My wife and I converted our late 80's vintage sun room into an ultra light, bright, clean and open kitchen. It was 90% DIY (contracted out the sheetrock and insulation) and we are so happy with how it turned out, that we wanted to share!
After two years of living in the home and doing several other renovations, we decided to pull the trigger and move our tiny outdated kitchen. L-shaped, it was cramped, small, the cabinets were falling apart, the tile countertop was in major need of replacing and had very little usable space.
We toyed with the idea of redoing the kitchen in the same place, but it still felt cramped, no matter the design. After almost 2 years or modeling alternative locations in SketchUp, we decided to move the kitchen into the outdated sun room.
Here's the sunroom before we moved into the house. It was cold, drafty, and had an ant infestation. The tongue and groove was in rough shape, the shelves were poorly made, and the tile was cracked and the grout dirty. BUT, the space had SO much potential!
We had a rough idea of what the layout would be and worked with Hancock Lumber to finalize the design. Dan Hanley was super helpful and easy to work with. The design required us to completely tear off the interior walls (and replace the insulation while we were there), replace the three big casement windows, and frame in the door. Initially we planned to keep the tongue and groove ceiling.
To start with, I removed all the T&G from the walls. Upon seeing the condition of the insulation, we decided to remove the ceiling as well. The removal and clean up took two days and was performed by myself and my wife.
Next I removed the old windows, the door, framed up for the new windows and framed in the door. This took a part of an evening and the next day. The next day, I helped my good friend Nick Kutch, a local builder, install the big double hungs and the small double hung.
What an immediate difference! The new panorama corner windows opened the room up so much. We were just so excited at this point!
I had a day before the insulators came, so I took it to do some interior framing. I framed the space above the french doors into a cool built-in shelf. We had big plans for this shelf... which you will see in the pictures to come!
I removed the french door and opened up the opening as wide as possible and added 2x2 strapping in the inside of the 2x6 rafters. The strapping was done both so that we could maximize the spray foam thickness and to minimize the thermal bridging.
The next step was insulation. We wanted the room to be warm and inviting, so we chose to go with tight-packed cellulose in the walls and closed cell spray foam in the ceiling. We did the foam in the ceiling due to it being unvented, and to add some structural rigidity.
What an unbelievable change that made. What was once a drafty, chilly room with a odd echo was now a snug, cozy, and quiet space. We are super glad we went with the cellulose and foam. Really nice stuff.
Next on the to do list was to raise the floor. The sun room had been built sometime in the late 80's and had been constructed on top of an old deck. The deck was 13 5/8" lower than the main floor of the house. We felt this separated the room from the rest of the house and would ruin the flow into the kitchen. So, we decided to raise the floor up to the level of the rest of the house. The countertops are soapstone and very heavy, so we made the floor VERY robust.
Next on the docket was sheetrock. Unexpectedly, Irving Starrett of Irv's Drywall was able to fit us in right before Christmas. It just took one night of working until midnight to make that work. ;-)
They did an incredible job and we were able to paint and put up the trim the day I returned from sea.
We ordered local Maine Ash hardwood flooring from A.E. Sampson and Son and it arrived three weeks ahead of schedule. Completely stoked, we installed in and finished it with Benjamin Moore water based poly in two days.
With the floor completed, I had to head back out to sea for 3 weeks. Upon return, Nick, our friend Jeff Kelley of JK Timberframes, and myself installed the cabinets. Over the next week and a half, I installed the M. Teixeira Fantasia soapstone (who were a dream to work with), lighting, hardware, finish plumbing, and did the touch up paint. We scheduled a big dinner party to keep the pressure on and we were able to pull it off with just the backsplash behind the sink left to install.
Long story short, it was an awesome time, we had a ton of cool people to work with and we are super happy about how it turned out.
Here's a few of our favorite details, including the built-in shelf I mentioned above.
Please ask if you have any questions. I'm glad to answer or find the answer. :) Hope you enjoy!
Studio NOO Design