dcwesley_gw

When to do backsplash? Final electric?

16 years ago

Our cabinets are installed (except for a few fixes they are doing) and our granite has been templated. The rough plumbing is done as is the rough-in electric.

Had a conversation with the electrician about his return for the finish work - under cabinet lights, outlets, finish ceiling fixtures. He says the counter should be installed and the backsplash finished before he comes back. (Which would also mean diong the backsplash before the canopy style hood is installed.)

Do you all agree with this order?

Comments (2)