Seriously, how long could this take?

18 years ago

Our remodel will begin sometime in the next 2 weeks or so. I am getting new cabinets and new counters (with new sinks, faucets etc) and some electrical work (cans, undercab lighting). That's it. The layout, floor and appliances are staying as is. This is how it goes in my head (stop laughing!) They rip out and install new cabinets in a day or two. The templeter (sp) will come out the same day the cabinets are installed. I know the counters will not be in for 2 or 3 weeks after that. BUT, can't I get a plywood counter and the old sink and dishwasher hooked up for the weeks I am w/o counters? So it doesn't sound that bad right? Am I just way off here....? Go ahead ruin my little fantasy! The mess and chaos is ok with me, I just need a minimally functioning kitchen. I can't imagine having no access to kitchen facilities for 3 weeks! And I can put all the stuff back in the cabinets as soon as they go in, can't I?

Comments (19)

  • 18 years ago

    I'm halfway through a 2 month remodel with layout changes. GC moved my fridge but still usable. I've cooked with my microwave and gas grill with burner. These two items have saved me. Luckily it's summer, so grilling out is a pleasure. Yes, you utilize plywood on sawhorses or on top of cabinet boxes until you have a counter installed. I'm doing that now. A folding table next to your microwave stand (mine's in my DR) is a good idea too. We're eating on paper plates and plastic wear, so there's not much to wash in a sink except a coffee cup or occasional pot used on the grill. My coffee maker and supplies are now in my master bath. And when I have to wash a dish I have a utility sink in my laundry room. A clean bathroom sink used exclusively for dishwashing would be fine too. Since your layout isn't moving this process should be easier for you and take less time. Yes, it'll still be a hassle, but it's workable. I can't speak to when you can put things back in the cabinets as I only have boxes, no pullouts or fronts yet.

    Hopefully you will not experience any delays, but anticipate your project running longer than the estimated time frame. It seems to be par for the course. Good luck.

  • 18 years ago

    9 months and counting. Opening of wall and installation of hardwood floor must be done first (you are not doing that, good, time saved) No finishing of floor because we want cabinets in before installer gets married. Kitchen cabinets almost completely installed. Kithcen installer got married and went on honeymoon. Cabinets had defects, began to show after installation while he was away. (? from being left out in cold truck overnight in winter, finish starts cracking after installation.) Showed him when he got back. Everything halted. Had to wait 2 weeks for cabinet rep apt., then kitchen installer forgot about it and had to wait another 2 weeks for new appt, then reorder cabinets, tear old old cabinets, reinstall new cabinets. Then it is Christmas and everyhting on hold for holidays until after new years. Then trouble locating granite slabs. Not as much turnover in granite in winter, not as much granite being mined, etc. Decide to go to with quartz. Call Costco where quartz is in price range, previous estimate no good, installer out of business, will call when they have a new one. Run around getting new quotes. New quotes, 700.00-1500.00+ more than Costco. Costco gets new installer, paid in advance, must order material, not in stock, 1 more week. Template done. Material comes in. 10 more days for installation apt. That is next Monday AM. Plumber scheduled for Monday afternoon. Livingroom floor now finished installing except for trim. Finish must wait until after counter installed now so it is not messed up by installers. Now finisher can't do it for 2 more weeks after countertop because he is booked.

    That is only some of it.

    IF you don't have cabinets that are defective, IF installers aren't sick, in an accident or otherwise unble to work, IF all materials including countertop is picked out, in stock and already approved, and IF they don't find any unforseen problems while doing this, you might be able to do it in that time with the limited work you describe.

    I wish you good luck and speedy remodeling. :)

    Sue

  • 18 years ago

    Sue: OMG. Reminds me of our 3 week bathroom redo last year that ended up three months later with me meeting the contractor at Starbucks (since we didn't trust his behavior in our house with our kids present) to give him a check for $2000 as payment in full on the $5000 he claimed to be owed and to tell him to sue me if he wanted more. Still not finished, a year later.

    So...since our kitchen demo starts Monday (with a new and reportedly fast contractor)--hoping for the best (8 weeks) but planning for the worst (T-giving?)

  • 18 years ago

    you're so cute....TWO YEARS!!!!! and i have a couple months to go!

  • 18 years ago

    isn't the rule of thumb to double the number and increment the units. So if you think it is 2 weeks, then it will take 4 months. I told my DW that it would take a month for me to do our bathroom. Well, after 3 years I finally finished it.

  • 18 years ago

    Mine took 3 weeks but my dh did all of the work. The countertop was installed exactly one week after templating.

    I didn't mind not having the kitchen as much as I minded having everything that used to be in the kitchen stored in every other room in the house. That drove me nuts! Once everything was in, I had to wait a few extra days for drain to cure (silicone) and not having a sink when I was so close to being done also drove me nuts. I now know that I couldn't live through a major reno.

  • 18 years ago

    My kitchen remodel (R&R cabs, new tile, floor, etc) took 2 weeks...in 1989. Seriously. I don't know when things got so complicated. This one was originally estimated at 4-6 weeks by GC. I got running water in the 8th week. I had about a 1 week delay with a flooring change, but otherwise things have moved forward, and it looks like it'll finish in the 10th week. (This does not count a few incidentals in the adjoining FR.)

    I haven't moved things back into cabinets yet (even though I'm sorely tempted). First, I want the drywall dust phase to stop. Then the trim guy/finish carpenter comes out to install knobs and pulls, which could put sawdust into drawers. Only then will I give everything a deep cleaning. I have started using the trash/recycle bin, because who cares if the trash bin gets filled with dust :) and I started to use the DW the moment it was hooked up again.

