pool build - 'what to watch for'

16 years ago

Our gunite pool build is underway (20 x 40 rectangular pool w/auto cover). Hole is dug, gravel down, plumbing done. Gunnite shoot will be next week. Are there are couple of critical things that we should be looking for to make sure all will be well right away and down the road? (e.g. we'll watch the gunnite shoot to ensure no rebound is used). Things people wished they had known? Contractor seems good, just looking for some a little advice given we want to get this right.

Comments (10)

  • 16 years ago
    last modified: 11 years ago

    Nearing the completion of our pool now, with decking, and plaster to go I would watch the following:

    1. Soil analysis ? Is it needed? Ask.
    2. Level? we are on a sloped grade, first forms for gunite shoot were not level, it looked off, I asked them to shoot the level again, sure enough I was right.
    3. Rebar? 12, 10, or 8 inch on centers? This is how big a square the rebar makes, should be in your contract. Ours is 10 on centers, they were doing 12, they had to correct it.
    4. Plumbing locations - are returns, jets and skimmers per plan? EASY to fix now, a huge mess to fix later.
    5. Depth, confirm that the dig is the correct depth before gunite, they had to dig out a 7ft x 7ft square of ours, it was sloped incorrectly.
    6. Light placement, is it per plan? --Now is the time to make sure.
    7. Sunshelf / steps placement, if steel and gunite, are they put in place per plan? They would have left out our spa step if I had not been there.
    8. Gunite thickness, check your contract make sure its all per plan.
    9. Physically look at the plan the gunite supervisor is holding in his hand. If any changes have been made to your pool since day 1 of the contract signing, he MAY not have an updated copy of the pool plan, make sure, its much easier to fix before the shoot than after.

    10. BE HOME! when they shoot the gunite so you can look for any monkey business. Don't be afraid to point out potential problems or concerns, you are paying for this and have to live with it, they don't.

    Not to sound like an alarmist, just giving my 2 cents as a newbie who just went through the process. I wish you the best.

  • 16 years ago
    last modified: 11 years ago

    Great - very helpful; thanks for taking the time to give us a detailed response, and so quickly!

  • 16 years ago
    last modified: 11 years ago

    Good luck getting them to shovel out throw out the rebound. That seems to be a selling point that some builders use to try and sell pools. Our PB said they did that as well, they did not.... When I asked one of the gunite guys he said "the stupid salesman say that, we never take it out, just step on it and push it into the floor bottom". I was concerned some but the shell has a lifetime warranty so I hope it hold up. Seems that it is pretty common practice in my area to just leave the rebound in the bottom, talked to a few field managers with other PB and they said the same thing, they leave most of it in.

    Be sure to double check all major measurements before and after gunite, length width, depth, rebar spacing and size. Also if you are getting umbrella sleeves put in make sure you personally tell the guys where you want them in the deck. Our guys put two of them in the coping, not where we wanted them so they had to put 3 more in around the pool in the decking next to the coping, so we have 5 sleeves all around the pool.

    Feed your sub's! Alittle food and drink goes along way in getting a great job done. If it's friday or saturday a case of beer at the end of the day say's "you guys are the greatest".

  • 16 years ago
    last modified: 11 years ago

    I can tell you things that went wrong with my build. I hired one of the pool builders who's been around forever, they run several crews, and they came with great recommendations from around the area.

    The hole was dug in the correct area, but a little too small. We called them on it and they corrected.

    When they set the rim boards to define the beam elevation, I thought they dug too shallow and I thought the elevation looked a little high. I asked a couple of times and they measured, etc, told me it was fine. I'm using my eyeball, they had transits. I figured I just didn't know how the final shell would look compared to the forms, and I was misinterpreting things. Well, I was right, The pool was just over 5" too high.

    Rebar and all was fine, but when shooting the shell they set two of the pool return outlets a few feet on either side of the skimmer. Didn't match with the plans and made no sense circulation-wise, nothing would ever make it into the surface skimmer. I pointed it out, they told me too late the shell is being shot and it is what it is. I made them place holes in the proper locations.

    Waterline tile was supposed to be a tight grained gray slate, appropriate for freeze-thaw. During the design phase we described the look we were going for and the salesman offered the slate. It was in the contract and we even provided the slate since they said they later said they couldn't source any. Even though we has the boxes of slate out by the pool, they instead installed bright blue glazed ceramic 2" tiles. Called the owner, he said well it's up, you have to leave it. I took a shovel and scraped it all off. We got the slate installed.

    Equipment pad. Pool area was to be surrounded by a fence, the equipment pad was going to be on the non-pool side of the fence, roughly 3' from the fence line. Pad location was on the plans and properly staked out on the ground. when it came time to set the pad and equipment, they pulled the stakes for the pad formwork, slid everything over right next to the pool patio, and plumbed and installed the equipment. This put the equipment right on the pool fenceline. The sad thing is the fence post holes were already staked out, so it was ridiculously obvious that the equipment was on the fence line. Had them cut the pipe, move everything over, and repipe. Lunacy. Or so I thought.

    My pool location was our old vegetable garden location. They removed about 30 yards of topsoil/compost from the garden area and piled it on the other side of my driveway where we asked them to. I came home from work one day to find the pool ready for the slab to be poured around its perimeter. The subsoil in the area around the pool was beautifully plate compacted, the welded-wire mesh laid out. Subsoil never looked so good. Wow, it felt good to see things getting close to the end. Until I looked over and saw that a huge amount of the compost pile was missing.

