Delays (unexpected). Time to abandon plan until Spring?

8 years ago

Our intentions were to break ground in September, and while it was probably a lofty goal, we were pushing hard. Lots of little setbacks with the subdivision approval process, etc. Now all that's left is the building permit (still waiting on it) and the loan. The latter of which is really starting to wear on me. The land is being gifted to us from my parents. The deed also needs to be transferred into our name before applying for a loan. Due to some paperwork errors and some oversight on the part of the parties involved granting me the ROW across my parents property, it's looking like next week is the earliest I will have the transfer completed. My lender is saying 30-45 days to close on their in house products, which is pushing us into mid/late October. My builder says trusses right now are 6 weeks out, but that may change. He (the builder) really wanted to get it dried in by November, and he's not feeling really confident at this stage which is fair since it's a fairly sizable build, and he's only a small operation (three guys).


I really don't want to deal with material inflation for a Spring build (no guarantee it will go up, but I'm banking on it), nor do I want to play the "what if" interest rate game, but at this point in time, I'm not sure I want to risk the complications that come with a winter build.


Have any of you pushed your builds back an entire season? Regrets?

Comments (19)

  • 8 years ago
    last modified: 8 years ago

    As the saying goes, time is money. So as a builder with holding costs always running, the sooner the better. Fall is always best in our cold climate, but I've started in November and December when necessary.

    Of course, with free land and a g.c. not confident or experienced in cold weather building, your situation is significantly different.

  • 8 years ago
    last modified: 8 years ago

    You've got the wrong builder. Better find the right one first.

    But only after you resolve the landlocked lot issue. Most banks aren’t going to loan on a lot like that without a purchased stripe to an access road. Or the creation of a private access road, with an association agreement from all property owners for maintenance. A simple easement isn’t likely to do it.

  • 8 years ago

    We had to push ours back 5 months from spring to fall for various reasons. It wasnt that bad. We didnt have a loan though, and owned the land. At that time (2014) costs were not skyrocketing!

  • 8 years ago

    Sophie,


    He said he will build throughout the seasons, he just prefers to have it under roof by the time snow and freezing temps hit. I don't think that's being unrealistic. We're a small town and he's born and raised here. Super trust worthy, has done work for my family, been in business 30+ years, I know subs that worked with him, people that delivered to him, people who had work done by him, and not a single bad thing to say. Believe me, I've vetted my contractors well.


    As for the ROW, I agree. I understand why there's a holdup with the process due to being landlocked. My parents own the ground we're going across (jointly with my uncle). Everyone is on board, and the paperwork was signed and submitted, but down without the proper signatures in a few spots that require that document to be re done. No worries, the lawyer is reviewing all documentation.

  • 8 years ago

    jn, the latter part of your statement is what worries me. Material prices are definitely rising, and rising fast. The prime rate is anyone's guess, but still a factor.

  • 8 years ago

    Virgil, very true.

  • 8 years ago

    Most builders in our area are so far behind from all the rain, that our fall start is going to now be a spring start too. I shudder to think what another Hurricane hitting the US is going to do to material prices......

  • 8 years ago

    You absolutely need access set in stone.

  • 8 years ago

    I wonder if the market can sustain the rising lumber costs beyond their mark for next year. It might not be such a bad thing to wait and get everything situated.


    Perhaps the builders on here can comment on the potential for loading next year based on the planning which usually takes place right now.


    One realtor once told me she would only build in early winter as spring has its own issues.


    I remember it poured out after my house was roughed in and then they started roofing the wet OSB. Rain filled the window wells and went into the basement.


    There really isn't a good time to build other than when you are ready.

  • 8 years ago

    We had all plywood specd here in the PNW. The wood survives, but boy was it wet. I was worried. Needlessly as it turns out. It does take some extra work in the winter, but people like paychecks that come year round so they find a way.

  • PRO
    8 years ago

    Welcome to the world of land development....

    November is 50+ days away. Focus on getting the easements and split complete, permit issues complete (you've cleared all reviews?) Until you have clear information these will be ready, don't close the loan. It really depends on your municipality.

    I start year around depending on grading requirements vs. rain, but it doesn't freeze here.

    Construction costs are almost always moving up in total at a rate higher than inflation, although each piece will move independently, plateauing and spiking. The most volatile piece to home value, the land, you already have in place so it will not change.

    NAHB 2018 cost articles


  • 8 years ago

    We planned to start in the fall. I can’t recall why but our builder couldn’t get the framers he wanted to use until the following early spring. According to him they were the best. So, we waited until spring.

    In the big picture a few months is not a big deal.

  • 8 years ago

    There is a lot that you can do before winter hits. Just move forward. The attorney needs to step up his game. Failure to insure the proper signatures is their fault. Tell them to make this happen yesterday. Plan on pressing forward.

  • 8 years ago

    Jeffrey,


    Yes all other permits have been acquired and all subdivision materials have been approved by both county and our municipality. I've filed all paperwork in the courthouse as well. The ROW Agreement doesn't get filed, but is required for subdivision approval. Luckily we won't need to go through that process again, but the agreement needs to be resigned to allow the deed transfer to take place. That is all that's holding us up at this point.

  • PRO
    8 years ago
    Would your builder want to get the foundation in before winter and let it set? you'd be the first project ready to frame.

    Might be viable if framing before isn't.
  • 8 years ago

    Letting a foundation sit through the winter is not a bad thing. However, letting snow/rain inside percolate all winter is not a good thing. If you were to get the foundation in and the deck on(floor joists and sheeting(sub floor) installed and have to wait until spring, I have a suggestion. Paint the entire wood surface-with Oops paint or the cheapest you can find. Slather it on with rollers. That will protect the wood(subfloor and all) until spring. It all gets covered anyways.

    In a week or two, plywood prices may rise(hurricane). By November, the prices should be back down. No telling what happens next year.

  • 8 years ago

    Not a builder, not a pro. Am someone having a house built who knocked down the old one and started in October of last year. I live in Vancouver and it rains all the time. No one stops here because of rain. We did hit a cold stretch that caused us some grief but we don't have ongoing cold to battle. In our case I'm glad we started when we did because we had to amend our drainage plan and also work more with a geotech to manage run off water and a creek under the lot. Much of this could have been hidden in a drier time and we would have been screwed come a wet winter. So for us it was great building in the worst times as it really made us feel secure in our water tightness.

  • 8 years ago

    We have decided to pull the plug. It's still too wet which is delaying the well truck getting back in, still no word on the time frame in which we will have the deed finalized, and frankly, with a 1 month at home, we don't need more on our plate right now. We're going to get everything on the lot finished this fall/winter (power, well, road), and then hit the ground running in the spring.