Fake Lien in Fixed Bid

18 years ago

We just foudn out by accident that our general contractor who is making 28% O&P on our job hid about 14K in additional charges in a line item. The invoice from the sub was $14K less (O&P not included) than what we were billed. The lein waiver was faked to look like the sub charged 14K additional.

It was a fixed bid contract. This line item was $20K and we found out the actual work and invoice was 7K. The contractor was still getting 28% on top of all this as we agreed. Does anyone have any advice? This is a huge amount of money and it pretty much makes me sick. Obviously we need to get the job done and stay on good terms if at all possible.

Comments (18)

  • 18 years ago

    I think you need to talk with a lawyer. That looks like fraud to me.

    Get info first from the lawyer, just so you know.

    Then, without mentioning the lawyer, point out the difference to your GC, and see what he says.

    And tell him what you expect him to do.

    but, if it was a fixed bid, is this $14k inside the total money you were expecting to spend? If he happened to get a great deal from his sub, or the work was simpler than he had expected when he submitted the bid? If so, wouldn't he expect that this savings would be HIS savings, and not yours? And if it had turned out to be more than his estimate, would you have expected not to have to pay that?

    Or is that not how your bid was supposed to be?

    Fixed bid, I thought was "pay me $x and I'll do everything on this list."

    Or is yours truly "cost plus"--that is "pay the actual cost of the material and the subs, and pay me 28% extra for my time and trouble."

    Which was it?

  • 18 years ago

    You want to remain on good terms with a GC who committed fraud? Why? First make sure it wasn't just an honest mistake. Sit down and talk to your GC about it and see what he says. If you are not satisfied with his response, then go through everything else with a fine tooth comb and call local law enforcement. Get a different GC.

  • 18 years ago

    You didn't say how you found out "by accident".

    You need to get your ducks in a row, verify absolutely everything possible and approach your contractor with evidence in hand. Tell him you signed a contract in good faith for work done.

    Don't say the "F" word yet (fraud). Tell him this charge needs to be taken off the bid, that's not what you signed up for when you agreed to work TOGETHER.

    Then don't say anything. Let him talk----people do not like silence and usually will keep talking themselves into a corner if their explanations are met with silence. Don't tell him "That's OK" or "Alright" - no affirmations.

    The less you say the more likely you are to get some satisfaction.

    Would appreciate more info on how you found out you were being shagged.

  • 18 years ago

    Well, it was fixed bid but 90% of the line items were the general contractor, plus they make 28% on top of everything. It was not like they jut got a good deal and that the extra 14K is their savings. We thought it seemed wrong which is why we looked into it. we ended up just calling the plumer and he told us the truth because he hadnt been paid yet. So far it is fixed bid in that everything that has cost more than their line item, we have had to pay extra. This is the first one we caught that was under and by A LOT and they didnt credit it to us. Do you think they could really face us and try to make us pay when it is so obviously unfair?

  • 18 years ago

    I guess I am a little confused by your original message - fixed price means I agree to pay X regardless of what it actually costs - as a previous poster said - that means if the GC comes in under he wins and if he goes over you win. On the other hand, if it was really a time and materials bid, then you pay actual costs plus overhead and profit. If in fact you have a T&M contract then it sounds like you have a problem. First understand what your contract says and then talk to your GC about it. It's possible it's just an honest mistake but if not then it's time to talk to a lawyer and/or withhold payment from him.

  • 18 years ago

    LOL Pecanpie you are obviously NOT British or you would know what 'shagging" REALLY means to us Brits. I hope she and the GC are NOT "shagging".

    Hmm, I agree that if this was a fixed bid contract and this was included in the bid then there is probably nothing you can do. Our GC was trying to nickel and dime us in the end because our fixed bid contract ended up costing him significantly more then he bid us because he neglected to give full disclosure on the work required to his subs and both the plumber and electrician underbid and ended up billing him significantly more - I am talking $5000 - which we refused to pay as it was not in our contract and had never been discussed as the project progressed. We did offer to pay for the items that we added on to the contract as the work progressed, eg two extra cans at $110 each, what we thought was a fair compromise but three months later have yet to hear back whether our offer is accepted or not. We are letting the bear sleep so to speak until the time to file a lien has passed and then we will make our offer one more time.

    What we learnt: Have a clause in your contract that says any work over $200 extra must be preapproved and any work that comes in more than $500 under estimate must result in a reduction of the bill. We will know for next time.

  • 18 years ago

    I'm even more confused now:

    >>So far it is fixed bid in that everything that has cost more than their line item, we have had to pay extra.

    That is not fixed bid - fixed means you pay the contracted price - no more no less - if he is charging you more when it costs him more than you have a T&M or cost plus contract. Also, if he is charging you more when it costs him more then he should credit you when it costs him less. I think you should consult with a lawyer to understand what kind of contract you have and what your options are at this point.

