Full house remodel Estimates

6 years ago
last modified: 6 years ago

I have finalized plans and have been getting estimates and find them to be vague. In pushing for further breakdown I will get things like Bathroom: 20,000 with some items listed. Is this typical or should I expect more of a breakdown by trade, plumbing, electrical, foundation, framing etc I ask because I feel that numbers seem high but will the vague breakdown it is hard to know since plumbing will be part of every bathroom as will framing etc. For Southern California for total remodel is there just a price per sqft I should be expecting? And are numbers quoted typically with finishes or without finishes?

Comments (31)

  • 6 years ago

    If it were me I would want a breakdown of cost for each area to be remodel with understanding that it’s just estimate and the cost could jump.

  • PRO
    6 years ago

    Eric:


    I never provide a free estimate, however, I will trade information. You'd like to know how much I'll charge to meet your specifications. That will take me some time to figure out. I'm not going to risk spending that time unless I'm sure you're a reasonably safe investment of that time.


    You'll tell me how you found me and answer any of my other qualifying questions. When I'm satisfied with the answers, we'll trade.

  • PRO
    6 years ago
    last modified: 6 years ago

    Are you sure that you have biddable documents from your architect? Everything you want to have happen is fully drawn and diagrammed, ready to be permitted? There is a massive list of all products and finishes specified from the architect and interior designer? You’ve got a book of all of this that you are paying for contractors to study for several weeks before submitting hard contractable numbers?


    If you don’t have full architectural and design documents, and you’re not paying for their time, you will get vague round numbers with allowances (guesses) as holding places for future to be specified products or choices. Any whole home renovation project is so very expensive and involved that many people investigate doing a teardown as a price competitive choice. Good luck!

  • 6 years ago

    @User I actually waited until now because I have a detailed architectural and structural plan set. Initially I was getting fixed price with a bullet list below and when asking for a break down I received numbers but was more per room which is hard when we are replumbing the whole house and changing layout etc. I have gotten subcontractor estimates for certain trades and compared and I had a subcontractor say foundation was double what one bid was and half what the other was. Yet, both bids end up the same overall. Are these numbers essentially individually made up with the goal of arriving at a likely number that will cover the whole project and I should not try to dissect as much?

  • 6 years ago

    @User The initial bid bascially included everything in the plans except finishes and had a number. I asked for a breakdown because I wanted to know if it was reasonable but the only way I know that is if for instance it says plumbing for X of foundation for Y and I know those numbers I can find out if it is fair. Saying a huge number with no breakdown is confusing where the money is going, I am sure it will be quite costly but makes me nervous sans breakdown. If that is normal I won't worry about it but had heard to get a "detailed" bid in the past.

  • PRO
    6 years ago
    last modified: 6 years ago

    A detailed bid is paid for time from a contractor. The cost is usually credited to the project total when you select the contractor. The exception is when you’ve hired the contractor as an ongoing cost control consultant to the architect as the plans are developed.

    An estimate is a rough guess, with few details, and without the subs visiting for costing to provide hard numbers. Which are you trying to get?

    Also, it doesn’t sound as though you have a finishes schedule? The difference between builder grade from a lower grade contractor and an upper end contractor used to giving an upper end result can be hundreds of thousands of dollars just in the finishes categories alone. .

  • 6 years ago

    @User So once I officially hire the contractor they give a detailed bid? How do we sign a contract and agree on a price without a detailed bid? When I ask subcontractors they given detailed bid with precise estimates. For a GC is the standard bid just an estimate with an overall number but not a detailed break down?

  • PRO
    6 years ago
    last modified: 6 years ago

    You have no obligation to hire the contractor after the detailed bid is prepared. But if you want harder numbers, that’s how to move beyond estimates. It takes a huge amount of time for detailed bids. Most people that want that amount of information, or have cost concerns about the project, just don’t end up moving forward with their project. This is why the busier better contractors have created an entry cost to begin a project exploration. It requires an investment of money for their investment of time.

