hsh2012

Fee schedule for architectural services?

8 years ago
I am interested in architectural services for a new home build from a firm I have spoken to. However their fee schedule seemed high to me for the very first payment but maybe this is normal? The fee structure is as follows:

Phase 1: Zoning analysis, field measurement and documentation of existing conditions
Phase 2: Conceptual design
Phase 3: Design development
Phase 4: Construction documents

Fees will be set based on square footage of home build. Prior to beginning the work, they require a 40% payment. Next payment is after phase 2 is completed (40%), and remaining 20% is due after completion of drawings. Thoughts? Thank you!

Comments (25)

  • PRO
    8 years ago

    Do you think the price is high or do you think the schedule is high? It falls within the range of normal, but normal has a very wide range. See if they are open to negotiation. As long as you agree with the bottom line price and nothing goes wrong, everything should be fine. Keep communicating and everything will be fine. I hope they design a home you love . . . forever.

  • 8 years ago
    last modified: 8 years ago

    As a builder, I usually paid nothing up front, balance on completion to the architectural technologists I used. (I guess I had good references!)

    Current project by an architect

    12.5% deposit

    37.5% after accepted conceptual, floor plan and elevations.

    50% and 13% tx. on total price after permit-ready building plans.

    Other architects had many more stages and pages of legalese as if they were designing a skyscraping officer tower. One wouldn't even permit me to see the floor plans other than in their office with no copies or photos taken. Jeeze Marie!

    hsh2012 thanked worthy
  • 8 years ago
    We went with a designer not architect but o would hazard a guess you are also getting that form a design build firm. We didn’t pay anything till work was done. We got a range of fees for architectural and interior work a min and max and Knew we would be in that. Work commence and we were build monthly based on work done to the maximum in some areas and well below in others.
    hsh2012 thanked User
  • 8 years ago

    Mark......you're an architect. (but normal has a very wide range).......HITH is that 'normal' if it has no definition? That makes NO sense. Are there NO regulations with architects? They ALL make up with what they can get away with in their locations? If that's the case it makes more people leery of architects which shouldn't happen if architects are out in the open country wide. I agree with the bottom line price. Can you explain to us what is actually 'normal'?

  • 8 years ago
    Thanks all. I’m ok about the fees (which is not a small amount) - it’s the initial 40% percentage I have to put down for what looks to be just phase 1 (zoning analysis). By end of phase 2 (concept design), I would have paid 80%. We did try to negotiate the payment structure but the architect would not budge on it. We are trying to see what the industry standard is. Thank you!
  • 8 years ago

    All design work is usually front loaded on fees. Or, should be. Most of the real work is mental, in the first stage. The documentation of the mental work may look like more work, but it’s not. You’re not paying an architect for drafting documents. That’s a drafter, who takes dictation. You are paying for the thought that went into the concepts that get turned into drafted documents. And if you got the concepts and decided to terminate the contract, you should pay the most for that.


    hsh2012 thanked User
  • PRO
    8 years ago

    What happened to Phase 5, Bidding Assistance and Phase 6, Construction Observation?

    hsh2012 thanked Virgil Carter Fine Art
  • 8 years ago
    last modified: 8 years ago

    IIRC, our architect was 10% of the target build cost with a 12% down payment. They billed monthly for hours + costs incurred during the previous month. There were some things where they notified us ahead that something would be extra cost.

    hsh2012 thanked opaone
  • 8 years ago
    last modified: 8 years ago

    Very well said Holly.

    Question for robin0919: In what industry do you work that has government mandated fees/pricing?



  • 8 years ago

    There are some industries that do. Insurance, banking, utilities, airlines, and many more are regulated to protect the consumer.


    In this case the OP is free to decide to use an architect and which architect they want to use based on references and their own agreement to the terms.


    I would shop around, compare, and make your own decision as to if this particular architect is the one you want to move forward with.

  • 8 years ago
    last modified: 8 years ago

    adkbml, I agree that there are government regulations in many industries, but there is a huge variance on fees in Insurance, banking, utilites, airlines etc. Huge. I could give examples but it isn't necessary. You can google (for example) homeowners insurance in Florida for a given property in a zip code and compare with a similar property in another zip code in the same state and come up with vastly different prices. Compare in different states and you have even more variance. Same thing with airlines, banking fees, utility fees etc.

    The thing is, do we want the government telling private companies what to charge for their intellectual work? Let the market do its job as Holly Stockley pointed out. We then have much happier buyers and sellers with the freedom of choice.

  • 8 years ago
    last modified: 8 years ago

    hsh2012

    If you don't like the fee schedule, move on.

    BTW, expect to make the same downpayment for custom building items such as kitchens, staircases and windows.

    Medical charges are set in excrutiating detail by the government here in Canuckistan with caps clawing back most of the fee when the practitioner's gross billings hit the mandated annual limit. Of course, everything's "free". It's Venezuela that works.

    hsh2012 thanked worthy
  • 8 years ago

    I have no dog in this fight but government regulations for occupations regulate the REQUIREMENTS for practicing that profession - i.e. education and licensing.

    Medical and legal professions are regulated in terms of educational requirements and licensing but fees are not set by the government although medical is a bit of a gray area since fees for Medicare and Medicaid are set by government since the government is paying for those services. However the same doctor not providing services reimbursed by the government is free to charge what they wish - or more accurately what each insurance company they contract with negotiates.

