Software
Houzz Logo Print
joseph_corlett

GC First, Then Engineer

I got a call to look at repairing some roof trusses that had been cut by an HVAC contractor when he installed a new air conditioner. My potential client is selling this condo and the compromised trusses were apparently caught by a home inspector. The work was done before she bought the place; she never had it inspected.


She provided me with a report from a local structural engineer that contained a drawing specifying the installation of a replacement web, the angled member between the top and bottom chord of the truss. The only problem is, the space required for the placement of the new web is taken up by the air conditioner. In fact, it's the reason the web was cut in the first place.


I emailed the engineer and enclosed the following photograph:


I'm holding the cut 2x4 web against the outside of the compromised truss and it's touching the side of the air conditioner. You can see the sawn end of the web at the bottom, just above the cord. Mr. Engineer wants the sawn end removed and replaced with the new web, but the unit is obviously in the way. I suggested possible blocking to support his specified gussets if the replacement web were mounted to the sides of the chords. He was having none of it.


As far as he was concerned, the AC unit has to go. In this 100K condo, that just isn't a cost effective solution. She's just set her engineering money on fire. He's provided mathematically perfect advice that has virtually no relevance in the real world.

Comments (12)

  • 10 years ago
    last modified: 10 years ago

    Dr. Lstiburek rails constantly about HVAC in attics. Another reason to avoid putting them there.

    At least some of the electrical "improvements" I've come across are more easily remedied.

    Who said electricity and water don't mix?

  • PRO
    10 years ago
    last modified: 10 years ago

    worthy:

    In smaller homes, floorspace is at a premium. My father-in-law just sacrificed a small closet in his small home to install central air here in Florida; you're lucky to fish a wire in his attic, let alone a unit. Hence the pressure to use the attic.

  • PRO
    10 years ago
    last modified: 10 years ago

    The point of this post is to refute the "common wisdom" here of running off to a structural engineer before contacting a general contractor. Had this woman contacted me first, I would have scheduled a meeting with inspection to see what they wanted or alternatives they would have accepted. Then I would have went to the engineer and told him the parameters within which he needed to draw to make a cost effective repair. It may be counter-ituitive for him to make a more expensive fix, but a more expensive fix may be the cheapest if it keeps the unit from being moved. Her money would not have been wasted.

  • 10 years ago

    So this engineer thinks they will undo around 7 to 14 grand of labor and HVAC when there is a more realistic idea that solves the problem? Dumb

  • 10 years ago

    Interesting and educational. Thank you! Also thanks to Cabot&Rowe, and Worthy, for the interesting, (and frightening) photos.

  • PRO
    10 years ago

    "So this engineer thinks they will undo around 7 to 14 grand of labor and HVAC when there is a more realistic idea that solves the problem?"


    The labor and material for moving the HVAC is just part of the cost/benefit analysis that engineers don't do. You have to have the realtor calculate the cost of the lost value when this condo, identical to 30, sells without a small but very valuable closet that every other unit has.

  • PRO
    10 years ago

    I offer the perspective of one who is both a licensed professional engineer and a general contractor. To cut to the chase, the GC- before-structural-engineer argument is a tired one; prescribing structural solutions in this forum based on photos is a fools errand.

    A licensed professional engineer should be able to render a professional opinion irrespective of whether a GC is engaged before, during, or after the scope of professional engineering services. The engineer needs to invest the time and effort to fully assess existing conditions before making a prescription. To do so in this case requires a field inspection and a photo is hardly a suitable substitute.


  • PRO
    10 years ago

    Charles Ross Homes:


    I would agree if this particular engineer had offered a cost effective prescription. He did no such thing. He peeked in the attic, took a few pictures, did a drawing, and basically said "Put it back the way it was." Duh. An eighth-grader could have made that assessment. There were tradeoffs to be made here and he refused to entertain any.


    While it can be difficult to assess arguments based on internet pictures, sometimes the photos are slam dunks, like crooked tile and/or HVAC units blocking the specified repair.


    I'm a licensed Florida building contractor and do mostly surface restoration work, but I'm in the cost effectiveness business. You call the guy that's going to explain your tradeoffs first.

  • 10 years ago
    last modified: 10 years ago

    The only point made by this thread is that the OP discovered a really bad engineer. I don't see why that experience would lead him to make generalizations about other engineers. I spent this morning with an engineer solving some pretty difficult structural problems. The contractor exposed the framing, took some measurements and held the ladder for the engineer while I made notes on the drawings. Everything worked out fine as it has so many times in the past. The secret: hire a good engineer.

  • PRO
    10 years ago

    JDS:

    I've no quibble with engineers. I've got a quibble with Gardenwebbers who see a naked wall or ceiling and pontificate that the poster needs an engineer when a good framer is all that the job requires.


    I'm certain that there are engineers that know that the 20' steel I-beam they'd like will never make it safely down the hill for placement, so they alter their plans for an equal built-up LVL that can be built in place by two carpenters.


    "I don't see why that experience would lead him to make generalizations about other engineers."


    Fair enough. When I said "The labor and material for moving the HVAC is just part of the cost/benefit analysis that engineers don't do.", I should have put the qualifier "some" between "that" and "engineers". Thanks for bringing that to my attention.

  • 10 years ago

    A good framer is hella harder to find than a mediocre engineer. And they are much busier.

Sponsored
AIS Renovations
Average rating: 4.5 out of 5 stars15 Reviews
Custom Craftsmanship & Construction Solutions in Franklin County, Ohio