  • 6 years ago

    Eric I feel for you. We, like you, wanted to understand the actual costs before going ahead to compare to others and to make sure we were comfortable with it. We got a lot of push back too. In the end we settled with looking at budget for similar projects from different builders to make sure they could build around our budget with similar finishes. We then agreed to hire based on that. Many months later the budget was revised once we had our specifications and the line items went up and down depending on the reality of what we chose. We still ended up pretty close to the starting point other than two unexpected overages that were unavoidable. It’s hard though as you normally want to know what your total costs to buy something will be and in renovations and building you don’t seem to get that so it is scary

  • 6 years ago

    Eric, slight difference in terminology. You are not officially 'hiring' your contractor, but you are committing to use him as your contractor, with hiring him to actually execute the job dependent on you both reaching an acceptable price for the remodel of your home (i.e. you are not in the 'interviewing for a GC phase'; you've already researched potential contractors, interviewed them to determine if there is enough interest and compatibility, have gathered reviews from previous clients, and seen first hand examples of their work). Once you pick the GC whom you feel is the best fit, then he will commit to reviewing your build package and provide the cost breakdown (with allowances because material costs fluctuate) you desire. After several iterations, you will agree on the contract price, then you are off and running. Forget the cost/sq-ft approach, because it varies between National City, and La Jolla, Fallbrook and San Marcos, El Cajon and Dana Point, Lemon Grove and Huntington Beach, etc. Best Wishes and Good Luck.

  • 6 years ago

    I would ask the contractors what it would cost for a detailed bid. Since it takes time to consult subcontractors and evaluate plans, they will want to charge you for their time, which is reasonable. If there is one contractor who you like, you might start with them. Sometimes they will refund or reduce the fee if you hire them for the project.

  • 6 years ago

    @User This is helpful. I think my major concern is that I will pay more than the 20-30% markup by having items not be transparent. The presumption is I am using this contractor and am not negotiating multiple against each other. Just that some of the numbers of the breakdown are outlandish and I could just replace the Sub with one I have worked with in the past for cheaper and know is good. I did not know how this would be accounted for if there are not line items.

  • PRO
    6 years ago
    last modified: 6 years ago

    Who will be performing the large remainder of design services for product selections and finishes scheduling? The architectural floor plans are essential, but are only half of the puzzle piece of costs. Narrowing down if you want $5 builder grade wood floors vs $12 mid grade wood floors, plus prep plus install labor, which can change of the product changes, is the rest of the money in the overall budget. Price shopping a project that hasn’t been fully specified is an exercise in futility and sticker shock. Which is why most contractors would not wish to be involved without compensation.


    A lot of this sounds as if you want to be the GC, rather than hire a GC. Owners don’t get subcontractor bids. That’s the GC’s role. Hiring and firing, and the job control that goes with that. That’s likely also sending a mixed message to any contractors that you are speaking with.

  • 6 years ago

    @User incorrect I had three bids, chose one, decided to move forward with that contractor and when asking for a detailed bid I was discouraged as some numbers were way higher and also way lower than they should be based on what I know. Now trying to figure out if I should worry about this or not.

  • 6 years ago

    Eric people here tend to look for an issue. You’ve done nothing wrong and in fact a ton right but still there will be those that find fault with your process.

    Since you are now set on this contractor I find it shocking you aren’t getting more detailed information, assuming this is not a fixed price contract? If it is fixed price you are owed nothing more. If it is cost plus you should get to see all invoices and there should be transparency.

    You should not use your own subs. If you want to manage the project on your own you get your subs. If you hire a GC you get theirs. You also get their working relationship with that sub and hopefully a good end result.

  • PRO
    6 years ago

    My customers get one chance to ask me for a cost breakdown, but they go on double secret probation anyway. If they ask again, they get their down payment refunded.

  • 6 years ago

    Joseph do you use fixed price then? I’m assuming so and that is totally fair. But not at all the same as cost plus contract.

  • 6 years ago

    I remodeled most of my SoCal house over the last 8 years. No walls moved. I had a designer do scale diagrams of the rooms showing the changes and tile locations. I used those documents to get bids. The bids were detailed enough breaking down the different components, such as demo, plumbing, electrical, cabinets, tiling, painting, etc. I bought all the fixtures myself, so there was no need for them to guess on those.


    The secondary bathroom were around $20K for all the labor, master bath was $40K and the kitchen was $50K ... no materials (fixtures, appliances, tile, cabinets) included, except for things behind walls such as plumbing, electrical, 2x4s, etc.

  • PRO
    6 years ago

    The definition of "price per sqft" is "a guess".

