Help! Should I ask contractor to redo floor??

11 years ago

We are redoing a guest bath. The floor tile is 12x24. Contractor mentioned that he will have to cut the tile on either end and I said I wanted the tile by the door a bit longer . When I came home to see the tiling it was already finished and the other end of the floor ended up with a cut tile that is only 6 inches. So the tile by thte door is 18 inches, all others 24 inches and the end is 6 inches. Picture attached. I don't like it but I don't know if I'm focusing on it too much (and it's my own fault anyway - I wasn't thinking of the other wall end). Not sure if when all done it wont be a big deal or should I ask to redo the floor? Help is appreciated


Comments (16)

  • 11 years ago

    What will be on the wall where the small tiles are? Will they even be noticable?

  • 11 years ago

    in the left hand corner there will be a vanity; down the middle and in right hand corner there won't be anything. I think about 2 tiles will be visible from the right corner to the middle. What do you think?

  • 11 years ago

    I'd rather have the "short" tile exactly where it is than have it by the door, or even split the difference. I think it's fine the way it is.

  • 11 years ago

    How wide is the tile by the doorway? Can't tell from the pic. But I think he did what you asked - he left a larger tile by the door instead of maybe a half tile on each end.

  • 11 years ago

    The one by the door end is 18 inches. The one on the other end is 6 inches. All other tiles are 24 inches. The one that is 6 inches is next to a 24 inch tile.

    yes, agree he did what I asked (left a larger tile by the door ) but after I actually saw it, I thought it seems off and would be better half tile (12 inches) on each end. But didn't know if it's worth a re-do

  • 11 years ago
    oops I meant the "short" tile is 8 inches.
  • 11 years ago

    If it is all level and there is no lippage, I would be happy and move on. Once you have everything finished this will be a non issue.

  • 11 years ago

    I agree with the others, it is only a bit noticeable now because there is nothing there. It looks fine now and will look even better once everything is in.

  • 11 years ago

    I disagree (respectfully, of course) with the opinions expressed by my fellow houzzers. It's worth a re-do if you're not happy with it, period. Now the question becomes: Who eats the cost of the re-do? Personally, I would be okay with splitting it 50-50, and I'll tell you why. You said you "wanted the tile by the door a bit longer." Longer than what?? And how much is "a bit?" I guess you can see where I'm going with this. By not giving him an actual length or ratio, you left the layout at his discretion.

    HOWEVER, he really should've known better. After all, HE's the professional!! Mastering the technical aspect of one's trade is important, obviously, but equally as important (almost) is effective client communication. (I say "almost" because, in some trades (electrical, plumbing, framing, etc.), not mastering the technical can lead to injury or death, while in others, not mastering the communication can be the killer of the relationship between pro and client (oddly layed-out floor tile hasn't killed anyone...that I know of!))

    The bottom line: Specificity (along with dry fitting the tile BEFORE laying it permanently!) is KEY in avoiding situations like this. But since what's done is done, and what's done doesn't sit well with you, accept partial responsibility (and cost) and start over! And please give us an update on the matter. ;-)

    Good luck!



  • 11 years ago
    last modified: 11 years ago

    He did what you asked, it looks good, the small tile will be hidden...you don't need to worry about this. Redoing it would result in a trivial change in my opinion, and wouldn't look any better than what you already have. If I were the contractor and you wanted me to redo it, I would, but reluctantly. And it's not unreasonable for him to expect you to bear the full cost for labor and materials, including a charge for demo-ing.

  • 11 years ago

    Trust me you will not notice it when it's done, especially since a good part of it will be covered. I remember stressing over every little thing in my reno and whether it looked right. Once furniture, etc was all in, I never noticed any of it again.

  • 11 years ago

    He did what you asked, it looks fine, and if you want something extremely specific, you would have to pay for it. That said, when there's more than one acceptable solution, I do like to be asked.

    I've trained my contractor and subs that If the question begins with "Do you care..." There is about an 80% chance that the answer is YES. Or maybe just Yes. Once in a while yes. But they come up in advance of doing the work.

  • 11 years ago

    It all depends on how much it bothers you. I don't see it as a deal breaker for me but it's not my house. If you have it redone I wouldn't expect him to cut any deals since he did as you asked.

  • 11 years ago

    Lori good thought about training the GC. I will make it clear that if there's more than one way to do something, to ask me first.

  • 11 years ago

    Yeah, maybe his last client was of the "don't bother me with the details" variety. I've heard those people exist...