Need help on what should be the next steps?

4 months ago

Hired a contractor to do a kitchen remodel and it looks like the they have started installing cabinets right after doing the demo. My gut tells me this doesn't the correct order. As you can see in the photos. There are exposed brown paper on the drywall and some spots also have exposed sheet rock between the wall and base cabinets--not to also mention the multiple colors of paint. The plan is to have backsplash tiles and also have the door trims removed for the kitchen entry and the passthrough opening.


Was the contractor correct to do this? If not, what should have been done in the first place and what should be we do now?