How much extras after signing contract

11 years ago

We are building a new home. We spent over a year with the builder asking questions and getting the house exactly the way we wanted it. It's a track house in a planned development.


There have been several extra costs that have come up after we started the build - some examples are paying to remove fill from the lot (which we asked excavation costs and were told much less then what they are trying to charge), some of the kitchen stuff had to be added on (because they forgot to put in pulls and a one of the cabinets cabinet).


I was just curious what others experience was. We are not contractors/builders and we assumed that there would not be as many charges as there have been.

Comments (13)

  • 11 years ago

    Did your contract have allowances? Ours specifically says who is in charge of what, but we've never built a tract home. Like electric we are in charge of (we got with electric company prior to signing contract) then builder is responsible for clearing lot. I'm sure things Will still pop up but we've felt our builder was very honest and addressed most of the potential issues before we signed.

  • 11 years ago

    If they forgot to include pulls and a cabinet that should have been in the contract that should be on them.

  • 11 years ago

    Excavation and moving and removing dirt is one of those variables I think. In many contracts excavation will not be fixed and there will be wording to that effect. They say they don't know how the dirt is going to be until they start digging. In our case, removing excess fill dirt plus a deeper excavation because of architect errors cost over $8,000 more than planned. I have seen other commenters say the same things.

    As for cabinet pulls...who does cabinets without cabinet pulls? They should be part of the kitchen package. However, we chose to buy our own pulls (the cabinet maker charged an outrageous amount for each pull) and get a couple extras (customizations for drawers and cabinets) instead of getting the supplied pulls.

    Good luck!


  • 11 years ago

    Thanks!

    Yes, there was wording in the contract about excavation costs. That is why we asked them. I did have an earlier post on this and it was common that this is a variable. The builder owns the land (they are mid way through developing the development) thus why we thought the estimate we got would be close to what we would have to pay (but, it was double).

    One would think that things forgotten would be their problem however, if we want it, we have to pay for it.

    I am super excited to get into our home b/c it's everything we want but, I'm not sure I would ever build again (hopefully won't have to). It just all keeps adding up.

  • 11 years ago
    Hmm so they put a specific cost to it? Ours just says builder pays excavation costs. Hopefully that's your last unexpected cost... :/
  • 11 years ago

    Our builder is covering everything. We have allowances for kitchen cabinets and lighting fixtures, which includes ceiling fans. We pick out what we want and if we go over, we pay the additional on those. Everything else is at builders expense, if he goes over or forgot something, that is on him.

  • 11 years ago

    I'm building with a large national builder so things are pretty clear. I haven't gone to the design center yet so I don't know what specific things are included (I'm not sure about the backsplash for example) but I know that all the major things are there and I have a selection to choose from. If I want to go up in level or add things it will be extra.


    I paid extra for 9ft basement pours and extending the garage 2 ft. But things like fill removal are included.

  • 11 years ago

    The builder should give you a full accounting of any additional cost. The most common reason for additional excavation costs is the removal of unstable (organic) material, the addition of granular fill and additional compaction. Ground water can be another issue. But you should have been given a statement of what additional work and material caused the charge. Millworkman is right; you should have a contingency amount in your budget. In this case it might be less than 20% since a tract house should have fewer surprises but you should always have access to 20%. No one knows what is below the ground without drilling and taking soil samples.

    The issue here is that the developer's profit per house from tract housing is not high and therefore additional costs that might be absorbed in the price of a custom house are passed on to the new owners.

  • 11 years ago

    Thank you all for your insight.

    I think our problem with all these extras is we asked a thousand questions (maybe even more). The community sales manager we were working with probably just answered questions to suit the sale (which is NOT our fault).

    We do not have any contingency budget because we were given a price, went to the design center (and added a lot more) and then thought we were pretty much done with the costs. We were never told that the extras would amount to this much. The company is reviewing these costs so we will see what happens. They have build 40+ houses in this development so should have known what they would find.



  • 11 years ago

    loveumms, you would like to think that they would have the costs down pat (and truthfully they probably do) but like I said "expect the unexpected", they are in the game to make money and the way a tract home builder makes money is not on the quoted base price. Change orders and the "unexpected" are where they profit the most from. Unfortunate but true.......

  • 11 years ago
    last modified: 11 years ago

    I'm keeping a running tally of ours on our blog. Some are "unexpected" and some are just purchases we made outside of the contract because they were a good deal, and they'll be "recouped" based on our allowances.

    Out of Pocket Costs

    North Georgia House

  • 11 years ago

    we had 2 very long meetings with our builder before he wrote our contract indicating our expectations as far as finishes, appliances, screen porch etc additional costs incurred during construction would be paid for by the builder unless they were a part of the "allowances" we were informed in advance of the approximate cost of every "change" we wanted to make we came in about 5 percent over the initial contract and most of that was a covered elevated breeze way 20 ft long and 10 ft wide both it and the front porch (almost 700 square ft total) were bricked we also enlarged the driveway (almost doubled it in fact) and asked for 10 ft wide doors on the garage and the driveway is about 1/3 wider than a normal build we would probably have come in under the contract price without the changes