Sub asking for deposit

10 years ago

I received a written bid from a sub. I agreed with the price and signed the contract. Work has not started yet and now they ask for a deposit. The contract says nothing about deposit nor payment before work starting. I signed contracts with other subs and none of them ask for a deposit. Any advice?

Comments (12)

  • 10 years ago
    last modified: 10 years ago

    You need to state what contractor, what deposit are they asking for. I normally tell exactly the same story to every contractor.

    =

    I once paid to a contractor and he never showed up again, and stopped answering my calls. Sorry, I do not do this anymore. I can consider paying 70% the moment you completed the job, or I can consider payment to a supplier the moment materials delivered to the job site. I will not pay 50% deposit on any job.

    =

    To be honest I can pay rough-ins materials to electrical, plummer, hvac - after they performed about a day of labor. Obviously if you pay 10k to framers - you will never see them again.

  • 10 years ago

    We're owner builder and haven't paid a deposit to a single sub and are at drywall taping stage.

  • 10 years ago

    How much of a deposit is he asking for? In the end, you are trusting the guy to participate in building your house, do you not trust him with a small retainer?

  • 10 years ago

    This is for waterproofing and drain tile to the foundation and they ask for 30%. I don't feel comfortable working with this sub. How would you cancel it if you already signed the contract? I want to work with someone else but what if they ignore the cancelation, show up at the site and do the work? I only want waterproofing and drain tile once.

  • PRO
    10 years ago

    Registered letter, signature required, stating notice to cancel contract immediately.

  • 10 years ago
    last modified: 10 years ago

    I've never paid a deposit other than to custom stair and rail builders and cabinetry suppliers.

  • 10 years ago

    How would you cancel it if you already signed the contract?
    Don't pay the deposit.
    But more importantly, do as Virgil has suggested.

  • 10 years ago

    I would probably do some homework to see if they are even licensed. Red flags for me!


  • 10 years ago

    Thank you all for the advice.
    Plumbing, electrical and HVAC contracts clearly show what % is due after certain phases and I don't have problem with these. Excavation, septic and pour foundation have no payment structure except the pour foundation sub asks for full payment within 2 weeks of completion. Foundation sub also mentioned if I paid in 5 days of completion they'll give 2% off.
    My concern is they may make up things to charge me more if I continue working with them. They told me twice that the price will change if the measurements they found are different.

  • 10 years ago

    Listen to what your gut is telling you! As you previously mentioned you don't feel comfortable with them. If their contract did not have a payment schedule as you mentioned above then you owe them nothing as a deposit. Sounds to me they have breached their own contract....which in MHO would be reason to pull out.....if I were you.

  • 10 years ago

    Good for you.