annkh_nd

Figuring out the schedule

13 years ago

I have an install date from my cabinet maker! He will be ready to start the install on July 15. We'll be on vacation the week before, so I need to have everything else ready before we leave.

I'm my own GC, so I'm doing my best to develop a realistic timeline. We'll be tearing out old cabinets, an electrician will move some outlets and add some outlets, a contractor friend will cut out the stud where the range hood vent will go (and build a header), and patch drywall; the flooring guy will prep the floor for tile; we will paint the ceiling and walls ourselves.

By "we" I mean my DH, my 18-yr-old son, and me. DH and I work full-time, so will be working on the house part-time. The kitchen is 10' x 10'.

I've got a call in to the electrician to find out how much time he'll need. Everything else I'm trying to estimate conservatively, and put in the right order.

- Empty cabinets: 2 days (much can be done ahead of time)
- remove cabinets: 2 days
- electrical (TBD)
- flooring prep: 2 days?
- drywall patch/tape/mud/texture: 3 days (allow dry time between steps)
- more drywall cure time: 1 - 2 days
- paint ceiling and walls, 2 coats: 2 days

Some things can overlap, like floor prep and drywall cure, if I'm lucky, but I'm not counting on being lucky. I'm looking at a minimum of 2 weeks of work (by us and others). Does this sound overly optimistic? I'm thinking that if I allow 3 weeks, I'll have a little cushion. Am I missing anything?

Comments (12)

  • 13 years ago

    Ann I am not sure how to compare this because I am doing a bigger reno but not by much. The kitchen is 13 X 13. I will be getting flooring installed in the living room and dining room and that will add some time.

    Reno starts this coming Monday. Soffit and cabs are coming out Monday and plumber is running a water line to the other side of the kitchen. Electrician comes in Tuesday and does the new lighting and circuit for the oven, and adding some new outlets. The following Tuesday they should be ready for the flooring contractor. Hopefully the following Monday they can start to install the cabinets. My kd says we should be finished by mid June. That seems like a long time to me but that is his estimate. I hope this helps but who knows if there will be glitches along the way. Good luck to you!!!

  • 13 years ago

    It might be a little optimistic, but in general it looks similar to the schedule we used (though our remodel stretched out a lot because our only solid work days were weekends, so there were some gaps). Definitely electrical before drywall since you'll inevitably have holes to patch. We have plaster which is another beast, but because it was done during very wet weather, our cure time was a lot longer than typical. Not sure if drywall can be affected by weather too, but if so, build in a buffer if you live somewhere where it might rain. Flooring prep took us a long time (old wood subfloor with tile/tar coming off) but if you have a professional doing it, probably will be much faster (and use whatever timeframe they give you). We did flooring after plaster, I think, because there would be a lot of people traipsing over it making a mess to do the plaster (but of course you can always cover it). Do you have any plumbing work to be done? How about permit inspections that will need to be scheduled at key points in the process? Add a little extra for both of those in case schedules slip.

    Remember that if you're working full-time and planning some of this work for the evenings, you need to plan around daylight hours (and/or get work lights and extension cords) if you want to work while electrical work is underway if the power might be off. Since you have the vacation constraint, I'd also add a week to whatever your most conservative estimate is, just to be on the safe side. (More if this is an old house and you're opening walls!) Good luck!

  • 13 years ago

    We also played the part of GC. Our timeline went like this:
    - remove cabinets and set up kitchen in the LR- 2 days
    - remove two layers of vinyl flooring and one million staples- one week
    - remove much of the drywall- most of walls and all of ceiling- 1 week
    - electrical(DH at night and weekends)- 9 ceiling cans, two pendants and light over table plus UCL'S- 2 weeks
    - HVAC- adding venting for range hood liner- 1 day
    - Drywall- 1 week (hired out)
    - 2 coats of drywall paint for new drywall- ceilings and walls- 2 days
    - 2 coats of regular paint- ceilings and walls- 4 days
    - hardwood floor installation- one week because they had to sand down high spots in our subfloor and nail gun broke halfway through
    - cabinet installation- 1 day

    Painting took way longer than expected as did floor installation. Life gets in the way too and some days are not as productive as expected. We started demo at the end of August and cabinets were installed November 8. We did have some down time in there but the break was nice. We were also working on a powder room and living room/dining room ceiling texture removal.

