Software
Houzz Logo Print
sgoldfield

Subs not getting paid

18 years ago

Hi, I appreciate any thoughts you can provide on this problem for us.

We are in a cost plus contract with a general contractor and about 9 months into the build. We have run into three situations so far where we've been told by subcontractors that they have not been paid against completed work, work which we were invoiced for in the past. We have paid the contractor bills promptly each month and in this latest case, we paid for this work back in March and the sub said they still hadn't been paid. Last week we told the GC we would not be paying our next invoice until he had paid the subcontractor. Next thing we hear from the sub that he has received a check, but only for part of the total due, and now the check he was given has bounced.

We can terminate our contract at any time for any reason, but we like the work the GC's direct staff has provided and we are depending on them to do a lot of finish work. Our project manager on site is great, its just the financial issues that have us worried. Most of the subcontractors have issued us "right to lien's" notices.

Is there a method by which we can pay by providing checks co-signed or directly written to the subcontractors and then one additional check for the work the GC provides and their fees? Is this meddling or protecting our property? Should we just insist on getting a signed liens release from every single subcontractor prior to paying the next bill? Other ideas?

Thanks again for any advice you can share.

Comments (11)

  • 18 years ago

    I would consult a lawyer or a design professional before writing any more checks. Forget how much you like anyone; you must consider the possibility that the GC will become insolvent and you will have to absorb the loss and hire others to finish the project.

  • 18 years ago

    Oh, dear. I feel your pain! The exact thing happened with our build. About a month before completion, we find out that GC hadn't finished paying for the LAST build he completed. The subs were trying to give him some leeway, but were growing impatient. When we realized what might be going on, we paid some subs upfront (got a better cash price, too) and made sure we got documentation that it was paid. Whether it's "under the table" or not, I think it's protecting your investment if you see things going south. If we would have known just how bad it was going to get, we could have paid EVERYONE upfront, but no subs told us anything about not getting paid for our job until 6 months after we closed! Five of them filed liens and we ended up paying them all. Makes me ill, but our thoughts were that we got the house at a decent price, if we had to pay $30,000 more for it, it is still a bargain for what we got.

    I don't know that any subs will sign a lien release until the entire job is done. Don't wait until it's too late to be proactive.

    Our GC did EXCELLENT work, but was a very poor business manager with personal problems to boot. Good craftsmanship isn't a reason to stick with him if he's not paying the bills. I'd see about finding another GC immediately, if that's possible. You'll end up eating it anyway if he goes under, so do what you can to protect yourself!

  • 18 years ago

    Our contractor is giving us releases signed by the subs so we know that they have been paid. I guess we were the first people to ask him to do it but he thought it was a good idea after we suggested it.

    One of the reasons we went with this builder over others is how everyone (vendors, customers, etc) talk about how honest he is. The subs say he pays usually within 10 days of the invoice.

  • 18 years ago

    We initially put both the GC and subs name on the checks (we are self financing) but GC whined about it being too much of a hassle for his subs. DH is an attorney and suggested GC give us the invoices and we'd pay subs directly. This has worked out pretty well although GC is still trying sneaky ways to get money.

    DH says writing on the bottom of your checks "exclusive payment for ---) insert sub contracters name will help. If your contractor cashes the check and does not pay the named sub, contact your DA's office as it is a felony, punishable with upto 10 years in jail here in LA.

    Maybe too late for 'susurradeluz', but perhaps can help someone else!

  • 18 years ago

    There is a very simple answer for this without the use of lawyers. People in the Gardenweb like to pull the lawyer card early and it really antagonizes everyone involved in the issue. We are a GC who works exclusively on a cost plus basis and when we work with lien waivers it is done in the following way. We invoice monthly and supply lien waivers with the following months bill. Most GC's pay the subs after they have received the funds from the client, however all charges on our invoice have been paid prior to submitting a bill to the client(we are not the industry standard!)making it easier for me to have the lien waivers in a timely manner. If you have not been requiring lien waivers, I would have a conversation with the GC and explain that no additional funds will be dispersed until all lien waivers have been submitted and confirmed by you and your husband. Make sure that you make a list of all subs that you have been invoiced for along with the amounts paid to the GC on behalf of the subcontractors. He may kick about it but if you have pre-lien notices you will need the lien waivers to release the lien. Financial trouble or not, he has a legal responsibility to provide you with documentation of payment to the subs and major material suppliers.

    Lastly, It is inappropriate for a subcontrator to contact you directly prior to the end of a project since the financial arrangements are between him and the GC, not him and the owner.

    Take care!

  • 18 years ago

    Just a small comment on the check writing part ( I am no way related or have GC experience). Maybe it will depend upon laws in your state, but here, writing the name/reason for the check at the bottom is not good enough- it MUST be written on the BACK of the check. I know from sad experience. I wrote 'for deposit on house', on the front of a $40,000 check I gave to my daughter for a house. She spendt it on 'stuff' in 4 months, with no house. I could not recover any money becasue I did not write what it was for on the back.
    Bellamay- sorry, it might be 'inappropriate in your eyes, for a homeowner to contact the subs regarding nonpayment by the GC, but it would be MY money, and I don't plan on paying for a house twice. The GC is the one who is inappropriate.

  • 18 years ago

    In direct contrast to the way bellamay states most GCs conduct business, our contract with our builder requires him to pay the subs and provide us with the lien waivers for all work PRIOR to us releasing funds to him. A GC should have a sufficient line of credit to allow this to occur.

    Homeowners absolutely have a responsibility to demand the lien waivers. This is not an area where you can rely on your GC to look out for you...there is too much at stake.

  • 18 years ago

    We were ripped off by our builder and I will never ever ever pay anyone a dime until I know all work is completed to my satisfaction and all subs are paid. I was naive to not have a contract like Dixie's.

  • 18 years ago

    Don't forget your Registrar of Contractors. They have a homeowners recovery fund, which may be able to help you recover a portion of your loss. Be sure to file a complaint with the registrar as well. If you go to court, having the complaint done is important. There is also the issue of the subs can threaten all they want, but unless you the homeowner signed their contract, they probably have no lien rights against your property, just against the general contracting business and his properties. Don't be too quick to pay.

    Here is a link that might be useful: CCC Builders

  • 18 years ago

    The above is a builders ad!

  • 18 years ago

    It might be a builders' ad, but a few of those houses are serious eye candy...and I don't even like the Southwestern style!