Second floor tile install - no mastic under backerboard?

17 years ago

The people that installed the travertine floor in our bathroom did not use mastic to apply the backerboard to the subfloor. I did make them level the floor first, (which they balked at), before putting down the backerboard. Since that time, I have read more, and am wondering if it might be a problem that they only screwed the backerboard in, instead of applying it with mastic. Is this going to be a disaster?

Comments (7)

  • 17 years ago

    In my opinion, They should redo it. Screwing down the backer board with no thin set or Mastic is absolutely unacceptable. Tile may loosen and grout may crack due to the minor deflective vibration that will exist between the backer board and the substrate. Redo it.

  • 17 years ago

    You've got a couple of problems. First, as you've said the lack of THINSET (NOT mastic) under the backerboard is a problem. This is not a recommendation. It's a REQUIREMENT from every backerboard manufacturer. However, leveing UNDER the backerboard is, as well. That means the screws won't grip as well, because they're not going as far into the subfloor, and additionally, the screws could conceiveably break up the leveling compound, causing even more problems.

  • 17 years ago

    Oh my, this IS discouraging. It took them almost three weeks to complete the tile on the floor.

  • 17 years ago

    3 weeks to finish a bathroom floor??? That's rediculous for them to take that long unless if your bathroom floor is incredibly huge.

  • PRO
    17 years ago

    Make doggone sure they give you a warrantee on that floor, because if it fails....as it very well may, you need recourse. You should NEVER use mastic to bond the Hardibacker. You need THINSET....even an unmodified "cheap" brand is just fine.....and MUCH cheaper than mastic.

  • 17 years ago

    When our house was built, 10 years ago, our contractor was not going to apply thinset between the Denshield and the subfloor. Said it wasn't necessary, even tho' the guy in the tile store where I picked out the tile said to make sure it was done. Contractor used his employees, not subs to install tile (they did a good job on the floors, but the shower walls and countertops were another story). Contractor called store tile guy a "salesman", implying that he didn't know what he was talking about. I went online to Denshield's website where it said that thinset was REQUIRED. Printed it out and showed it to him. Upset him a lot but he did it and we haven't had a problem with the floors in the ten years we have lived here. (Don't ask about other things in the house, tho'. DH developed a deep hatred for the contractor by the end of the build.)

    We are going to build again next year. I know a lot more about tile installation now than I did then. I plan to interview the sub and watch every day. Will make sure he is o.k. with that. If he's not, we'll get someone else.

  • 17 years ago

    I detest babysitting workers. One of the guys told me I should have just done the work because I knew more about it than he did. Ugh.