Can you negotiate down the purchase price when building a custom home?

Comments (19)

  • 6 years ago

    Define custom?

  • 6 years ago

    Well, I guess you could try, but the builder will most likely make up the difference some other way. It’s not like buying an existing home.

  • 6 years ago

    If it truly is a custom home then you are paying the cost of said home. You either pay this through cost plus where you see each line item plus a mark up the builder adds or a fixed price contract where you agree in advance on a fixed price for the items with specifications included but you then don't see the mark ups etc. If you want to have some control over the costs choose cost plus and then you can control the finishes. If you want to pay less you can choose cheaper flooring or a lower end cabinet etc. The builders costs will not change and are not negotiable. The only thing you have the potential to control is the choices of things you put in the home.

  • 6 years ago

    You’re not buying a commodity. its not a gallon of milk or Velveeta. It’s the premium grass fed farm raised milk made into specialty cheese, with the one of a kind bacteria that only comes from that one location. All of the single non commodity work that goes into that is why it’s $30 and not $2.

  • 6 years ago

    Yes you can - by building a less expensive floor plan, choosing less expensive finishes, etc. A custom builder (or most builders for that matter) will not negotiate with you on prices. As in - these cabinets will cost you 30k - you can’t negotiate those cabinets down to 25k. You can, however, be very clear about your budget and ask periodically, “what can I do to save 5k on this kitchen?” The builder can suggest areas to cut or downgrade.

  • 6 years ago

    It’s not so much about saving...it’s more about preventing cost overruns....make your decisions early....don’t change your mind...do ask about lead times and make sure things get ordered.....be flexible, because shlt will happen, and you will need to make decisions quickly. If you have the time, you will be a much less expensive “gofer” than anyone the builder could pay, but you have to be available and willing...and the phrase, “While we’re at it...” will cost you. During our last remodel, my husband told me he did not want to hear those words...and guess who uttered them first?

  • PRO
    6 years ago

    The way you control and manage costs for a custom house is determined by the decisions consumers make on the design and finishes of the house, while it's being designed.


    The other significant cost control phase is during construction--properly managing allowances and change orders.


    Indecision or changing your mind can be costly.

  • PRO
    6 years ago
    last modified: 6 years ago

    100% @Virgil Carter Fine Art


    OP - Understand that the willingness to negotiate on the other side is based on their experience, training and cultural background. With some contractors, their first price is their only price, with others, there is room. Do you feel lucky? (are you negotiating with #1 or #2?) The answer will reveal.


    If you have a good listener on the other side, they might understand you need it done for less and find the items to eliminate or modify to meet your goals.


  • 6 years ago

    What Virgil said.

  • 6 years ago

    I feel like this isn’t always true. Our builder and designer said the same thing and yet our two overages were framing and excavation. Pretty sure there were zero things I could have done to mitigate that. The implication that the homeowner alone is in control of keeping a budget in check is false. Site conditions, tariffs and bigger global issues, unforeseen situations do arise.

  • PRO
    6 years ago

    @AS,

    I agree with you. How the builder executes what's shown in the plans (storage of materials, wasted materials, inefficient deliveries, etc.) can have a significant effect on the construction cost of a home even without the vagaries of tariffs, price increases and unforeseen conditions.

    If you have a well-documented set of plans and a fixed-price contract, the risk of most of the above should be on the builder and not the client.

  • PRO
    6 years ago

    "...the implication that the home owner alone is in control of keeping a budget in check is false..."


    I don't think anyone has said this or inferred it.


    Certainly there may may be circumstances which are beyond anyone's control, as Charles described. And these can be a reason why a consumer may wish to reduce project expenses.


    But, as I've already said, the only way to reduce expenses on a custom house is to adjust the design and finishes, while managing allowances and change orders.

  • 6 years ago

    All advice has been homeowner specific in this thread for the most part. I commented specifically to provide the alternate perspective that even with extensive effort on the home owners part it was often hard to stay in budget. The fact that almost all advice here is about what the home owner can do and very little was about preparedness for unforeseen situations is part of what people end up over budget. Having it in your mind that something might happen and being financially prepared and having a plan for a what if is important. That’s all.

  • PRO
    6 years ago

    This is called a "contingency fund", and is always an advisable strategy.


    Unfirtunately, it is an additive amount, over and above the amount needed for the construction contract.


    It is not a strategy to reduce the construction sum, as the OP asked about.

  • 6 years ago

    It is part of having a good awareness of costs overall and making sure you can afford a build. It is important to discuss as well. Correct it isn’t a cost saving measure explicitly but failing to consider the need for it sure can cost a lot.

  • PRO
    6 years ago

    Had one client get within $360 of contract amount. Its possible.

  • PRO
    6 years ago
    last modified: 6 years ago

    If a high degree of cost control is desired, then the project needs to make the investment in comprehensive design services. That’s more than a well specified set of architectural plans. That’s also a well specified set of interior designs and finish schedules. You pick out everything in advance, as far as is humanly possible. Remain fixed on specific products, and remain versatile enough to shift should those products become unavailable.

    Or you buy a spec house, not a custom house.

  • PRO
    6 years ago

    And woe be to the consumer who says, "As long as we're doing this, let's just add this and that..."