    Hairdressers, plumbers, electricians are all licensed by the government but have no governmental restrictions on fees charged to end users.

  • 8 years ago
    @Virgil Carter Fine Art - thanks for raising phases 5 and 6 - it looks like as part of their services they do no help with the bidding process. Answering basic questions posed by contractors is included in the contract but it looks like they will not oversee the construction. Should we be concerned that these phases are not included in the contract? Thanks
  • 8 years ago

    Dear hsh2012,


    You should select a builder or at least have multiple builders prior to this. The fee scheduler: "Prior to beginning the work, they require a 40% payment. Next payment is after phase 2 is completed (40%), and remaining 20% is due after completion of drawings. " - may be alright, but how do you know if your architect designed you un-buildable house?


    The feedback from the builder could be priceless at this stage. You want architect and the [selected] builder to work together and come up with a plan that fits your budget. Most ppl have to work with the constraint of money. I can create a amazing rooms with 25' ceilings. Most will run out of money trying to complete it.




    It appears that this firm bails out after the "Construction documents" phase. You may be wasting a lot of your money on this "project".


    hsh2012 thanked BT
  • PRO
    8 years ago
    last modified: 8 years ago

    "Can you explain to us what is actually 'normal'?"

    Normal is the usual, average, or typical state or condition.

    “Usual" is habitually or typically occurring or done; customary

    “Average" is constituting the result obtained by adding together several quantities and then dividing this total by the number of quantities

    “Typical" is showing the characteristics expected of or popularly associated with a particular person, situation, or thing

    "State" is the particular condition that someone or something is in at a specific time


    “Condition" is the state of something with regard to its appearance, quality, or working order

  • PRO
    8 years ago

    "...Should we be concerned that these phases are not included in the contract..."


    Have you been on this forum for awhile? Have you seen the frequent postings about problem issues with bidding, such as allowances which are far under bid, and result in subsequent change orders and unexpected added expense?


    Have you seen frequent postings about unexpected and undesirable construction issues during the construction phase? There may be more postings on this subject than just about any other.


    Builder's do not have a fudiciary responsiblity to an owner. They do not place an owner's interest foremost. Buillders place their own business interests foremost.


    An architect has a fudiciary responsibility to a client who contracts with the architect for architectural services for a project.


    What is fudiciary responsibility? From Wiki: Fiduciary. An individual in whom another has placed the utmost trust and confidence to manage and protect property or money. The relationship wherein one person has an obligation to act for another's benefit.


    Does this help answer your question about the importance of architectural services during bidding and construction?



    hsh2012 thanked Virgil Carter Fine Art
  • 8 years ago
    last modified: 8 years ago

    Virgil, not sure I understand. These articles seems to indicate that prior precedence in two cases leans towards a fact that there is no fiduciary responsibility between an architect and their client.

    http://www.constructionlawyerblog.com/2007/06/fiduciary-duty-.html

    http://www.theaiatrust.com/whitepapers/fiduciary/authority.php

    I can see a contractual obligation (as outlined in any contract no different than with a builder), but not a fiduciary responsibility.

  • PRO
    8 years ago

    Virgil... both the optimal architect the optimal contractor will have the clients best interests in mind.



  • 8 years ago

    My builder did! I can see some that may not though.


    I like Holly's advice. If their character and previous work gives you a good gut feeling then make it happen!


    I personally wouldn't move forward with any designs unless a builder or contractor was involved in the process.

  • PRO
    8 years ago

    Jeffery is certainly right: there are builders who have client's best interests in mind. But they are not fiduciary agents.


    And how many posts are on the forum about builders and their subs who obviously do not have their client's interests in mind? How many current threads are there with construction-oriented issues?


    I think the record speaks for itself.



  • PRO
    8 years ago

    I like to keep billings in line with the amount of time required to get to a certain state of completion. For me this is (values are cumulative):

    • Pre-design - 5%
    • conceptual design -20%
    • Design development- 50%
    • Preparation for engineering -60%
    • Draft contract documents -90%
    • Final coordination and publish permit set 100%

    I ask for a 10% retainer which covers half of the conceptual design. My clients and I have equal "skin in the game" at this point. I've never had a client say "thank you very much for the great design, we'll have someone else draft it and stiff you for the remainder of it".


    I charge hourly for construction observation and contract review.


    The arrangement in question is very heavily front loaded. Either this architect is charging very little with thin margins, has had some bad experiences, or is so in demand they can ask for whatever they want. I suggest you talk to some of their clients and talk to some other architects.

    hsh2012 thanked Summit Studio Architects
  • 8 years ago

    Summit's schedule seems to be reasonable and doesn't get 'ahead' of the work. Doing this house project and dealing with a variety of contractors - I don't pay more than work completed. Pretty good words to live by, generally.

    hsh2012 thanked just_janni
  • 8 years ago

    I was looking into the very same question recently and came across these numbers from the Royal Architectural Institute of Canada.


    Phase

    Schematic Design 12 -25%

    Design Development 12-25%

    Construction Documents 35-45%

    Bidding and Negotiation 2.5 - 6%

    Construction Phase 25 - 35%


    http://www.mbarchitects.org/docs/guide_architectservicefees(e).pdf

    hsh2012 thanked rycm