Hi there,

Looking for some insight into retainage. I'm an attorney, but new to TX/TX law and am not a construction attorney. I understand that I need to retain 10% of the contract amount to protect myself from mechanics' liens as this will limit my liability to that 10%. My builder wants me to release the retainage every month (30 days from the 90% payment invoice) after he provides me with lien releases from the subs. I am concerned that this doesn't protect me because although I am protected from those subs who signed the lien releases, what about the last sub?

For example, say we have a $500k contract. Retainage on the job would be $50k. If I am releasing as we go, I won't have the $50k pool to pay the painter his $25k, only the 10% on the painter's $25k ( so $2500). Or does the payment along the way reduce the total contract value/value of the work, so by the time the painter comes along I'm only responsible for a $25k portion of the work? That's the only way it makes sense to me but that doesn't seem right.

Comments (4)