I had a contractor in to give me an estimate on some handyman work. It was about $4000 worth of work, none of the materials expensive at all, and the estimate was $8000. I figured he padded it a bit to negotiate, but he also wanted 1/3 up front, 1/3 half way through and the rest before the punchlist. I told him no, absolutely not. He also scratched my wood floor kicking my kitty litter pan across the floor (bad), where it was temporarily located.

He came back with an offer for us to pay half, halfway through, then another half at the end, after the punchlist.

He's a mid-size operator, and is in the pocket of a rival RE agent (to mine).

He's still trying to get our account (no idea why - I'm hearing conflicting stories from contractors, lots of work going around, nothing much happening, but I'm not seeing the work trucks). I told him no, because the bottom line is that I just don't think he was being forthright with us. He checked me out with the RE agent, so he should have known what sorts of people we are (we pay well and we're super easy going).

Am I right to kick him to the curb? Oh, and this is kitchen work, by the way. :)

Comments (9)

  • 17 years ago

    If you have a bad feeling this early...definitely look elsewhere. 95% chance that if you don't, you'll live to regret it. Who asks for full payment before punch list??? Even if he changed on that, I think it's a VERY bad sign.

    Always trust your gut.

  • 17 years ago

    1. His estimate is too high
    2. He doesn't show respect for your home (kicking my kitty litter pan across the floor whether it scratched your floor or not -- why did he do that? What if the litter or other contents had scattered onto the floor? Would he have cleaned that up?)
    3. His terms are not acceptable
    4. You don't think he was being forthright (lack of trust)

    How much more reason than that do you need to move on? Any one of those would be enough for me to say no.

  • 17 years ago

    Get some other bids, but be prepared to pay anywhere from 1/4,
    to 1/3 to 1/2 up front at the start of the job.......

    Do you build a house with nothing down and no money of your own up front?

    Any customer of mine that is not willing to put THEIR money up fromt
    gets the "Hey it's been REAL nice visiting with ya, but I think my NEXT
    available date will be on February 30th of NEXT year.... See Ya"
    Does that make sense? People that WANT something, but do not want
    to front ANY of their money - don't need 'em... don't want 'em....
    There's PLENTY of folks out there that understand how the "drill" is done..
    I have been working with them since 1978...... Not trying to bust your
    chops on the money issue - but the old saying is true - "IF you've
    got the GREEN - I'll be on the SCENE"

    Clearly the guy that came to your house and kicked Fluffy's Litter box
    is a bit "lacking" in his interpersonal skills. Get some more bids....

    but be prepared for a gut check when it comes to paying SOMETHING
    up front... IMHO only idiots or guys that don't know any better
    (ie; NO prior business or trade experience) will work for zero money up front,
    and that is NOT how I roll......

    just my .02 cents worth as a contractor for over 31 years

    kevin

  • 17 years ago

    I was really happy to pay some money up front. My RE agent told me that I shouldn't pay anything - it's just not the way things are done around here. She said I could offer to pay for materials and the pay for the skilled laborers. I offered that. I can't see paying $4,000 at the end of one week, even if the job isn't really half way done when the job shouldn't cost that much in the first place.

    I was even willing to pay the 1/3 up front, but not anything else until after the punchlist, but the RE agent said, 'oh no you don't.'

  • 17 years ago

    Out here in CA, contractors can only charge a minimal up front fee, like $100. Then they can progress bill for work performed.

    Like the pool, I paid nothing until there was gunite shell (this after hole dug, steel cage built, plumbing pipes laid, and electrical. All that happened, 3 weeks of work then I made the 1/3 payment.

    For the kitchen and landscaping contractors I paid nothing until the job was done and cleaned up. Then payment was due then. Same with the fabricators.

    It's just how it's done here. It seems weird to put down money before the service is started.

  • 17 years ago

    Well, I wouldn't be so certain that your job is $4K if his estimate was $8K. There are very few contractors out there that stupid. If he has experience, he might come in 20% high, but that's probably about it. Different regions have different prices for the same work, and some places, the price IS double what it would be moving from elsewhere. You need to get more estimates to determine what is a fair quote for the work you're proposing. It may be a lot more than you think And, 30% up front would be about standard for most contractors. That allows them to begin getting the materials for your job. Then 1/3 at about half done, and the last third when things are complete.

  • 17 years ago

    i would be pretty surprised in this market that you would get a price from a contractor who wanted work that was double the price

    doesn't make sense

    not in this market slowdown for contractors

  • 17 years ago

    I definitely agree that you need more bids. I actually wouldn't consider hiring a contractor without at least three bids. He still may be too high. Or he might be right on. You won't know till you get something to compare it to.

    However, the lack of trust is a big problem. How do you let someone you don't trust work in your home? Also the kitty litter thing. I just don't get that.

    As for the terms, 1/3 up front, 1/3 half way through and the rest before the punchlist -- I think it's pretty standard to withhold 10% till after the punchlist is completed. pay half, halfway through, then another half at the end, after the punchlist. These terms might be acceptable though.

    But again, it comes back to trust. I had a great contractor and one of his big things was trust. He felt it was important that I trust him from beginning to end. And he more than earned that trust. There were some GCs I interviewed that I didn't trust at all. I don't care what their price/terms were, I wouldn't have hired them. They might have been a-ok guys, but not for my job.

  • 17 years ago

    Don't hire so you won't have to fire.
    And put your guilt aside.
    Even if you have to pay more for the next
    guy it will be someone who you trust this
    early in the deal.

    I'll bet even your kitty was offended. :)