yoyoma_gw

Contractor Bid w/ Allowances

18 years ago

I recently agreed to a bid by a contractor which included various allowances for flooring, countertops etc. However, when I found out about who would be fabricating the countertops, I did some research and read a bad review on GW about them. So I decided to call around a couple of places, who specialize in this material, and both sell, fabricate and install it. It turns out that in addition to getting great reviews, they are actually significantly cheaper than what I was quoted for the allowance.

When I asked whether I could use them rather than who they were going to use, they said I could, but when I agreed to the bid, they thought that I was going to use them for everything. They charge 15% on top, to manage the project, so my question is, is it normal for someone to use a different company for flooring/countertops than who they recommend/use usually? Is the 15% to manage the project always paid in this case, even if I arrange everything and take responsibily for this part? Thanks.

Comments (8)

  • 18 years ago

    You needed to negotiate managing certain subs in the initial contract. Now, you should pay 15% to the GC for all aspects under the contract unless he/she agrees to let you manage that aspect.

    But, you should have the GC earn the 15% and do all the managing of the coutertop installer. You pick out the color (or actual slab) and then have the GC deal with all the install details.

  • 18 years ago

    So I guess why that's why he wants to work with someone he's familiar with. It's probably more of a hassle for him now. Should I feel guilty about this? Or this fairly common?

  • 18 years ago

    It's your money, get what you want and as stated above, understand the g.c's 15% for overseeing and covering the workmanship. Make sure the counter people back their work as well.

  • 18 years ago

    The counter people sell the slabs too, so there could be no passing the buck between the slab seller and the fabricator/installer which I think is great. And they back their work up with a 10 year warrantee. Thanks for the info.

  • 18 years ago

    It is common for contractors to not allow a homeowner to supply important, hard to schedule, work and materials without expecting their fee to be paid although some don't mind. Usually it is a matter of how they compute their profit. Pulling something out of their work can upset the apple cart. Also, realistically, the GC will end up coordinating the work and sorting out who is responsible for errors.

    An allowance doesn't represent a bid price or a "not to exceed" price so don't take it literally and don't compare another supplier's price to it.

    Allowances represent small "Cost Plus" contracts inside of a "Fixed Price" contract. They should only be used when it is impossible to determine the material to be used at the time of contract signing and NEVER (in my humble opinion) for labor. If possible, include unit prices for labor in the contract. In the usual situation, the favored sub can give any price he wishes to the GC, even in excess of the allowance, and you would be stuck with it. Such sweetheart arrangements facilitate kick-backs to the GC cleverly disguised as discounts or refunds at a later date which is difficult to prove and prosecute. For this reason allowances are often very dangerous things and should be carefully defined or avoided.

    In this situation the best solution would be for allowance item be bid with more than one supplier and that you be able to approve the bidders list and select the winning bidder. That's the way it is handled in large projects. Of course, you would pay any amount over the low bid.

    If it is too late to include this feature in the contract you could request that your favorite sub be used and expect to pay the GC his fee. Because the sub is unknown to the GC you might save enough to pay the GC's fee. Of course, you'll never know that.

  • 18 years ago

    don't feel guilty but also understand that GW people tend to think that they know a lot, when they really don't. Many of them are trying to be General Contractors without the training or expertise to coordinate a project. So the review on the builders counter top people may not be an actual reflection of the work product but a repesentation of some yahoo trying to get his house built on his own and not understanding the correct questions to ask. Having said this, we don't work with the cheapest subs out there because you get what you pay for and the low ball prices are usually adjusted with change orders after the fact. Also....stone slabs are sold to fabricators, rarely does a fabricator own the stone yard. You may want to check your facts with the people you have been talking to.

    Good luck.

  • 18 years ago

    I am afraid to say it is commom when the original bid is altered.