Software
Houzz Logo Print
jrtgal_gw

Contractor not responding

18 years ago

Hello everyone. I am hoping someone might have a word of advice for my situation. I began a home remodel beginning of July, and I am contracting the work myself. Per architect approved plans the job involves knocking out a wall, creating a new cathedral ceiling for kitchen/living room, and remodel of kitchen and 2 baths. The job is being done in 2 phases, with the master bath to be left untouched until the other bath is functional.

I hired a single contractor to do demo, framing, drywall, hot mop, and finish carpentry. I chose this contractor as he showed me good framing work in the past, was willing to work on these terms (he is a GC), and offered a good price.

Everything has gone pretty well up until last week. The contractor's crew was hard working and did nice work, even complimated by the inspector. My only complaints up until then is that this contractor was not great about returning calls and was lax in supplying estimates for additional work I was interested in using him for. He always had an excuse (my computer broke down, my phone reception was NG at other job site, blah blah blah). And every week there was at least one day when his guys just did not show up unexplained. I was willing to deal with that as things were still moving along.

A week and a half ago we passed our inspection for rough in (woo hoo), and they started the insulation and drywall 2 days later. Then, starting a week ago, both of the phone numbers I have for this contractor had messages that "the subscriber has requested that this phone not accept incoming calls". I do have an email address for him so I emailed him. Got an email back from him once last week and it sounded like they would be back to work end of the week but no one showed up. I emailed him with a request to discuss schedule and when they would be back to work as I have to reschedule my other contractors (tile, flooring, paint, etc.) I have not heard back from him. I can find drywall and carpentry contractors to finish his part of the job, however I do have a contract with this guy. So, how do I proceed? Is it OK legally to break a contract under these circumstances? Many thanks in advance.

Comments (5)

  • 18 years ago

    Any properly written construction contract has a section describing when the contractor's failure to perform is grounds for termination of the contract and describes the procedure to be followed to do that. If your contractor wrote the contract it probably doesn't have those provisions (for obvious reasons) and you would need to ask a lawyer how to proceed.

  • 18 years ago

    thanks for responding mightyanvil.

  • 18 years ago

    The process would likely include mailing the GC a letter saying something like, "I have tried to contact you about completing the work you contracted to do. If I do not hear from you by xx date with your plan for completion (or if the work is not complete by xx date), then I will assume that you have abandoned the contract, retain the amounts I have not yet paid you, and pay someone else to complete the work."

    Obviously there's more legalese to use, but that's the gist of what you need to notify him about. Then you give him the xx days and move on, documenting to him what you've done. As mightyanvil said, cover this with a lawyer to make sure you've done it right.

  • 18 years ago

    amazingly his guys showed up this morning. Thanks though weedy that was my thought as well

  • 18 years ago

    When several projects are running concurrently, sometimes there are delays at one location. Sounds kind of normal, with the exception of the blocked incoming calls.

    Though I've never done it, I often want to nix the phone when I'm up to my neck in alligators. Recently I lost a job and had a nice block of time to give a client who wanted some work done in short order, but then dawdled for weeks. Now that I have no time, he wants new quotes and basically to get it going. That's kind of how it goes, though.