Pushing Renovation Budget Temperature Check

4 years ago

Should I be more direct and demanding? I've been presented with my 3rd progress invoice. I have no problems willing to pay. The bottom line is I want to know where my General Contractor is now with managing the budget after 3 months with about 2 months remaining. We are doing a full on kitchen, Bath, whole house flooring, painting, etc. I don't want to blindly trust and end up with a surprise bill for overages or a separate bill after the project has ended.


I have good communication with my general contractor and work is moving along with some challenges. I've progressively asked (twice) that I would like to know where we are with the renovation expenses and have been diverted. I don't want to get stinky and risk souring the relationship. Any thoughts on how I should proceed? Thank you.

Comments (7)

  • 4 years ago

    Are you not getting details on the costs with each request for progress payments?

  • 4 years ago

    What type of contract and payment arrangements were made upfront? Is this change order work or base project? Weren't costs determined upfront?

  • 4 years ago

    If this is a fixed cost contract, that information should be on your contract. If it’s a cost plus, you should be getting cost statements to do the math.

  • PRO
    4 years ago

    Much better to deal with a small stink now than a much larger stink later. Money is power and you'd better make sure it's traded fairly.

  • 4 years ago
    last modified: 4 years ago

    Your original contract should have outlined that expense for each item, for example demo and waste removal, insulation, sheetrock etc. If you haven't signed any change orders there shouldn't be any surprises.

    You can ask for a detailed draw invoice that will show what you are being billed in each item of the contract.

    Make sure you know what parts of the construction are considered a capital improvement and are provided with the CCI to fill out. You will not pay tax on capital improvements.

    Approach the invoicing and payment the same way a commercial customer would.

  • 4 years ago
    last modified: 4 years ago

    If you've been asking him on the fly, it's time to schedule a sit down with it made clear what's on the meeting agenda. If you want to see receipts or have a breakdown of costs so far, you need to put that on the agenda so that he knows to come prepared. It doesn't have to be confrontational. If he's professional, he won't have a problem letting you know where things are at.

    LIke other posters, I don't understand the sort of deal you have with your contractor. Maybe I'm misunderstanding but it sounds like he's doing work and telling you costs as he goes along and you're paying whatever he says. We've always had estimates on the whole project with costs broken down. We've usually paid a percentage upfront and then the balance upon completion. Can you explain the nature of your contract more clearly?