Hey all, happy fourth!

Just to update,

We walked away from the bad architect with the first design/build firm, even though we loved the builder. We only paid a $2000 design fee, so it wasn't too bad. Chalk it up to education.

Then I talked to a second firm about just drawings, they came out, and wrote up a contract. (then I got busy at work again...) I found a lawyer to review the contract, but she wants to start with due diligence vetting of the principals. OK by me. She will negotiate for me, too. I am excited to have her on my team - she has decades of experience, including lots of construction contract dispute resolution.

The process in the contract at hand is

A. they draw my house,

B. draw three ideas, then pick one, and

C. take it to permit ready drawings.

Now I'm thinking I want them to

A. draw my house,

B. draw it after stage 1, and

C. draw it after stage 2.

I knew I couldn't convince them to change their process, but maybe my lawyer can find me a way to get it done my way. Maybe I need to consider other firms for this work.

Comments (3)

  • 15 years ago

    I'm not sure what you mean? Why redraw it?

    One comment i do have. For our project, which involved a fair amount of demo as well as reconfiguring as well as adding almost 2000 sq ft, our GC suggested we do floorplans but no elevations, to save time and money. I kind of figured I had enough imagination to work from a floor plan. It does save time and money.

    However, with complex tie-ins to existing, and with non standard ceilings in a few places, it ended up being a mistake. If I had to do it over again I would ask for elevations in any case where it will be non standard.

  • 15 years ago

    I used to work as a draftsman, and this is how we did it:

    1. Meet with homeowner and discuss wants and desires for the house. Collect 20% of estimated fee to begin the plans. This fee is a certain $ per square foot of estimated square footage under roof.

    2. Draw a preliminary floor plan based on this discussion. It contains dimensions for all rooms and a front elevation but little else (no electrical or plumbing). Homeowner reviews this plan and marks changes on the drawing.

    2. We make the changes the homeowner cites. If it was just some very minor tweaking, the plans are then "finished" - we put together everything it needs to get a building permit. With more major changes, we continue at the preliminary stage until the homeowner is satisfied. There is no additional cost for this stage, unless you decide that your 8000 square foot house needs to scale down to the 1350 square feet you can actually afford. At that point, it's a new plan altogether and you need to start over.

    3. You pick up one copy of your finished plans. Because these are sufficient for getting a building permit, you pay the remainder of your balance. You can still make adjustments, but no major structural changes are expected at this stage. Most of the adjustments are light switches and outlets. Once the client marks the changes, we make them and get the OK to make final copies. I think we ordered 8 or 9 sets of plans. One or two went to the permit office, you keep one, and the rest goes to the general contractor to distribute as needed to the subs.

    We would sometimes include "alternate plans" for certain areas - usually master bathrooms and kitchens - where there was room to play around with different options. These were especially helpful for indecisive clients.

    I didn't invent this system, but I thought it was a fair one. It shouldn't be that different in a design/build firm. The design part should be pretty distinct from the build part, IMO. Sure, the GC can (should?) be present at meetings to understand your expectations, but he shouldn't be telling you how to design your house.

  • 15 years ago

    That wasn't very clear, sorry. I drifted from a general update to the next decision on my mind. We are adding about 1000 square feet to the house. Stage 1 is rip off the old roof, and add a second and third floor over the garage on the south end. The third floor will extend into a storage loft along the ridge line.

    Then we stabilize, and stage 2 is a two story master bath over kitchen addition on the northeast end of the house.

    I'm not real clear on how the two stage approach affects the drawings we need or the permits. I realize the biggest risk is blowing the whole budget on stage 1.

    I guess I am resisting paying to draw extra ideas.