Spoke to my GC yesterday,(via text) ..I was informed that the demo guy broke his ankle! Work was supposed to start this monday. I took the day off work! My question is this:

Do I continue purging the demo area of all my things? Do I wait to hear back from GC?

Comments (42)

  • 8 years ago

    Angry at who? The guy for breaking his ankle?

  • PRO
    8 years ago

    That poor contractor is probably out of work for two months. :( I would ask your GC if he expects you to wait for him to come back or if he’s securing a new contractor for your demo. These things happen. Please don’t get angry at your GC.

  • 8 years ago

    of course I am not angry at the guy for breaking his ankle ..angry that I lost out on a days pay ..I have not heard back from GC yet..More importantly..Do I continue to purge the area today? Or not waste my time on it till I hear???


  • 8 years ago

    You are going to have a heart attack if you continue to freak out at every set back and every additional cost. You should read up on Reno’s and adjust your expectations.

  • PRO
    8 years ago

    I don't know why you'd take a day off work for demo. Leave a key and go. The last thing I need on any of my jobs is a homeowner. I've thrown a few out on occasion.

  • 8 years ago
    last modified: 8 years ago

    If you hired the right GC you don’t need to take off work and babysit them. Leave them alone and let them do their jobs without hovering. Talk with them in the morning about the day’s prognosis. Inspect the work after you get home, address any issues with pictures and an email, and go to work the next day.

    Or, have your KD be your interface with the contractor, as you should already be doing. They aren’t emotional over normal construction issues.

  • PRO
    8 years ago

    What do you mean by purging? Do you mean as in getting rid of stuff or packing up the stuff you normally use, or what?

    If you mean purge as in getting rid of stuff.. go ahead and do your purge regardless on what's going on with the demo since you are planning on getting rid of that stuff anyway.

    If you mean packing up your regular stuff... start doing it anyway. No sense in putting it off when you know it needs to be done. Assume your GC will get in another demo guy for now and prepare for it. Just start with the stuff you use least, and go from there.

  • 8 years ago

    I would continue to purge and pack up because it's an exhausting process. How are you still purging and packing if demo was set to begin - wouldn't that have occurred already?

    I can't imagine that your GC isn't able to get someone to do demo for a quick replacement. It's the least skilled aspect of the whole remodeling process unlike the skilled tradespeople the GC will bring in to rebuild your kitchen.

    You should contact your GC and have him give you an adjusted time schedule with a new demo crew.

  • 8 years ago

    If work was starting on Monday, you should of had most stuff out of the kitchen and been setting up your temporary kitchen area.

    I'm on week 11 with no kitchen and have a few more weeks to go. I am tired of bbq-ing on the grill and steaming veggies in the microwave!

  • 8 years ago
    thank you to all of those giving useful information...
    criticizing that I took off work, or haven't packed up kitchen already..not helpful.
    I've not done this before ..ease up.
  • 8 years ago

    Did you take the day off to purge? If so, that was smart because packing up and purging is exhausting and takes longer than you think it will if you want to do it in an organized fashion. Make a list of everything that is going in each box - I made a list while I packed and also took photos. :-)

    You will be well ahead of the game when demo starts pretty soon. If the GC says that there is only one demo person he uses, that's pretty insane because it's unskilled and would just need supervision of the crew.

  • PRO
    8 years ago
    last modified: 8 years ago

    Not sure why the cabinets haven’t already be emptied? It’s the Saturday before demo is scheduled! That’s cutting it way too close for the amount of stuff most people need to go through.

    We do projects all the time without the homeowner having to disrupt their schedule! We’re doing one right now where they handed us the keys and left town for the whole summer while we transform half the house.

    We did have an all hands meeting where we went over the design, and the scope, with everyone in attendance. But that was at closing when we took the deposit and started the materials ordering portion of the job.

    I send them pics and updates, but I deal with the day to day interactions with keeping the subs on track with the design. As does the contractor. He has the full written specs on everything that I prepared to be the guide through the process. And that is all that is usually needed. Good design documentation, and good contractors that are willing to follow that documentation.

  • 8 years ago

    Also don't just pack up everything you have ... take the opportunity to throw out (or donate) things you never use, mismatched stuff, stuff with missing parts, expired foods, etc.

    My DH gets a bit carried away in those stores that sell spices and rubs that you buy by weight. There was a cabinet full of them, some a few years old. I was a bit ruthless in cleaning those out and will claim "remodel stress" when we put stuff back in the new kitchen :-0

  • 8 years ago
    last modified: 8 years ago

    I wish you would explain what you mean by purging. Some of the comments you don’t like are a result of people simply not knowing what you meant, and trying to guess. Purging to me means de-cluttering, but why would de-cluttering stop because the demo is delayed so maybe you meant packing up, I don’t know.