    If you can double your time estimate, do it. Less stress at the end.

  • 13 years ago

    Thanks, all!

    No plumbing, which helps. We're not taking out any walls. We're adding some outlets, and moving some others, so drywall patching comes after. Current floor is sheet vinyl, original to house (25 years old). Footprint of new cabinets is different, so I'm planning for it to come out, but I'll ultimately leave that up to the flooring guy.

    DH and I will be working full-time. He has regular hours (8 to 5); I'll be working 3 pm - 11 pm the two weeks I've slated for this work (including weekends). That allows me to work on the kitchen during the day, and DH can work in the evenings. Our 18-yr-old son will be helping both of us, as needed. I'll also be home most of the time when subs are in the house.

    I've painted these walls and ceiling before - I'm confident I can get 2 coats done in a day (without cabinets to edge around, it should go fast!). I'm planning 1 day for the ceiling and 1 day for the walls.

    I'm using the last week before our vacation, as well as the weekend before the cabinet install, as a cushion. If everything works out with the subs,

  • 13 years ago

    With you both working full time? Better double your time estimates. The electrical especially can bite you big time if your service is marginal. What size panel do you have? If it's not a modern 200 amp panel, you will find it really difficult to do all of the code required modern kitchen circuits without upgrading the home's whole service or perhaps installing a subpanel.

  • 13 years ago

    Thanks, Hollysprings, I'll check my panel tonight. The house is 25 years old. My electrician will be replacing all the outlets in the kitchen, adding 2 new outlets in a cabinet for chargers, moving the outlet for the electric range, and adding wiring for UCL (LEDs).

    I have a call in to him today - I'll get a time estimate.

    Since I'm hiring out the electrical, flooring, and drywall, my work (tearout and painting) will be at the beginning and the end. It shouldn't matter if I'm working or not.

  • 13 years ago

    Its tough to go on vacation in the middle of a reno. It's tough to live 2 hours away! Best if you can be on site to supervise.
    Suzi

  • 13 years ago

    I'm planning to have all the site prep completed before we leave, and cabinet installation will begin after we get home.

    It will be nice to be on vacation, recovering from a whirlwind few weeks, and with a functional kitchen!

  • 13 years ago

    If you haven't already, read through my "It's time!..." Thread. I'm in the middle if our roughly 12x12 plus powder room remodel and have been posting daily updates. I know some here are following closely as they are right behind me in decisions, but also to provide a look at how long things take.

    We hired out everything except cabinet removal, which Mom and I did in 2 days. You can do it a little quicker if you aren't reusing them. My optimistic estimate was 3 weeks not including granite. We are a week behind at the moment. The electric took 2.5 days between sorting out the wacky circuits and running new wires. We added recessed lights, UCL, and a wall oven, plus had to move a few outlets and the fan. This is in addition to upgrading our main panel, which we did in February because we were out of room.

    I would plan 3 weeks optimistically, 4-5 realistically especially if you run into anything unexpected.

  • 13 years ago

    I always figured when we had reno work done at one house we could stay at our other but that sure isn't working out. Our pastor's daughter and husband needed a place to stay while they are looking for a home to buy. I can see their faces if we showed up at the house with our suitcases in tow! :)

  • 13 years ago

    Hollysprings, my panel is 200 amp - hooray!

    williamsem, I've been following your thread with great interest, and I appreciate your experience. We're only reusing one set of upper and base, and the upper can come down early. I can also start boxing up things we don't use regularly.

  • 13 years ago

    Here goes...

    Cabinet install will start Monday, July 15. We will be on vacation the week before that, so all decisions will need to be made before July 6.

    Electrician will start June 17, so we'll have the old cabinets out before that. He expected 1-1/2 days.

    I have a call in to my drywall guy. Hopefully he can come in as soon as the electrician is finished. Since it is just some patching (no new walls), it shouldn't take him too long. He's done work for me before, and he doesn't waste time.

    Flooring guy is coming out next week to see what sort of prep will be required for my new floor (and estimate how long it will take). We'll do prep before cabinets; tile after.

    Hopefully drywall and floor guy can mesh their schedules so they are in one after the other. When everyone is finished, I can get in and paint. With only drywall patches, painting should go quickly.

    I have 3 weeks from the day the electrician starts until we leave on vacation. I'm hoping to get everything done in 2 weeks, with a week to spare.