  • 18 years ago

    I guess my question is that if I am presented for a lien waiver for more than double the actual amount of work that was completed, invoiced and paid for is that legal? Since there is an O&P line item, I dont really think it is fixed bid but when I read through the contract I cant really tell.

  • 18 years ago

    I agree that you should speak with a lawyer. Your GC will never know, unless you find out that it is fraudulent, and have to discuss it with him or take legal action. If you go to him first he may just talk a big talk and confuse the heck out of you.

    loves2cook4six-- that clause is a great idea. I will keep that in mind when our kitchen reno is underway.

    Keep us posted- hope it all works out for you!

  • 18 years ago

    I would contact the licensing office that governs his license in your county if you can't resolve this.

  • 18 years ago

    loves2cook, no, not British, but went to school there and have watched Austin Powers, LOL. Around here, 'shagged' is a euphanism for 'being taken advantage of', ahem.

    I am confused as to whether this is in fact a fixed cost bid.

    Regardless, if a lien waiver/line item was faked to include an additional charge not included in the original bid, that smells like fraud to me.

  • 18 years ago

    It does sound like indeed she may be getting "shagged"

    It does sound like a cost plus contract and in that case there is a problem. If its a true fixed cost contract than there is no issue.

  • 18 years ago

    Well, cost plus or fixed cost, there is the issue that the contractor faked the lein waiver to bill an additional 14K.

    While the terms of your contract may have obligated you to pay the entire 14K for SOMETHING, my question, as I'm sure yours is as well, is why he drew up a fake charge and, continuing along that line, whether any of his other charges were falsified, and whether he might do so again in the future.

    I would not visit the attorney's office yet. You will be charged, and if your contract with the GC is in fact a fixed cost, you really might be SOL. Nevertheless, what he did is not right and does not inspire a relationship of trust between you and him.

    This is what I would do. Let your GC know you want to meet with him so he isn't caught short of time. Have your approach rehearsed so you are confident.

    Tell him that you know about the faked lein amount. Tell him how you found out. Tell him finding falsified bills makes you wonder about the rest of the bills and bills to come. You are happy with his work but your relationship as contractor and homeowner requires a significant amount of trust. Then explain.

    He trusts you to pay him in a timely manner, with checks backed by sufficient funds, to pay your electric and water bills so his subs can operate, and to disclose any previously known problems or defects with the house that could endanger his workers or affect the bidding or outcome of the job.

    You have to trust his judgment as to the competency of the subs he hires, and their trustworthiness in your home every day. You trust him to make decisions affecting your safety as well as your home's future marketability.

    This falsified line item goes to the issue of trust and you would like him to remove it so you can proceed with the relationship and the work.

    It is important to tell him what your/his expectations are re: trust, and also EXACTLY what you want him do to (remove the charge).

    If you can't bring yourself to a face-to-face with him, a calm letter to this effect will work as well. Be sure and keep a copy of all correspondence. If you can include a copy of the bill in question, all the better.

    Best of luck!

    pecan

  • 18 years ago

    Actually pecan, I disagree with you. I think an initial consult with a lawyer is in order - often a first consult is free and even if it isn't in this case it's probably worth it. At this point the OP doesn't understand what kind of contract they have and how it works. Before confronting the GC about improprieties, I think it would be better to get things understood and then decide how to proceed.

  • 18 years ago

    jlk0802
    Has anything happened with this concern? We are curious how this will play out.

    JB1176

  • 18 years ago

    I agree that an initial consultation with a lawyer is a good idea here. If the OP isn't clear on exactly what kind of contract they have - and fixed cost vs. cost plus is a BIG difference in this situation - it's worth it to get that understanding. And there is a good chance it will be free; even if not, I'd consider it worth a couple hundred bucks to know what ground you have to stand on, etc.

    In any case a faked lien release is a big red flag. You should be checking with every sub directly and making sure the other lien releases you have are real.. because if the GC was faking other releases, taking the money and NOT actually paying the subs - those subs can still put mechanic's liens on your home. Your recourse would be to sue the GC if that was the case.. but a GC who's doing that is having MAJOR cash flow problems and/or flat out planning to take the money and run, so you'd be unlikely to recover anything.

    And it's possible that the whole thing is just a big misunderstanding, and that the lien release for the wrong amount was an honest mistake. It could have been as simple as forgetting to go back and put the actual invoiced amount in when printing up the lien release.. still something that would need to be fixed, but if it was an honest mistake they shouldn't have any problem with fixing it.

    So basically I see no reason to be confrontational AT THIS POINT. Talk to a lawyer, don't mention that you've done so to the GC yet (that would make things confrontational real fast), and just say "Hey, I noticed that this lien release doesn't match up with the invoice from the sub. What happened?" See what they say.. that should give you a good idea of whether they're up to no good or not.

  • 18 years ago

    any updates???

  • 18 years ago

    I am curious if there has been an update??