    In any case, I had the same thought when I read your OP as what Helen mentioned. It’s a shame that someone on the crew broke his ankle, but why is that delaying the demo which is an unskilled task, and even can be done with the remaining crew and perhaps just take an hour or two longer. Your OP said “the demo guy”- that doesn’t mean there was just one guy who was going to demo your kitchen, does it?

    I can’t imagine that the GC is suspending all his projects over this. I don’t want you to start feeling negative about your GC, but if you don’t hear back from him soon and with a specific date for the work to start, I would be concerned.

  • 8 years ago
    Sorry *purging* incorrect term
    still need to roll up carpet, tarp furniture, set up temp kitchen..
  • 8 years ago
    I always stay home for the important parts of the project or when I’m working with a new GC for the first day or two. Everyone chill.
  • PRO
    8 years ago

    "...the demo which is an unskilled task..."


    Yeah, on home improvement television shows. You had better have the ability to tell what's behind the wall you're removing before you bash it and you'd better have the skill to label and terminate the mechanicals inside.

  • 8 years ago

    @Bri Bosh Agreed totally. There's a lot of triggered GCs posting in this thread apparently. And crapping all over the OP for simply asking the question is no help either. These forums are supposed to be for helping people, and if you've never done a kitchen reno before then there are dozens of things you just don't know!


    @Stacy Reynolds-Krynski While it's unfortunate that his demo guy was injured the GC is still on the hook for getting the demo work completed. Certainly he deserves some additional time to set this up but he needs to provide you with an updated schedule of what will be happening when so you can plan your life around it. Remember, you're paying him for all this, this is absolutely something he needs to provide you with.

    In terms of preparing for the demo, I would continue your work, it is much more to do than you probably imagine. Even aside from moving the stuff you gotta organize and plan...divide your stuff into 2 categories, things you can't live without (plates, cutlery, cooking utensils, olive oil, basic spices, basic pots/pans, etc) and things you seldom use (roasting pans, pressure cooker, ice cream maker, etc). Store all the latter stuff in the garage or basement and think about how you will set up a functional temp kitchen while the work was going on. You'll fine tune it over time as you learn what works and what doesn't. The good news is it is summer so take advantage of your outdoor grill if you have one. I use my cast iron skillets on there to cook veggies and potatoes etc while I grill the meats. Good luck!

  • 8 years ago
    @S MacD THANK YOU for the useful advice..
    I really did fall in love with houzz, and its community. But yes being "called out" for not using correct terminology on clearing out the area?? really? Your right I SIMPLY WANTED SOME SOUND ADVICE. which some on here have given...Thank you
  • 8 years ago
    clean everything out today and go get a massage tomorrow. Don't worry, it will all work out.
  • 8 years ago

    When we remodeled our kitchen, I was actually able to move the “kitchen” into our laundry room. Bitty table (for the kids) and two kid chairs, an electric fry pan (with lid) and toaster oven, and we made use of the laundry sink. Prior to start of our demo, GC had sat down with us and we knew where they would put up zip walls (floor to ceiling wall of plastic on tension type rods) to help in containing dust etc.) everything in your demo area that is not physically attached to your house must be cleared out. If space is an issue, sometimes Pods can be rented. Good luck!

  • 8 years ago

    Oh and one more thing I thought of with regard to the temporary kitchen that helps is to simplify your meals. One pot meals like chicken and dumplings or a pan of lasagna for example will simplify your life because you'll have fewer dishes (if you're without a dishwasher this can be huge) and you'll have leftovers to put in the fridge and heat up for an easy meal. Salad fixings are great to accompany anything too, easy to prepare and healthy.

  • 8 years ago
    Our demo was pushed back a week after an issue, I’m still without a kitchen now (we are 4 weeks in), my advice, yes keep purging and cleaning, and set up a makeshift kitchen somewhere. I bought a counter microwave and set up my toaster oven in my garage by my fridge (which I moved out there from my demo’d kitchen). It’s a real pain but you get used to it after a while. I buy easy foods for my teenagers and I order delivered healthy meals (already cooked) for my husband and I. Also you don’t need to be there for demo.
  • 8 years ago

    Something else I hadn't considered also..The use of a crockpot


  • PRO
    8 years ago

    Crockpots are great! And also, if you own one and can set up outside, a propane camping stove is a nice addition to temp kitchen action.

  • 8 years ago
    was today's temps in Michigan feeling like 100 degrees how like a probably just cook on the sidewalk LOL
  • PRO
    8 years ago

    Crockpot, hot pot, electric skillet, instant pot. Even the George Forman grill...ha! The first week is the hardest. You’ll get used to it.

  • 8 years ago
    cupboards pretty emptied out just have to deal with the oak entertainment center and the ceiling fan and tarping living room furniture
  • 8 years ago

    I hope they will tent off the area in addition to you tarping the furniture. Have fun!

  • 8 years ago

    Get the throwaway crockpot liners and paper plates. I thought demo was an interesting process to watch but I don’t think I’d take off work for it. Did you plan to be there every day they work?

