How to level a concrete floor?

20 years ago

I am doing a basement remodel and need some advise about floor leveling. I already leveled 2 areas previously. One spot was a bathroom floor which the floor was raised about an inch. it wasnt to bad because I blocked off the door way and pourd in the self leveling compound. The other spot was in front of my fireplace for the hearth was releveled ablout an inch using a form. Now I need to to some how relevel an open area leading to the bedroom and in front off the fireplace. The floor does not have to be perfect because it will be coverd with carpet. But I am afraid of 2 big messes when tring to even out this transition. That self leveling compound is going to run every where. I cant really make a form because I am tring to do do maybe a 5 -6 foot area. The floor was sloped in the bathroom area originally for the drain. The floor over by the fireplace was just poor construction.

Sorry to be long winded. I just wanted to make I got all the facts straight.

Mark

Comments (5)

  • 20 years ago

    the idea of self leveling compound is that it will run everywhere until it levels out. that is how it works.

    you could mix up some concrete patch and fill in the low spot, that is what we did in a smaller area when our office was remodeled. but our area was only about 2 ft at most and less than an inch deep. i do not know if it would work on a larger area such as this, it probably would crack apart over time.

  • 20 years ago

    I thought about using concrete patch but was also worried about it cracking or chipping apart. Not to say that the self leveling compond wouldnt either but its suppose to be a thin top coat up to an inch. Anyone else got any ideas? I am trying to get this floor leveled so my buddy can start putting down the base molding.

    Mark

  • 20 years ago

    Don't know if this will work for you, but I saw a "this old house' clip and this is sort of what they said.

    They first nailed down furring strips, leveled to the finished height. Then you pour the leveler between the strips, and then when that dries you remove the furring and fill it in. I would use a float to make it even since the capillary action can make it want to rise higher than the edges. One caution (from me, not them) - make sure there are no gaps under the strips or the leveler will flow under and it will be a big mess.

    After writing this, and come to think of it, I'd just nail down furring at the edges (making a form), and pour the stuff in there. Make sure you know what the low spot is, and adjust accordingly. If there are any gaps under the furring, seal with duct tape first.

    Good luck.

  • 20 years ago

    If you don't want the hassle of nailing to concrete, then tape the wood forms at the edges to the floor with duct tape. (Don't have too much tape overlap onto the floor, maybe 1/2' or so.) When you remove it after it dries, score the tape with a utility knife first.

    Maybe it's not "by the book", but I think it should be fine.

  • 19 years ago

    Why not secure the wood strips with large blobs of morter and once this has gone off trowel some morter into any gaps between the strips and the old floor ?