Delay due to electrical panel backorder.
Will be approximately 20 weeks.
Does it make sense for the company to clean the pool (before plaster and pebble finsh), when it will be full of ground water for almost 20 weeks? And if they clean and do the plaster/pebble finish, is it ok for the pebble finish to sit in ground water for almost 20 weeks?
Pool is in Florida, ground water is 2 feet deep without rain, going into rainy season.
Just want to protect our investment. Pool was supposed to be done in 12-14 weeks, will be 40 weeks + now.