so it was a full month before everything, including baseboards were in.

    Costs:

    Vanity- about $1000
    Marble- $40 (remnant!)
    Marble fabrication and installation: $420 (2 undermount sinks)
    2 Faucets, 2 sinks: $360
    2 Medicine cabinets: $500
    3 lights: $130
    Above toilet cabinet: $130
    Flooring: $450 (this could have been a LOT cheaper, but the vinyl sheet material I chose was only available in 13' widths, so I now have enough flooring left over to do my other tiny bathroom AND my parents' small bath. I also paid to have it installed, and watched them, so I'll do the other two baths- easy!)
    Contractor (all the stuff listed above): $2000
    Tile for backsplash/decor around tub: $300 (also I certainly could have made this way cheaper, but I had my heart set on a certain tile, and the #@**!! dome liners were $7 each. I already had the tools for installation, and borrowed a tile saw.)

    New shower rod, curtains, hooks, other accessories: $220

    Total: about $5500

  • 17 years ago

    I can't comment on labor costs since we diy pretty much everything around here, but we did our guest bath in 2 shortish days (including numerous trips to the hardware store for things that popped up). We did not replace or re-tile the shower though, but we did re-tile the floor (used quick-drying thinset), replaced vanity, toilet, mirror, lighting, towel bars and painted. We can see under our vanity so we had to do the floor first, therefore, the toilet got installed pretty quickly which is always important to me! The most time-consuming part was actually installing the faucet - specifically the drain assembly. If you have all of your materials onsite and ready-to-go, it is not that bad. We did ours right before Christmas. Nothing like having 20 people over to keep you on track! Ours cost about $1500 after the rebate we received for the toilet (water saving) and I got a great deal on the vanity and top from RH outlet after many months of looking. Good luck with your remodel!

  • 17 years ago

    well, we were in the spot as you in our old 80's house...one day we were complaining about the brassy shower and we were just gonig to refresh...the next day the tub was gonig out the 2nd floor window and the place was gutted...6 mos later, 1/2 DIY, and 10k later we had ourselves a wonderful masterbath.

    The next day we found ourselves relocating to the otherside of the US and now we our attempting the same thing again in our "new" 80's house...baths are really like a can o'worms...besides paint and hardware one thing leades to another...I just hope when we get we won't move again...then again our last house sold in a day!

    personally I would much rather jsut get the whole thing done than do a couple things and be disapointed later.

    The 80's are a tough decade b/c everything seems to be alomond and brass...

    I am looking forward to our next remodel-we learned a lot from the last and are gonig ot replicate a few things we did in the last remodel we really liked too.

    I guess if I were you I would stick to new paint, new hardware and call it good. Good luck!