Phasing from a Pro Perspective

20 years ago

We're buying a new house on a 7+ acre parcel in rural north/central NJ and am looking for a landscape design firm to work with us on a long-term plan, with installation done in phases over a couple of years.

We've worked with a designer in the past, so are somewhat familiar with the process. However, this is a much larger job than we've had in the past.

I've spoken to a few companies, and when I've asked about phasing, they've hesitated. In the end, it seems they'll do the front one year, and the back the next, but not break it down further than that.

Is this the norm? Just want to have an understanding of what to expect. Thanks for any insight you can provide.

Comments (12)

  • 20 years ago

    Phasing is a "red flag" to a lot of contractors. Contractors, particularly design/build contractors, usually value their design time in terms of steering it toward making sales on the installation side. When they hear "phasing" it means that they are fishing in a pool of smaller fish. When design and/or consultation time is slim (spring to early summer), it makes sense that they do not want to take that resource away from bigger payoffs whether that seems fair or not. Phasing also can be an indicator of "limited resources" which can mean a greater probability of delayed payment or lack of any installation sale at all.

    Consumers tend to look at design services as a separate entity from installation. They also tend to think that the direct profit of design services should mean that the more design sales the merrier whether there is an installation sale or not. The problem is that it is time consuming work with a very limited (usually one) staff to do it. A dead end design often consumes a 40 hour work week which displaces a different design with a greater chance for an installation. That time can not be made up.

    Your incentive to pay for a design is that you will have a full master plan that can be phased in. Their incentive is the price of the design and the chance of building it. There is a chance that they will give you a price to build it all at once. Since that chance exists (how ever slim it is), it is not wrong for you to leave that option open in your mind. Before you close that option, get the plan and then let them bid on it. Then you can decide to phase it.

    In other words - don't talk about phasing with the designer until the design is complete.

  • 20 years ago

    We had a master plan done knowing the installation would be phased. We hired a designer who does not do installations so it made no difference to her. We've gotten several bids on all aspects of our job, and all of the contractors were willing to break things out for us so we could pick and choose what to do first. It was difficult to decide, should we do all masonry this year, and plantings next, or do the entire front this year, and the back next?

    They were generous and willing to go this far, cheerfully and politely:

    Cost of masonry front
    Cost of masonry back
    Cost of masonry side
    Cost of grading, ammendments, bed prep, and sod front
    Cost of grading, etc. back
    Cost of grading, etc. side
    Planting front (broken out cost PER PLANT)
    Plantings back (")
    Plantings side (")
    Mulch price delivered, then price to distribute

    Irrigation was separate. Driveway was separate.

    Add it all up, for total cost.

    Keep in mind there are many firms and the services they offer vary. Laag's firm probably wouldn't want to work for me, but there are plenty of others that do.

  • 20 years ago

    Spunky's experience was exactly ours. And because of this firm's willingness to break down our project into workable phases, they'll be the ones getting the call each time we're ready to do the next phase. We would've *liked* to do it in one crack, but can comfortably afford it only if it's in four or five pieces.

  • 20 years ago

    I'd rather work with 10 clients who want to phase the job and are up front about it than 1 who tells me to design for the stars and then freaks out and goes away when the bid comes in. We're a design/ build firm, so we basically just cover costs with the design fee and get the rest of the profit on the install. If we know the client wants to do it in phases, we break down the project into sensible phases, based on what they said was most important to them, and bid each phase. It allows them to pick what they want to do cafeteria-style.

    I've found that once they see the quality of work we do and how easy and stress-free we make their end of the deal, they ALWAYS come back for the next phase as soon as they can afford it.

    laag, I completely disagree with your last statement. The more information you can give your designer, the better your relationship and the more likely the designer will create the perfect landscape for you. This includes budget and how you want to break the project down. I just did a great little front yard remodel design for under $2000 installed. Had she not been up front with her budget, we both would've walked away from the table frustrated.

    Dave

  • 20 years ago

    Spunky's perception of this industry is perfectly accurate - there are as many types of designers or design firms with different modes of operation as there are different types of clients. It is just a matter of searching for the designer/design company that is the right fit for you.

    I would also agree that you need to be as frank about your intentions and budget upfront with the prospective designer as possible.

