drtthompson2014

Down Payment for Subs

7 years ago

I am at the start of my first new home construction project and running into a problem with some of my subs requesting down payments. My flooring folks and cabinet makers want 50% down payment. I assumed this was pretty standard. However, my construction loan officer says this is NOT standard, and they will not release money for work not completed. He says the bank is protecting me from the company potentially going out of business and running off with my money, then not enough left in the budget to finish the project, blah blah blah.

I found some posts about this from 2011, but wondering if things have changed. Since the housing crash I know banks have really tightened their reigns on lending, so I don't know if this is part of their strict regulation process. The loan officer says the subs should be using our builder's line of credit to start the job. Anyone know who is right here?? I just want to keep my project moving forward!!!

Comments (7)

  • 7 years ago

    Are you the general contractor/builder or do you have a builder who is hiring the subs, etc?

  • 7 years ago

    The loan officer says the subs should be using our builder's line of credit to start the job.


    Sounds like you're not the builder/gc.


    On the other hand, if you're the builder/gc, suppliers will not provide certain custom elements without a downpayment. As a licensed builder, I always had to put down 40%-50% on windows, cabinetry/counters, staircases, fabricated custom fireplaces.


    In any case, what the bank says goes. (That's why, after the first build, I self-financed.)

  • PRO
    7 years ago
    last modified: 7 years ago

    Welcome to the Wild West.

    Some lenders go the added effort of examining and qualifying your GC before approval as its their depositors regulated money being loaned back to you. My evaluation of trade contractors and suppliers is similar. Some very large const to perm lenders will advance for reasonable advances.

    A custom cabinet manufacturer is fabricating to your order, a piece of unreturnable furniture for your walls. I'm writing a check for at least 1/3. If my client has a cooperative lender who covers this (most do for me), I charge the client a little less for the use of my capital.

    When you get away from standard items in moderately priced homes, the products get more custom and advances become the norm, often lenders aren't involved. Examples are commercial type aluminum windows. Large orders of imported tile brought into the country months in advance. Slabs.

    The beginning of a project is a little early for flooring & cabinets, though.


    Added (CA):

    No advances given for trade labor. CA law restricts deposits to the max of $1K or 10%. There are more than a few retail shops unaware of these laws. It is only allowed with a very large bond. The big box stores carry these bonds and require 100% up front from consumers in many cases.


    Contractors as well as material suppliers are protected by lien laws if they notify the owner.

  • PRO
    7 years ago

    If you're a first time owner/builder, trades and suppliers have no previous relationship with you nor the expectation of any continuing relationship as they would with a builder. They're not sure they are going to get paid. A downpayment cuts that risk in half.

    As a custom builder/remodeler with a long history of on-time payments and which maintains long-term relationships with our trades, we aren't typically asked to make downpayments. The exception is where the trade partner has to make a downpayment to their supplier, for example to purchase an elevator or a special order item.

  • 7 years ago

    Where are you? I have never heard of a down payment in this area, Charlotte.

  • 7 years ago

    I’m going to order $38000 worth of custom windows, specific sizes, configurations, delivery date. My supplier, depending on their business model, wants 50% deposit with order or payment in full 10 days after delivery or 30 days after delivery to me, not after you get your draw after I have installed them with my labor, overhead, etc. After they are installed, you and SO get in a fight, stop the project, and begin divorce proceedings. The job site is vandalized and my windows are smashed. You and the GC are in a legal dispute over the basement being 30 square feet too small according to your measurements, so the GC stops work. Guess who eats those $38000 windows? Not me. I had it in my bid that I would get a 50% deposit before I would order the windows. You were told by the contractor that he would need these deposits for his subs and the bank was aware of the terms and conditions. We all agreed to them and, because you gave me money, the contract is enforceable in our state.