    Prices are geographically dependent, ask someone local.

  • 6 years ago

    Are you asking for remodel estimates that include demolition of existing portions of the house, and then new construction in the same areas? Cost estimating for new construction is challenging enough, but trying to estimate the cost of a remodel is really difficult until you get into the job and know more about the existing structure. Many unexpected problems get uncovered during demo that will have a big impact on the new work.

    Bruce

  • 6 years ago

    Even though price per square foot is a guess it’s a starting point. For example if someone thinks they can build for $150/sq foot and local trends are more like $300 they need to have a new plan. On the other hand if they are more like $275 they probably can find a way to make it work. I think price per sq foot weeds out the folk who have no actual idea at all on costs.

  • PRO
    6 years ago

    Guesses can be misleading, and they become a bigger problem when people base their future on them. Square footage costs are offered up buy those that are hundreds of miles away and do not even know what materials are selected. If the OP has "finalized plans" and the estimates are vague, chances are the plans are vague. Square footage cost is a good starting point as long as it is based on information descriptive of the owner's expectations of the house and the scope of work.

  • 6 years ago

    @Mark Bischak, Architect the Plans are not vague. The bid does not say plumbing x, foundation y, framing z which is what I expected but instead it is more like bathrooms x, kitchen y so it is hard to splice out what things are actually costing but maybe that is normal

  • 6 years ago

    What does your contract say expectations are? Have you asked for more info? I wouldn’t be okay moving forward without more transparency unless it was a fixed contract

  • PRO
    6 years ago

    The bidding instructions would spell out the format of the bids.

  • PRO
    6 years ago

    Also the fact that your project is a remodeling would dictate the format if the bids; at least in the eyes of the bidders.

  • PRO
    6 years ago

    Whole-house remodels are a pain to estimate. I would rather estimate the cost to build two new homes than a single whole-house remodel.

    One approach is to divide the overall scope into a series of smaller remodeling projects where the cost to execute each is estimated based on similar projects. So the quoted price is the sum total cost of a (similar) kitchen remodel, a (similar) bath remodel, a (similar) master bath remodel, etc. This approach precludes any line-item scrutiny of the estimate which is probably a fool's errand anyway because different remodelers will include different tasks under different line items. For example, one might have a line item for demolition that includes any required drywall demolition and another might have the demolition included in a drywall line item because they or their trade partner performs both the demolition and installation of drywall.

    That said, each quotation should make clear what is included for fixtures, appliances, cabinetry, etc. either by stating the specific make/model information or as a cost allowance.

    Best wishes for a successful project.



  • 6 years ago
    last modified: 6 years ago

    You will have a huge BOM (bill of materials) - tile / windows / floor coverings / light fixtures / bath fixtures / kitchen .... on, and on, and on. Those all have to be spec'd out.

    I'm a software developer. I can tell you that the larger the project the more cost overruns, and delays for the final product.

    I bill time and materials. If you want a fixed price - I may double the bid. If the project is huge - I don't know anyone who will make a fixed price bid.

    If it's possible I'd do the remodel in phases. That way you can 'get your arms' around the project, get a more detailed estimate, and supervise the construction (do this after hours - just to see the quality and progress of the work).

    What you don't want to do is have a huge project - and just wait for it to be done, with no involvement.

  • 6 years ago

    Any project with only architectural layouts, and no finish schedule, is too incomplete for accurate pricing to occur. Once the finishes are known, that adds additional labor, and the “bid” can easily double in price. Blueprints only is like blueprints for a custom car. Without knowing if the body is to be fiberglass, or aluminum, or custom stamped steel? Without knowing if it’s a radio delete hose out interior or the finest Corinthian leather and walnut burl? You have no clue what the end cost will be.

  • 6 years ago

    "Whole-house remodels are a pain to estimate."


    Borderline next to impossible without demo, at least selective demo first. You never know exactly what material and in what condition you will find inside a wall, under a floor, behind drywall or tile.......................................

  • PRO
    6 years ago

    I agree wholeheartedly with the need for investigative demo. We do a pretty thorough investigation of existing conditions--mostly visual, and making use of fiber optic cameras, lasers and other high-tech tools where we can to do so in a minimally-invasive manner. Plus, there is always a shovel at the ready.