Building a home before the pandemic

5 years ago

So we started to build our home before pandemic starts, approximately 9 months before march 2020 signed the contract, the contract stated 12-14 months to finish, loan end at 18 months. We are currently at 25 months now, builders said because the short of labor and materials, he keep pushing closing date putting us paying the loan indefinitely, and yes the bank us willing to extend the loan because of covid. It has been the most stressful years because we are living with boxes. When you were planned to move and the construction was planned to be done more than a year ago, the last stage of construction took another 15 months and still not finish. Builder insisted if we want the construction to be “on time,” meaning in a faster pace than now, we have to pay a ”premium” price because the pandemic has make shortage of labor. But then the house was finished 3/4 before the pandemic even started, the 1/4 took him the extra 15 months and still on going. Even it was called a Custom home, this builder has not fulfilled what we want most of the times, but instead install things that we didnt want and later make us pay extra to change it or we just have to stick what he give us. For example, we ask for a borders on tiles in the master bath, the technician installs the tiles when we were there without the present of the builder. it was all installed when we get there, and we ask the tech to contact the builder because there should be a border. the tech said there were no instruction and the only thing he has was the tile inside the house in each room. the builder then said he will arrange someone to come back and see if they can dig out some to add a border. never did and just let go plus he said everything else will delay the process of the house making me and my husband just let go. what do you think about paying premium, shall we keep waiting, or whats our options? we have enough talks with the builder and he is never a on time person who shows up on time or he will let you know the last 10 min before we meet he can not make it. There are many tiny things that he said but never fufill what we have ask for, again, it was a nightmare more than anything else. but we dont feel right that we have to pay extra to get things done, and not to mention all of the upgrades prices are only listed with one handwritten price, so when you ask for more details. but long story short, we do want to get out of this nightmare but just dont feel right that we have to pay extra for something that was suppose to be done a long time ago!

Comments (14)

  • 5 years ago

    Do you have a contract? What does the contract say about changes, delays, etc?

  • 5 years ago

    Yes the contract say 12-14 months but anything such as natural diaster or similar can be excluded, hence the pandemic is giving the reasons for him not be able to move forward for the 1/4 of the construction and took another 15 months and more! we can also find an attorney but he has said the best way is to work out with builder because it could take more times and expense!

  • 5 years ago

    This sounds like a horrible situation.


    If the exact specifications for tiling the bathroom are not spelled out by the architect/designer as part of the contract you are basically at the mercy of the builder.


  • 5 years ago

    unfortunately not, because the contract didnt specify but only mention upgrade, and we did upgrade on tiles too! thank you anyways!

  • 5 years ago

    You have my sympathy; this sounds horrible!


    How much of a premium do they want to speed things up? Would it be a separate contract? Could you penalize them if they agreed to finish by a certain date for extra money and then they didn't finish? Would it be worth it even if it seems like they are trying to force you to pay more? Maybe. I would ask for numbers and then also what guarantees you might get. If there aren't strong protections (and have it checked by a lawyer to be sure), it probably wouldn't be worth it. But if it gets it done finally, maybe it is. So sorry!

  • PRO
    5 years ago
    last modified: 5 years ago

    Contract, schmontract. This is all about who is in a position of strength. He is, you aren't.

  • 5 years ago

    Sadly you just picked a lousy builder and covid gave him an excuse to be even worse. I'll bet that he has a whole bunch of new projects started that have given him money and the older projects are getting dragged along when he has time to get to them.

    I would just push to get the house finished, end the relationship with the builder and move on with your life. You might not get exactly what you wanted, but you can always make some changes in a few years. We are building right through covid and should get done in 13 months, which is end of this year.

  • 5 years ago
    last modified: 5 years ago

    Prices have gone way up since your contract was written. He is losing money. You do not want a builder who is losing money. You want him to make money on your job. A contract price adjustment due to prices increases would be fair. It would result in him being more interested in completion as well. A builder who is losing money on your job has an incentive to cut invisible costs that are more important than visible ones. That is a bad position for you to be in.

    Adding a border to tile, or any other change, always costs extra, and should require a change order. If you’ve been making changes all along, you may get a big surprise bill for those changes. You cannot request changes straight from the subs. You must go through the GC so he can charge that extra. This needs straightening out immediately, and an accounting for those changes you requested needs to happen. You cannot expect to not pay for changes. You don’t want to be blindsided with a big bill just before closing.

  • 5 years ago

    @User, the OP didn't say if this was a fixed price contract or cost plus, so we don't know if the builder is actually losing money. I'm sure it wasn't a well defined and detailed contract to begin with!

  • 5 years ago

    Thank you all for replying! we went to a last minute vacation with kids before school start. yes we understand prices had gone way up since the contract was signed, but this builder is not the best to manage his time, plus he is the only one person we deal with thru the whole process. it takes him at least one to two week to response a question. i would love to expect something from him in details such as a price and expected time to finish so that we can close. however he never specify what is there to finish in the house for us leaving us so confused if we have to pay him more on painting to speed up and then he can ask more money for other things? my other concern is our construction loan, it has specify in the contract that he suppose to finish in 18 months, (there is a seperate contract between builder and us that needs to finish in 14 months) other than natural acts, i suppose covid is the cause but even the construction loan manager said it can be EXTENDED indefinitely because of covid because we are at 26 months now! we are so lost but hiring an attorney will take even more stress to go thru this mess!

  • 5 years ago

    If you have tried to talk to the builder and nothing has come of it, then maybe your builder needs to be prodded a bit and a nicely worded letter from a lawyer might be worth a try. Do you really have anything to lose?


    I just realized no one asked you a very critical question.

    Do you own the lot and contracted the builder to build a house on your lot or does the builder own the lot?

  • 5 years ago

    I sympathize. We are in a similar situation. We waited for lowered prices instead of paying a price difference for lumber and other materials. The builder owns the lot. We are still at mercy of material substitutions. Home is still being framed.


    Good luck to all of us, buyers and builders alike, in completing projects during these difficult times.

  • 5 years ago

    We own the lot, hence have been paying non homestead property taxes for couple years now plus the HOA fees. Can’t believe the bank is giving extensions indefinitly, especially meaning there is no point of signing the contract as it has been past its said period.

  • 5 years ago

    You need to talk to a construction lawyer to see what your options are and to possibly get the lawyer to prod the builder.