    I've made this remark before but I can't believe it is simply a west coast phenomenon that there are designers out there that practice their trade without a direct affiliation with a design/build firm or other landscape contracting company. Surely these types of professionals work on the east coast as well? Locating this type of designer is a direct route to being able to phase in your design in segments over a period of time as budget permits. I have a list of a number of contractors I refer clients to who do this type of segmented installation as their schedule permits - often it is far easier to fit in smaller job between a couple of larger ones, when the entire crew is not absorbed. Just be aware that the peak of the season is the time when you may not get the full attention of the contracting companies - if you are able to be flexible in the timing of your install work, you should not, IMO, have any trouble finding someone to work with you on this type of project.

  • 20 years ago

    I'm not a pro, but being 3/4 of the way thru a multi-year phased project, I'll share my experience. I had no issues in finding a designer to work with me and I was up front at the start about needing to do it in phases. She did the entire design of all phases first (which I paid for). Then the cost of the installations were broken out into logical sections. I've been able to combine some phases as budget permitted.

    Obviously when phasing over multiple years, the cost of material and labour may change. My designer does a quick recalc of the costs when we are ready for the next phase. So far, the costs have never skyrocketed, but be aware that an adjustment of your original estimate is needed.

    The other item to perhaps be aware of when phasing is the availability of some material changes over time and this is another reason to be up front about phasing so you both are aware of it. I ended up waiting on the third phase as the pavers to match the previous phase were in very short supply. If I had it to do over again, I might have done the phasing differently to eliminate the possibility that what I had previously installed would not be available. I got lucky and they did come available again, but I would have been in a pickle if they hadn't.

    The only other disadvantage of phasing, for me at least, is if you are going to change your mind and need adjustments! I've already decided I want to enlarge the deck - and that is two phases away! But the advantage is that I've had enough time in the garden to know that by now, and I'm prepared to pay for the additional cost so I end up with what I want. If this had been one big job, I would have a deck I was ultimately not pleased with. It is hard sometimes, when faced with a lot of changes, to be completely sure about all of it. Phasing has allowed me to tweak the original design - which has been more costly, yes, but much more satisfying to me as an end product.

  • 20 years ago

    I've also worked with two different designers on phased projects. One did design-only, though she does regularly design and manage the whole installation, using subs. She knew upfront that I would be handling the installation and hiring of hardscape installers myself, and didn't have a problem with it.

    The second was a design-build from out of state who does design-only when asked to work out of his local area, though he does sometimes bring his own crews on location for installations. He also had no problem working with me on a layout that could be installed in phases.

  • 20 years ago

    Thank you, everyone, for your thoughtful input! It has been a great help.

    I've talked only to design/build firms because we had a wonderful experience with one in our last home, but perhaps I should seek out some individual designers to speak with as well. We're so burned out from hiring contractors and having work done in our last two homes, that the idea of "one stop shopping" is pretty appealing ;)

    Today I did get a voicemail back from one design/build firm that sounded happy to work on a phased project. So, I'll keep plugging along until I find someone who fits our needs.

  • 20 years ago

    There are several highly respected design only and design/build firms in Northern NJ that would be happy to work on a master plan that would be phased over a period of years. It isn't uncommon.

    I'm currently working on one that is planned to be implemented over 5 years and now in it's second year and the homeowner has decided to wait for fall to continue. INMO communication is the key in these types of long term projects.

  • 20 years ago

    "I've spoken to a few companies, and when I've asked about phasing, they've hesitated. In the end, it seems they'll do the front one year, and the back the next, but not break it down further than that. " by the OP.

    You can agree or disagree, but this OP is obviously not finding it easy to get a design/build to do the design. I also prefaced my response by saying "a lot of contractors" rather than all contractors. My entire post was referenced to design/build.

    A master plan does not often need to take a lot into account whether it is phased or not until it is broken down into those phases. The exception being very large elements that are necessary from the get go which would cut off access or have to be altered later.

    Something is obviously keeping design/build people from wanting to do this design. I have designed for several design/build companies and the experience that I had is reflected in the post above. It does not mean that no design/build will welcome the phasing. I'll stand by it that "a lot" won't particularly a well established reputable company in a very busy market at the busy time of the year.

  • 20 years ago

    Perhaps that's the problem laag--the OP was contacting "design/build" groups--when what she needs is a "design only" firm.

    If one goes with a design only firm--how does one find a build firm and/or contractors to fulfill the vision? I know I could find the various contractors I need here...but I've lived in the same area for 24 years. And it took me the first 15 to build up a "stable" of contractors I can trust.

    melanie

  • 20 years ago

    The local designer I worked with had a number of contractors that she worked with regularly, and she was able to recommend some if I needed them, or handle the installation if I wanted her to. In fact, I found her when the contractor I was talking to recommended hiring her to help with my hardscape plans.