Aclimating hardwood floor

5 years ago

Hi guys! This forum has been such a big help so sharing another dilemma.

I purchased solid prefinished hardwood floors that are being delivered next week. (Brand:landmark color asphen)

The house is in New York and issue is the house ac/venting/heating hasn’t been installed yet and is not going to be installed for another 4-6 weeks
They just finished the Sheetrock and plaster and ready for priming now

The floors are supposed to arrive on Monday 5/17 and they will be installed after one week after

The weather is getting warmer (70-80) is this going to be an issue?
I asked the plumber to come before but he’s won’t come earlier.

Any experience or recommendations?

Comments (12)

  • 5 years ago
    last modified: 5 years ago

    Stop the delivery. Read the warranty, everything you are planning on doing will void it.

  • PRO
    5 years ago

    Are your floors prefinished? If so, I recommend you wait until trim is installed and everything is painted. And I wouldn't do either without the HVAC operating for at least a week.

  • PRO
    5 years ago

    The HVAC MUST be up and operable for any finish surfaces to be installed. Builders don’t like paying the utility bills, and some may not have factored that in. Tough. Cabinets, flooring, millwork, etc must have a conditioned home. Moisture readings must also be taken and recorded.

  • 5 years ago

    I’m getting mixed opinions, the HVAC guys said don’t turn on the hvac until everything is done as the dust with kill the system ... but right now there’s not much humidity 44% ...

    The trim hasn’t been installed yet ...
    we haven’t done the prime that’s coming up tomorrow or Monday, not sure what the sequence should be?

    Here’s what’s left maybe in this sequence?

    Bathroom tile install
    Painting
    Hardwood floor install
    Molding & base trim
    Door and windows casing
    Hanging the doors
    Kitchen cabinet install
    Installing light fixtures
    Installing railing

    Not sure if I forgot anything

  • PRO
    5 years ago

    That would be a typical order of operations if the hardwood floors were the sand-and-finish-in-place type, but not for pre-finished hardwood flooring I wouldn't install any flooring or interior trim until the HVAC system was up and running for a week. And I wouldn't install pre-finished hardwood until the trim was installed and the painting was complete.

  • PRO
    5 years ago

    Your project at drywall stage is about 1/2 complete. Your GC will determine the sequence, not vendors selling & delivering materials.


    East vs west coasts will vary in preferences, new custom construction, cabinets are built up to accommodate floor thicknesses, so they install before flooring.


    What we do before prefinished hardwood:

    • Drywall finished, dried and sanded. I like to see the home kept at 55 degrees min for drywall finish and paint btw.
    • Messy trades next - tile, door & trim, cabinet install, interior masonry, measure for railings, enclosures, slabs
    • Interior Paint
    • Install electrical, mechanical, plumbing fixtures
    • Exterior flatwork if possible

    After hardwood, we install baseboards and thick cabinet toe kicks to cover edge gaps.




  • 5 years ago

    Thank you for the detailed responses!

    Jeff, wouldn’t the hardwood floor go underneath the kitchen cabinets? So why install that first?

    And in the above comment when would they 8”install/turn on the hvac?

  • 5 years ago
    last modified: 5 years ago

    The order of operations that is easiest for the builder ensures that you void the manufacturer’s warranty on a wide variety of expensive materials, flooring and cabinets both.

    That’s a construction conundrum that won’t be solved, because no homeowner wants to wait another 4 months for the home to be completed, and no builder wants to change things for a longer build time either.

    Industry standard requirements. Which most builders ignore

    https://nwfa.org/wp-content/uploads/2020/03/JobSite-Checklist2.pdf


    https://www.masterbrand.com/-/media/masterbrand/pages/care_and_cleaning/5452mbcihumidificationeducation.pdf

  • PRO
    5 years ago

    No as I explained: "cabinets are built up to accommodate floor thicknesses, so they install before flooring." Your builder may do it differently so ask.


    Ignore what you see on DIY TV. This sequence allows us to avoid construction traffic on hardwood and more easily meet the standards required.


    Is your flooring person pushing this? Who is running the show?

  • 5 years ago

    Well... I kinda fired my GC as there were huge mistakes made! We extended the house and in the back side of the house they didn’t install the waterproofing around the foundation and that’s why the basement has a leak there’s another post with pictures... the leak is still happening and I’m getting quotes for 10 k to get that fixed, most contractors said they will have to remove the patio door and redo the foundation/waterproofing.

    Now I’m on my own but getting quoted from other GC for the rest of the job... now trying to choose a good gc but everyone is giving me different information

    Thank you everyone for the guidance really appreciate it!

  • 5 years ago

    Your bank allowed you to become the GC?

  • 5 years ago

    A lot of people save up and pay cash for remodeling projects ... or even new construction!