Understanding reasonable expectations for contractor

11 years ago

I'm mostly a lurker here, but you guys helped with my kitchen design and I've learned so much. I wanted to get some insight to help me work with my contractor and thought the wise minds on this forum could provide it.


What is reasonable to expect from my contractor re: how often they work?


Background: we're doing a BIG remodel--two bathrooms, garage, kitchen, family room, craziness. We went with the GC who was the most enthusiastic about working in our old house and the least bothered by jumping through the hoops required of our historic district. It's a small company, and the GC likes doing things himself--he lays the tile, does the wiring (he's a licensed electrician), etc. When he and his crew are here, they work like fiends, hardly taking a lunch break. The work itself looks great.


But (you knew that was coming) he's got lots of other jobs going, and days--once a whole week--go by where no one shows up. (And I'm not talking about delays waiting for permits or materials or dealing with weather. We've had to cope with all that, too, of course.) The local economy has really picked up, and everyone's building and remodeling. I think the GC's overbooked--he told he was going to be working all weekend on a commercial job.


I want to be reasonable, but I would like this done before, oh, Christmas. My husband thinks since we hired them, they should be here 5 days a week. I'm starting to think that's never gonna happen and we should reconcile ourselves to 3 or so days a week--and after all, everyone warned us it would take forever. We've never done anything like this before and don't know what we should expect--and considering we're living in chaos, it's frustrating when nothing gets done.


So what's fair? Should I tell my husband to chill out and be happy as long as we don't lose momentum entirely? Or is a come-to-Jesus meeting with the GC in order? (Or some other step in between.)


Thanks so much!

Elizabeth, who is sitting right now in a very quiet house in which no remodeling is happening

Comments (14)

  • 11 years ago

    Quick, good, cheap. Pick two. You can't have all 3. Pick your battles and be thankful that you are getting good quality work!

  • 11 years ago

    It sounds like timing wasn't addressed in your contract? Communication is the best option, otherwise what you can do at this point? Ask what the contractor what he feels is fair, and tell him what you want. Keep payments tied to accomplishments if that is possible.

  • 11 years ago
    last modified: 11 years ago

    Homechef has some really good ideas.

    We gutted our house down to studs and plywood and the job went according to the laid out time table, 6 months from the day we moved out to moving back in. The firm specializes in updating homes built in the 60's and 70's and do/did exquisite work with no complaints from us. The job was on budget - a very expensive budget.

    Only you can determine how much of a loose timetable you are comfortable with and will tolerate given their positive attributes.

    As per Sophie we had 2 out of the 3 - Quick (well, on time), Good but definitely not cheap.

  • 11 years ago

    We chose a quick and good contractor. (Not cheap for Portland at approx. $100 per square foot to renovate from total gut to rough in/ drywall.) He only does one project at a time and he was on site every day. Unless your GC has project managers helping him out, there's no way one man can manage multiple projects with the efficiency of a person who is focusing on just one job.

    If your GC is juggling multiple projects, I don't think it's possible that he'll be there every day.

    As a couple who had actually considered being our own GC (insanity) our eyes were totally opened to the work involved in that role. Our General Contractor worked his tail off for us and completed our 1100 sq ft job to our complete satisfaction in 7 weeks. I would assume that if he was working four jobs, it would have taken him four times as long to complete our project and we would have only seen him 1/4 of the time.

  • 11 years ago

    Our GC pretty much only works one job at a time. There's some overlap with the finishing up at one job and the demo at another. This is as best I can tell from talking with him, I haven't quizzed him directly about this.


    But when he did our master bathroom remodel, that's what was obviously going on. They started our job when they wrapped up the job before. Once they started they were here every day unless they were waiting on materials (minor annoyance that the GC didn't order some tile until about two weeks after I picked it and it took longer than he thought for it to come in. So we were at a standstill for a couple of days waiting on that tile). And then at the end when there were just a few last things like towel racks to install our GC came back and did those by himself while his crew worked on the next job. I think we waited two or three days for that to happen.


    I don't have any great advice to offer, but wanted to let you know that it's not some universal given that good contractors are juggling multiple jobs at the same time and always leave projects hanging for days.


    (As far as price goes he was not the high bidder on our bathroom. The high bid was $70,000. The next highest bid of five was $40,000. We didn't even consider the 70k. Our GC came in on the low end--there were three bids that were pretty might the same. We chose him based on recommendations, the ability to see in person some of his work and the feeling that he understood what we wanted. We didn't shop our upcoming kitchen and hall bath remodel; we just hired him again.)

  • 11 years ago

    Thanks for all the input. This is super helpful. Homechef, what marvelously sensible advice. I really like the idea of establishing a schedule with milestones, because then it's not me telling them how to do their jobs. I really don't want to have to say "I need you here 5 days a week at 7:30 in the morning." I'd much rather say "The garage needs to be finished by April 15." Then they figure out how to get it done. That's how *I* like to be treated--as a professional.

    The contract *was* light on milestones--there was just a general estimate of time to completion. In hindsight, a mistake, but not a fatal one.

    OK. I'm strategizing how to organize a sit-down with a very specific agenda. You're absolutely right, no one likes confrontation, me included. But without it I'm never going to have my amazing kitchen!

  • 11 years ago

    We didn't have a milestone timeline (just an estimate that our project would take 2 months), but we did have a milestone payment schedule. I'm attaching ours in case anyone finds our milestones and terms useful. Please note, I don't know if these are typical, good or bad; they're just what our GC used. And we're managing the project post-drywall.


  • PRO
    11 years ago

    elunday:

    If your contract has no timeline or no penalties, what incentive does he have to agree to them now that the deal is signed? None. Be prepared to terminate the contract or live with the delays. Either would be better than empty promises.

  • 11 years ago
    last modified: 11 years ago

    If all of the contractor's other obligations include agreed dates for completion, you will fall to the end of the line since yours does not. Since you haven't complained about it, he may feel like you are completely okay with the pace of things. Agreeing to "be happy as long as we don't lose momentum entirely," doesn't sound like a solution because your posting here shows that you are NOT exactly happy with that. Just let him know how you really feel and maybe he will be more accomodating than you expect.

    (Excellent advice all around, homechef59).

  • 11 years ago

    What I've experienced in my area is that once the specialties are finished (rough-ins, plumbing, electrical run, etc), GC always had one guy on site daily. Sometimes it was the same guy, other times a diff guy dependent upon what was being done. Would having 3 guys instead of one be faster/quicker to get the job done? Yep, but having 1 guy onsite daily kept us from experiencing what the op is currently experiencing...silence. We had milestone payments as benjebride shows, with specific dollar amounts noted.

  • 11 years ago

    The contract has completion milestones, so they don't get any more money until we make more progress, but as jellytoast says, I'm starting to wonder if I'm being pushed back because I'm being so accommodating. Just because I'm nice doesn't mean I should be a pushover!

  • 11 years ago

    Elunday, I used to have GC issues like that with the electrician working for half a day then disappear for two weeks and the GC busy somewhere else. After that first time. I refused to work with construction people unless it's on a timeline.

    You have to set the expectations with the GC from the start. All my GCs in the last 12 yrs have worked on my job solely til almost done then they slowly transition people out for the next job but there's someone there every day.

    Sit him down and have a chat. Set up a Gantt chart.

  • 11 years ago

    Yes, a Gantt Chart! Our GC did have that, but it was communicated directly to my husband so I had forgotten about it.