tbaker_04

Major kitchen beam issue - 8ft ceiling, 12" beam - HELP!

9 years ago

We have a major kitchen dilemma. We have a small kitchen that we bumped out the back of the house to gain a little extra space. So the issue is that now we have a large support beam running right through the kitchen where the exterior wall used to be. There is also some plumbing from upstairs that will need to run along side it. This means that in our small kitchen with 8-ft. ceilings, we will have an approximately 12"x12" (hopefully no bigger!) beam running right through it, and not in a convenient spot. We have to figure out how this is going to work with the cabinets. Originally we wanted to go the whole way to the ceiling with them, and we still want to maximize storage, since it really isn't a large space. I've seen many posts about similar beam issues, but they all seem to address nice, we'll call them "dainty" beams, not behemoths like this one.

Below is a recent picture of the construction site. The ladders that are lying down are under the future kitchen window.

Below that is what we were thinking for the rough kitchen layout. We have a 21" (face measurement) full-height corner cabinet for small appliances (kitchen aid, toaster, coffee pot, etc. to be tucked away but still plugged in). There's then a 7" slanted base cabinet on either side to bring that corner cabinet out to standard counter depth, where we were just going to store cookie sheets, muffin tins, cutting boards, etc. The total measurement of that, for the base comes to about 39" from the corner. That will probably come to about right about where the beam starts on the ceiling, maybe up to 1" within it, depending on the drywall.

Comments (11)

  • PRO
    9 years ago

    If you could rerout the plumbing, you can probably install the beam flush with the ceiling joists.

  • 9 years ago

    Thanks. I'm not sure that we can, though. Both the bathrooms, the water infeed, and the waste drains are located along the back of the house there. And I don't think they can route them through the joists because of the size hole they would have to drill through the joists there.

  • 9 years ago

    Is the beam already installed? Is that the beam we are seeing in the photo? If so you should go measure it.

  • 9 years ago

    Yes.

  • 9 years ago

    What did you end up doing? I am in a similar situation and would love some ideas! Photos as well, if you have them. Thanks.

  • 9 years ago

    We are still in progress, so I can't post actual pictures yet, but here's a drawing of what we're planning (top down view and front view).


    Where the beam actually ends up falling lines up pretty close to right beside the range/microwave. So, The rest of the cabinets go to the ceiling, but that one we made the whole width available to the corner, but made it only go up to the beam. Then in the void beside the beam, we're putting a little "dummy" cabinet. I asked him if there was a way to actually make the "dummy" door functional and leave it open behind there so that we had the space to put something there if we want, since the kitchen isn't very big, and he's going to try to do that. I'll try to remember to post pictures when it's all done!

  • 9 years ago

    Thanks. Mine may be done first, though! Beam went in this week. I am meeting with contractor and cabinet person on Friday to brainstorm ideas. Unfortunately, I have 7.5' ceilings so it makes our choices under the beam a little more limited as we are looking at a space about 23" high from counter to bottom of beam and maybe 9" wide.

  • 7 years ago

    What did you guys end up doing? Would anyone mind posting pictures? TIA

  • 7 years ago

    Did you find a solution for this? I have a similar situation and could use some tips

  • 7 years ago
    last modified: 7 years ago




  • 7 years ago

    That looks good, a nice solution. Thank you!