Contractor lowered ceilings to "LEVEL" for tiles, Normal solution??

Hi, Our contractor lowered our bathroom ceiling by about 2 inches (maybe more) without consulting us about it. He later claimed it was because our ceiling wasn't level enough to tile all the way up to the ceiling. But as a bonus he suggested we do recessed lights since now we have the option ( original ceiling is concrete) which of course he will be charging us for since we agreed.


Is it normal to lower the ceilings in this case? I wouldn't say it was noticeable before when it was just painted without tiles so its hard to confirm how un-level it really was or wasn't.


Really wish we didn't just walk in on ceilings that are lower with no explanation. Now we are thinking this may not have been necessary?


Also I cant seem to find any clear info researching if this is a legit solution or not.

Comments (8)

  • 5 years ago
    last modified: 5 years ago

    We've had this ceiling work be necessary on a couple of jobs (our kitchen and one bathroom), but it was discussed and agreed upon by us and the contractor as it came up after the demo. Your underlying problem is communication. It's normal for issues like this to arise on a project, but the contractor should call you to discuss after they demo and measure. If the contractor squared up the ceilings, that's probably okay, so they can do a good job on the tiling and give you the better lighting. But you should have a discussion (back up all discussions with email confirmation) about communication. Make sure the contractor has all your contact info and you have theirs. Ask them to reach out to you to involve you in these types of decisions as your reno moves along. Tape your phone number up on the wall. There will be other things that come up, so ask them to call you you when they do.

    Issues arise all the time during renos. What matters is how they are handled and if the parties are communicating.

  • 5 years ago

    Ironically enough my phone number is posted on the wall in two place. I have asked them to call me or text or whatever with any questions and yet when something big like this happens they just proceed to so it anyway. Emails get ignored completely. We have a contractor that doesn’t know how to communicate at all.

  • 5 years ago

    Thank you Joseph! I hope so, Our contractor already layed our tiles on one wall in a "brick" layout and we asked for it to be in a "checker board" layout ( sorry don't know the terms) - clearly either is memory is an issue or his communication is really lacking.

  • 5 years ago

    It does sound like the right thing to do. It’s just that homeowners don’t know the process and can get worried unnecessarily if left to wonder bc of lack of communication.

    But if contractors do this kind of thing they should explain it and tell homeowner why it‘s the right path. After demo just tell the homeowner ”I’m going to square up your ceiling so your tile will be straight and beautiful, and you‘re getting a lighting upgrade. The upsides of this far outweigh the small 2” difference in ceiling height”


    Communication helps homwowners not worry and fret when they see something unexpected.


    It’s so common to need to do this, probably every contractor could just say ”I’m probably going to square up your ceiling/wall/floor… to get you a beautiful straight/plumb/flat tile/woodfloor/wallpaper installation” at the beginning of every project.

    whyisrenosostressful thanked AJCN
  • PRO
    5 years ago

    Change orders are the bane of both the contractor's and homeowner's existence.


    Your remodeler inherited an existing out-of-level condition which is pretty common. The issue is how they addressed it. First, there should have been some disclaimer or boiler plate language in the scope of work about such conditions noting the potential for additional costs, and second, the contractor should have provided you with the option to correct the out-of-level condition as a change order with a defined cost before proceeding with the work.

  • 5 years ago

    Our contractor already layed our tiles on one wall in a "brick" layout and we asked for it to be in a "checker board" layout ( sorry don't know the terms) -...or his communication is really lacking.


    You admit to not knowing the term for what you want yet you think the contractor's communication is lacking??!!!


    What does the tile manufacturer suggest for a layout of the tile?

  • 5 years ago

    ci_lantro, We showed images to our contractor for ref of what we wanted. And he drew out the exact layout only to do something totally different 2 weeks later. So yes I would say the communication is lacking.