daf999999

contractor payment schedule?

11 years ago

We are doing a substantial addition and remodel with a GC selected after competitive bidding. The GC is essentially a one-man shop (owner with a couple of foreman and established stable of subs) who has done many projects of our magnitude (and larger) in the immediate neighborhood. We are very comfortable with him but want to be reasonably cautious - for example, if he gets hit by a bus halfway through our project we don't want to have committed too much cash. We are not looking to be unfair to the contractor but don't want something unfair to us.

Here is his proposed payment schedule. Can anybody comment on whether it is reasonable? Thanks

+++

Payment 1. Upon signing of this contract, $10,000

Payment 2. Before start of construction/Demolition $45,000

Payment 3. Due when Foundations are poured and backfilled $55,000

Payment 3. Due when addition and porch are under roof $55,000

Payment 4. Due when mechanicals are installed, and renovation/remodeling
complete, all areas are dry walled. $55,000

Payment 6. Due when all inspections are passed, and all finish work is completed. $60,000

Payment 7. Final payment after Punch list items are complete $8,653

TOTAL $288,653

Comments (12)

  • 11 years ago

    Reasonable.

  • PRO
    11 years ago

    No way I'd make that deal if I were your contractor. It would say something like "Addition and porch work begin after payment for demolition." Every time I didn't get a payment, work would stop.

  • 11 years ago

    It's a little heavy on early payments prior to work being completed, but not bad. Aside from a good faith small deposit to start I try never to pay for work or materials not done or purchased, since said work or materials may never materialize. I also then pay every two weeks or so for work completed rather than waiting for larger chunks of the project to be done. I think a fairly tight pay-as-you-go schedule minimizes risk for both parties.

  • 11 years ago

    In California, contractors making improvements to residential properties are not allowed to ask for such a significant down payment before the commencement of work ... it is 10% or $1,000.00, whichever is less. Not sure where you are located or if there are such limitations in place, but it might be good to know. Personally, I'd have a problem parting with $55,000 before construction even begins.

    This post was edited by jellytoast on Mon, Nov 17, 14 at 11:10

  • 11 years ago

    Open an escrow account, with all payments subject inspection approval.

    You're present schedule requires you to finance the construction.

    If he is not strong enough to finance his operation, then back away.

  • 11 years ago

    I thought it was pretty heavy at the front end too.

    $55,000 seems to be the magic number. I think paying relative to the work being completed is safer than evenly paced chunks based on the project total. No doubt in my mind he is putting you on the short end of the stick, without leverage, if there are problems.

    Doubt you can change that though, unless as jellytoast stated, there are consumer protection laws around it.

    You also have to worry about bankruptcies. Not always apparent on the surface of things.

    $110,000 for demo and a foundation is pretty steep, imo.


    This post was edited by snookums2 on Mon, Nov 17, 14 at 13:51

  • 11 years ago

    IMO, a contract should be fair and equal to both parties. This one seems to favor the contractor, allotting him a significant chunk of change before he has even completed any construction. That protects him. What protects his client? If I really wanted to go with this particular contractor, I would renegotiate the payment schedule so that I wasn't paying so much for "future" work. If a good deal of that $55,000 is intended to go for materials, I'd protect myself along those lines as well.

  • 11 years ago

    Which, I am beginning to think from listening to other discussions, he might be needing your money to fund other things/projects. In essence, his clients are floating him loans. Interest-free at that, with a lot of risk attached. This could indicate financial problems, as snooby noted.

    At least try to renegotiate to protect yourself. If he won't, you need to make a choice how much risk you want to expose yourself to for this particular company.

    There was a seemingly sound company around here that bellied up, a near million in the hole. I'm sure their business partners and clients did not fare too well either. It does happen.

    This post was edited by snookums2 on Mon, Nov 17, 14 at 19:58

  • 11 years ago

    I just talked to a contractor today. That is standard. He told me it'll be like 10% up front. He said this is for some beginning costs, some materials later in the job they need long lead times on etc. They have costs after each phase (foundation, plumbing, electrical etc). So it's reasonable.

  • 11 years ago

    "I just talked to a contractor today. That is standard."

    With their hand in your pocket, they'll tell you anything, to get you to keep it there.

    Talk to a bank or an escrow.

  • 11 years ago

    Standard? Hardly.

  • 11 years ago

    That is a very reasonable draw schedule and pretty standard. I'd argue that you will be way ahead (to far imo) towards the end of the project. You should be about 95% complete after inspections and still owe the contractor 68k. Most of the problems, if any, will be towards the end anyway.