katiejay

Basement "capped drains" = bathroom rough in?

11 years ago

We were told we could add a bathroom rough-in to the basement. However, the description of this option shows up only as "basement capped drains." Can anyone explain this a little more?

We are wary as a realtor told us our current home had a basement bath rough-in, and not knowing what the mysterious white PVC was in the corner of the basement, we believed her. Later, a GC and master plumber were totally mystified by it and we discovered upon cutting it open that it led to a literal hole in the dirt under our foundation. GC speculated it was an alternate location for our radon system. ANYWAY - don't want to see a similar "capped drain" appear in the new basement...


Comments (6)

  • 11 years ago

    A capped drain would usually indicate a rough in for a basement. If you have it in writing then it shouldn't be an issues. If you are concerned you should ask to see the plumbing before they pour the basement floor.

  • 11 years ago

    There should also be another pipe for the sink drain which vents up and outside the home.

  • 11 years ago

    Thanks, griffinto. Sounds like as long as there are *multiple* capped pipes, it's truly a bathroom. I think I'll ask for something in writing indicating what each pipe is for as well.

  • 11 years ago

    What you described above in your post with the pipe to the dirt is not a capped drain.


    A capped drain would be a plumbing drain that is capped to prevent bad things from coming into the home. In other words it is a rough in.

  • 11 years ago

    Look at the plumbing cut in the drawings, it should be obvious.

  • 11 years ago
    last modified: 11 years ago

    Great input. Thanks. We do have a (fuzzy) copy of the plans, but I don't see anything in the basement indicating where plumbing lines may go. Perhaps we're not far enough along in the process to have those drawings yet. This is the biggest reason why I have so many questions - it seems standard procedure to choose a list of options and sign a contract before actually being served any details on the options. And, if we hadn't had such an odd experience with the capped PVC in our current basement, I probably wouldn't have any concerns at all with the promise of a rough-in.

    *I should also add that we are actually asking these questions of the sales staff, but obtaining answers has been time-consuming. We're less than the 10th sale, so I suspect they just haven't compiled the answers yet.