  • 8 years ago
    no of course I am not off wk to bbsit..
    it's just my first time having a major run out was kind of wanting to see how it's done while staying out of the way..
  • 8 years ago

    Stacy -- You'll be aghast at the construction dust that is so fine it travels through the air, particularly if you have lathe and plaster walls. Zip doors help a lot but do not contain all the dust by a mile. It settles on the walls, windows, furniture, and floors. It gets tracked from room to room. I know that sounds awful but a little preemptive work will help your sanity. First, remove your window coverings in adjacent rooms, wrap them up in plastic bags and store them away from the construction zone. It will save you a ton of money in cleaning bills. You're smart to throw covers over all of your upholstered furniture. Consider covering the beds with sheets that you can toss in the laundry. Then plan to have the entire house cleaned, including HVAC vents, when the project is finished.

    Remodeling a kitchen is kinda like being pregnant -- by the end you're miserable and asking yourself "what was I thinking!?!" But once that baby is in your life you are thrilled. So take a deep breath and keep your eye on the goal. Good luck with your project.

  • 8 years ago
    @einportlander.... thank you as soon as I get some coffee in me that's what I'll do I also put towels and blocked my vents I don't have air conditioning so it's not a problem
  • 8 years ago
    UPDATE:
    we are delayed 1 week I have to give my house key to my GC
  • PRO
    8 years ago

    Well that's not too bad at only a week. Gives you a moment to take a breath and start getting used to your temp kitchen and such.

  • 8 years ago

    In the scheme of things, a week is nothing - speaking as someone who has been dispossessed since March 26 :--).

    My initial start was delayed because I didn't know there was a 10 day wait for the State to sign off on my asbestos removal - and then another week because I had to wait for my building to shut off all the water so that I could install a way to shut off water from the building to my unit so that water wouldn't have to be shut off each time my plumbing was worked on. I had regular angle stops on toilets and sinks but because all pipes were removed, I had to have a way to completely bypass water.

  • 8 years ago
    @helen.. so I assume you're probably in a condo wow that must have been hard
  • 8 years ago

    Yes I'm in a condo and doing a full gut remodel so living in it would have been out the question. I had put off doing it for too long because packing up everything and moving out seemed overwhelming.

    I am not sure the end is in sight since the tiles I ordered now have delivery delayed until July 13 so showers can't be completed until after they are delivered and I am not sure I want to move in without showers although I could probably use a shower at a neighbor's place. The kitchen tiles wouldn't be delivered until then but since it's only the backsplash, I could have a functional kitchen before then.

    As my good friends keeps chortling at me - twice as long and three times as expensive although I think for me it's probably three times for everything.

  • 8 years ago
    hang in there Helen we're all going to make it through this
  • 8 years ago

    Hi Stacy, well now at least you have a goal to work towards. Things are going to go wrong throughout the project, there will probably be some delays, my best advice is to have an exception that you won't be done by the earliest time they quoted you, then you will be pleasantly surprised that it went better than expected. The most important thing is that your contractor takes care of things properly and keeps you informed. My recent kitchen project was my first home improvement project where I was actually around a good deal of the time they were working. I will tell you that I found excuses to go out even if I really had nothing to do because I couldn't bear watching and wondering if everything was going to come together. Overhearing them grumble when something went wrong sent me into a panic, so I headed for the hills! Your contractor should be licensed and bonded, so giving them a key should be no big issue. My project manager specifically scheduled himself to be there when any sub contractor was going to be there, so they would not need to be given a key. And my tip for surviving without my kitchen, I found the biggest inconvenience was not having a sink. I could grill, cook in my Breville oven, make coffee etc. Second was ice once they disconnected my fridge (which they kindly waited for the last possible moment to do) I totally banned everyone in my house from using real dishes or glasses, even mostly silverware. I kept one fork, knife for each of us in case we needed something sturdier. and made everyone wash their own. We had sturdy paper plates, bowls etc. I had to grit my teeth and kind of give up on recycling to avoid washing things out. I made things that required little prep: grilled chicken or steak with baked potato, microwaved or grilled corn or salad in the bag. I bought preprepared food that I just had to heat up. It wasn't the best of kitchens, but it worked, reduced my stress and made the day my sink was installed the happiest day ever! Try to relax and enjoy coming home every day to see what new has been accomplished. Good luck!

  • 8 years ago

    Our temporary kitchen was the dining room, right off the patio (since we used the grill a LOT). We washed what few dishes we used in the bathroom sink - luckily we have a lot of counter space there.

    Did you know you can cook a pizza on the grill?

    When I just HAD to use an oven, I baked at the neighbor's. It only happened a couple of times in 3 months.

    We did our own demolition, but we weren't changing walls at all, just removing cabinets and laminate countertop. DH and I finished than in a day (including moving old cabinets to the laundry room and garage).