    I got a shovel and scraped away some of the subsoil, underneath a couple of inches of subsoil I found all my compost. They had backfilled around three-quarters of the pool beam with compost, some areas down to 18" deep. They filled the plumbing trenches with compost, and over about a third of the area that was to be pool patio, there was a several inch thick layer of compost underneath the subsoil.

    Called the pool owner. He went ballistic over the phone that his guys would be so stupid to do something like that. Then called me back to tell me that I was wrong, he spoke to his crew and his crew said they didn't do it. He added that even if they did, I'd probably sell the house within a few years so it'd be the next guys problem.

    I fired them. Finally.

    Finished the pool surround area myself. Dug out the compost and refilled, did the 1800 sqft slab and tiles on the slab, did the pool fence, pergola, stonewalls, etc. All looks nice. Been several years and thankfully all is well mechanically with the pool. I do have one rust spot on the floor of the shell, I think it's rebar that was too close to the surface of the shell and and plaster that was possibly applied a little too thin in that location? Not sure. Oh well.

    I later talked to a couple of people who gave me the thumbs up references about this company. They both then admitted difficulty during their builds. Sigh. Nice references, eh?

    So...take nothing for granted during the selling phase. Everything agreed to should be written down. Any amendments to the boilerplate contract should be initialed by both parties.

    Then just follow up as things progress. Keep a dialogue going with the site supervisor. Any inches that you give could turn into feet later on. Don't bow to timeline pressure that "if we don't do it now it'll be a week before we get back here". Wait the week to get the pool you want.

    Didn't mean for this to be a gripe list. Just encouragement to keep your eyes open.

  • 16 years ago
    last modified: 11 years ago

    As many of you that have been reading know we had an awful experience with our PB. We had arbitration last week and are waiting for the outcome. We are not confident that the outcome will be good as the PB was very experienced in how to defend himself and we got the feeling that we had lost before the meeting began. but, that is another story.

    We also have an auto cover and it has been the source of much trouble. The person that installs your cover is very important. Ours did everything wrong. Where do you live? who is your PB? What brand of cover are you getting? Do you have a salt pool?

    We have salt and they put in iron brackets. Four months later they are all rusting, it is costing us $2500 to replace them as the cover box was shot way too big and the brackets had to be custom made. If you have a cover box be sure to find out if your cover stones have been ordered. this is a special order item in most places. Our PB put in stones that were twice as thick as the coping and three feet wide. The cover people i hired to clean up the mess could not move the stones....$1500 was the cost to replace them including labor and having the original stones disposed of.

    I think with a pool (and I must apologize here to all the fantastic PBs who contribute to this site and do great work) it is buyer beware. There are some really bad PB out there that ruin it for the great ones.

    Keep your eyes open and ask lots of questions and make sure you are comfortable with the answers.

  • 16 years ago
    last modified: 11 years ago

    Sharon - that sounds awful; i hope the arbitration comes out ok.

    We are getting the cover from coverpools; our pool will also have salt, so you have made me nervous. what kind of brackets did you get to avoid the rust? also, what size should the cover stones be?

    Really appreciate your advice!

  • 16 years ago
    last modified: 11 years ago

    According to the expert we have now hired to fix and replace the mess: cover box should be 14 inches deep, this is big enough and will fit standard brackets. brackets should be either stainless steel or aluminum. Stainless is best but more expensive. As it has been stated in many places on this site, Iron and a salt system are not a good combination. Make sure you meet your cover installer and I would suggest you visit some of the pools he has installed on and find out if they are satisfied with his follow up service. You should have one year of free service on the cover so you will have to deal with him. Also the cover may need adjustment and you want to be sure he will come right out to take care of it or you may have trouble opening and closing your cover. At one point we had to jam a rod into the side of the cover to force it to open. Also make sure the electrician and the cover people communicate. Just a few days ago we found that the box used to open the cover did not have the proper gasket and that would have blown out the control. My husband fixed it. It will be much better to make sure things are done correctly in the first place.

  • 16 years ago
    last modified: 11 years ago

    Thanks - you are making me nervous! Our PB is going to install the cover; he has done them before - asking for a year of service is great idea; we will also look into stainless steel for the brackets. That's great that your husband was able to fix it - hope to avoid that!

    Who makes your pool cover?

  • 16 years ago
    last modified: 11 years ago

    My suggestions? TAKE PICTURES! Get good pictures of the rebar & plumbing prior to gunite, then take pictures as they do the gunite fill. Lots of pictures. We are a year into our build, still trying to find out where certain things are and why some things aren't working, and why we are losing so much water.

  • 16 years ago
    last modified: 11 years ago

    Our cover is from Automatic Pool Covers. Our gripe is not with them. They gave us a credit for $500 for the new brackets because they felt so bad. They have tried to help, but the installation is the problem as well as choices of material the local dealer and PB used that were not from the manufacturer. The cover was installed by a local dealer and that is the source of the trouble. My husband was not able to fix the cover, he was just able to pry it open so we could use the pool. He had to pry it each time we opened it. We had a dealer from a neighboring state come and fix the cover at our own expense that involved many steps, Our new brackets are on order and once they are in we should be good to go.

    It sounds like your PB is the dealer for the cover. That is good as you will have one less person to deal with. I would go see a cover he has put in and talk to the homeowners and ask if they have had any issues. Also ask how long he has been putting in covers and talk to someone that has had one of his for at least 4 years and see if all is going well.