  • 18 years ago

    get ready for no kitchen...get the big stack of paper plates at Costco. It WILL take longer than it should...there's no getting around it. Plan for longer and if it's shorter you will be happy. You could probably hook up old sink, etc while waiting for the new stuff...good luck and welcome to the club of remodeling @#$%^&*.

  • 18 years ago

    We did demo in February, and we just had cabinets delivered yesterday. Some cabinets. And boy is there lots left to do after cabinets. And they tell me that installing my cabinets will take two weeks!

  • 18 years ago

    We had a great crew - two weeks start to finish except for granite. That included demo cabinets / floors / etc, new floors, relocating some electrical and gas line, removing a bulkhead over the old island, installing everything, etc.

    Granite took some time from templating to install - 3 to 4 weeks. We used plywood counters and they hooked our old sink back up in the interim

  • 18 years ago

    Hahahahahah! Heeheeheehee! >


    OK...IF all components are delivered and ready to go (and inspected for damage, etc.) AND there are no problems (like finding unknown pipes/electrical in the way OR walls that aren't true & need to be fixed) AND all measurements are correct (a BIG one!) AND a great crew AND they have no other jobs to split their time between....MAYBE you'll finish on time...maybe 3 or 4 weeks (no layout or major plumbing or electrical changes).

    You will also be at the mercy of your county inspectors...when are they available for preliminary and then final inspections? [Ours were actually very good...they were out the next day...of course, we haven't had our final inspection yet...]


    I'm not being cynical (or at least I'm trying not to be), but you need to be realistic and expect delays (expect the worst, hope for the best!). We were w/o water on the first floor from 1/21/08 until Good Friday (3/21/08). We do have a sink, DW, and ovens now...but still no cooktop and only partially installed granite.

  • 18 years ago

    I'm one of those rare lucky ones whose GC promised to have it finished by a specific date and actually delivered. He would have been done early, except for a delay from the cabinet guy. In addition to the regular cabinet removal demo, I had a wall and hardwood flooring removed and the materials preserved. All remaining walls were drywalled, tongue and groove ceiling was installed, travertine tiles were laid, cabinets, soapstone counters, lighting, plumbing, and appliances were installed. The whole project took five weeks from start to finish.

    Most of the "action" happened in a two-day period. In fact, in almost exactly 48 hours, I went from this...

    to this...

  • 18 years ago

    Ugloochic, Holligator is making me cry again. Make her stop. I am telling!

    Sue

  • 18 years ago

    Aww, Sue, I'm sorry! I promise not to flaunt my speedy kitchen any more. :)

    If it makes you feel any better, I am still waiting five months later for them to come fix two things (the phone jack they installed doesn't work, and they never finished closing up the old stove vent on the outside of the house). Since they are all paid up and those are pretty minor things, they're in no rush to get here. All I have to hold over them is my CD full of kitchen pictures that they want. I also don't have a backsplash yet, but that's my fault because I still haven't picked one out.

  • 18 years ago

    We started ours on Jan.5, still not done but 80% complete.This is a total diy remodel with walls, plumbing, and electric moved.Just hang in there

  • 18 years ago

    We DIY'ed ours, and in one week demo'd, did minor moves to plumbing and electrical, tiled the floor, and installed the cabinets (we both took the week off from work and worked 12-hour days). It did take us a couple more weeks of working evenings to finish up all the trim details, and the granite counters came 3 weeks later. There were a few missing parts for cabinets that we waited for too (the final decorative panel just arrived last week...6 months after our remodel). I must confess we haven't done the tile backsplash yet.

    There was someone here back a few months who got a new kitchen (counters included) in 3 days!

  • 18 years ago

    We started gutting the fall of 03'. I've lived with my "deer camp" kitchen for a long long long time. Upper cabinets are being installed as I write. I feel like someone that's lived in a cave for the past five years coming out into the light...."is that a kitchen I see???" Holligator, you've done about as much damage to the grading curve as I have!!!

  • 18 years ago

    I was very fortunate to get a very honest, hardworking GC who did ALL the work himself except for the new HW floors, plumbing and sheetrock taping/mud. He started demo on April 1st, and finished up May 9th for the most part (except for a few pieces of trim, etc.) He worked some Sats and Sundays, though. He also put in our old sink in the plywood once the cabinets were installed. I again repeat how fortunate we were to find him. I think it was good luck to balance the past 20 years of bad luck I've had with different contractors. (Can I tell you the story about the one who put our roof shingles on wrong, and left with our money? Or the one who took SIX months to build a screened porch? Yikes!) One other important fact though, all the kitchens on GW are so different in scope, the time factor can't be compared too precisely.

  • 18 years ago

    Well, some of you are scaring me! I actually love our contractor, he has done other work for us in the past, most notably coming to our rescue when a thief, er...contractor demoed our master bath and then disappeared. That remodel took from July until March! He isn't the fastest guy, although he is a perfectionist and 100% trustworthy. We don't pay him a penny until the job is complete. (did I mention we love him?!) I know something unexpected always comes up and I am trying to prepare, but the kitchen is such an integral part of a household. It will be a challenge to manage if there are big delays. I'm thinking I may have them inspect all the lower cabs when they come in to make sure everything is there before any demo begins. As long as the lowers are in, they can template and a few things can be hooked up.

    Thanks for all the stories!