We recently completed an addition to our existing home. Upon measuring for the hardwood floor installation, it was brought to our attention that the level of the tile, which had already been installed in the kitchen and foyer, was considerablly different from the level of where the hardwood would be after installation. In order to create a smooth transition between the tile and the hardwood, we had to pay to have plywood installed over the entire subfloor, which covers both "old" and "new" areas of the house. We just discovered that there is a similar issue in the upstairs flooring between the "old" hallway and the "new" master bedroom, which, if left as is, would result in a "dip" and uneven wear at the threshold. It's been suggested by the carpeting company that shims and feathered plywood be used to create a smooth the transition. When doing a home addition, is it the contractor's responsibility, as part of the renovation, to make sure that there is a smooth transition between "old" and "new" subfloors, or is this the responsibility of the flooring/carpeting company? Input from the trade would be most appreciated. Thank you.

Comments (2)

  • PRO
    12 years ago
    Every contractor will tell you that it is almost impossible to match up the floor heights between old house and "new" addition. This uneveness is so common that everyone has a quick fix for it.

    The "responsibility" is hard to point to. It should have been discussed with you at the time of the build and a contingency plan put into place (as an extra expense that you would have signed off on) with the contractor to mitigate the "lip". It is quite possible that the GC did everything - to the letter - of the contract. If there was no "letter" for the height difference, s/he would not have done anything more than was necessary.

    I'm not sure who hired the flooring people - yourself or the contractor. If the contractor is subcontracting out the flooring installation (and everything is paid to the GC) then s/he might have left it up to the subcontractors to work it out for themselves...I'm not sure what your contract states and where the build "ends" and the "finishing" begins.

    This difference in floor heights is extremely common and should have been discussed with you to find out what you wanted done to reduce this concern. A quick look at your contract will tell you where things stand.

    Whether your contractor puts in the "fix" or the flooring people put it in...either way you will need to pay for the work. A quick phone call to the contractor will tell you whether or not s/he had billed you for the mitigation work. If you paid for it in your contract, the GC MUST have the work done for you...without extra cost to you. If you did not pay for it, then you will need to pay for the mitigation that the flooring installers have to do.
  • 12 years ago
    In general, a good contractor should have gone over this with you before construction began. It should have involved the EXACT floor covering you would use, as they come in different thickness. If these things are not picked out ahead of time, then the contractor would have to assume that the top of the new subfloor should be even with the top of the old subfloor. With too many remodeled layers on the old floor, this could be a problem because nobody knows whether the old layers will eventually be torn off or not. That is why it should have been an in depth conversation from the start.