Contact with Construction Manager/Expeditor

13 years ago

We are about halfway through our build and I have found that lately I have been e-mailing/calling out construction manager quite frequently and feel like I am starting to annoy him.

I should note that unless I contact him we have no idea what is happening at our house unless we take time out of work to go out there during the day. Should he be updating us on when things are happening?

I contacted him 4 out of five days this week to see where things were with our inspections, concerns, etc....
He seems agitated in both e-mail and voice correspondence.
What is normal?

going in to the process I felt lilke we would at least get like an update once a week just to let us know exactly what was happening for that week, but at the last minute our builder hired this new construction manager (who supposedly has 20 years experience) so I just am unsure if my expectations were wrong, or if he is just not that great of a construction manager.

Any input would be great!
Thanks!

Comments (10)

  • 13 years ago

    Communication isn't often a builder's strong suit. Even so, you're describing over the top behavior from yourself. Have their been problems in the build that you are insisting on daily updates here? If not, then yes, back off. That's beyond too much. It's distrustful and unnecessarily time consuming.

    If there aren't actual problems, then a once a week update should be all you would need. And if you backed off some, you might get it. Spending a lot of time answering daily questions doesn't leave any time at the end of the week for a comprehensive update.

  • 13 years ago

    I am not insisting on daily updated, there have just been things go wrong this last week and wanted assurance (shingles blowing off during a windstorm and we are expecting 3 days of rain, inspection issues, I ordered the kitchen cabinets and needed details on where they should be put in the house when they arrive)
    I am not calling him every day saying "SO Mike, what's happening today?"

    I have honest, legitimate topics.

    I should note that the first two months of the build we had about ZERO contact with the construction manager, so that is where our concern came into play.

    So basically a once a week update is all I want and we don't get it unless I make a point to contact him and even then he seems bothered or put out by it. I understand he knows what is happening, however, we are brand new to the process and would just like to be somewhat up to day, after all this is the biggest investment we have ever made.

    But yeah, I was feeling like a pest this week, and just wanted to confirm it. :)

    I should also note, we are currently about a month behind schedule (to be expected in winter, I know) but a couple weeks of that is just because contractors haven't been showing up when scheduled to, so that is another small concern)

    Thanks!

    This post was edited by kaljr82 on Fri, Jan 25, 13 at 10:45

  • 13 years ago

    Was this addressed in your contract at all?
    Next, I'd talk with the manager (next week) about communication--saying you know you were a pest last week, but all legitimate. You'll try to consolidate your questions this next week. But, you'd like to be informed/contacted by him with a summary update every Wednesday afternoon/evening (or whatever time works for you).

    If you reach an understanding on that, and you continue to have to nag for updates, then, discuss it with the company that hired this "new guy". Lots of experience or not, he is new to the company you contracted with, and they may not know, or they may have different communication expectations than you do.

  • 13 years ago

    I would ask him if going forward you can have a weekly meeting. That way you know you'll get an update every say, Wednesday at 8:00 am. He'll also know that he needs to give you the update at that time and can organize for it in advance. Zero updates over two months seems very odd though. Unless you don't own the house and land yet? And obviously you should have contact outside of the weekly meeting if there are issues going on. I think you just need to talk to him about being kept in the loop and try to come to some agreement about it.

  • 13 years ago

    I talk with my builder about once a week unless he calls. Inbetween calls I created a google doc with questions that I update throughout the week. When we talk I pull up the sheet and ask him all at once.

    I wish he did google docs... Then I could share it and he can answer the questions when he has the time.

  • 13 years ago

    We are trying to be as "low maint' as possible, the thought being that the more we bug people the slower they go while they are stopping to deal with us. Our hope is that our builder will use his best judgement and give us the finished product we want. To that end we are giving him as much info up front as we can, possibly even overkill but we would rather him have more info than he needs, than not enough.

    I think it would be reasonable to ask for some form of communication on a weekly basis unless there is no update.

    IMHO, if you don't hear from a builder, you should assume that everything is proceeding as expected. If shingles blow off, or whatever, I would expect him to deal with it and resolve the issue in whatever way he saw fit in as timely a manner as he felt it demanded.

  • 13 years ago

    The title Construction Manager has a lot of meanings. I suspect this person is just a project manager for the general contractor so he should be keeping you informed.

  • 13 years ago

    Is this person a "field person", or an "office person"? Is he full time at your site or only part-time, spending time at other construction sites during the week? Clearly he is the builder's employee and, thus, responsible to the builder. Perhaps the builder has him doing other things.

    The advice above is good: contact him and have a short but clear discussion with the goal of reaching a mutual understanding and commitment about scheduled communications. Whatever the arrangement turns out to be, stick to and and don't be the one who breaks the arrangement for more frequent updates.

    Figure out a way for you to keep track of issues and questions until your scheduled meeting and then cover all that you have, asking him to do the same. Good topics include: 1) what has happened in the past week; 2) what's scheduled in the coming week; 3) are there any deliveries, inspections or other similar activities in the near term.

    Good luck on your project.

  • 13 years ago

    Discuss with the manager, or his boss, what would be the most appropriate communication and the frequency.

    As a builder, my first custom build was aggravating for exactly that reason. The buyers--from my plans on my lot, based on the model home--never stopped showing up and pestering everyone. Everywhere. One day both husband and wife came knocking excitedly on my door at 8AM to tell me to get over to the site quickly as something was going wrong. When I got there, my project manager had everything in hand; whatever it was, was just normal construction procedure. Other times, they'd ask the subs what they were getting paid! Or they'd stand over tradesmen. There's nothing more irritating to many people. (Of course, I'd like my young kids sometimes to watch as I work on something to appreciate that not everything in the world moves with the rapidity of a video game! No luck though.)

  • 13 years ago

    thanks for the input.
    I can assure we do not just show up out there randomly and when we do go out there (usually once a week) we do it on a weekend when nobody is working.

    We are not trying to pester him or tell him how to do his job, we honestly would just like to know what is happening on a week to week basis. And many times when I call he will give me answers that seem more like what we want to hear as opposed to the facts.
    (a couple times he has said, such and such is getting done tomorrow, and it turns out it isn't done for 2 more days)
    Yes, we are building in winter and I am completely aware weather affects progress but when went 2 whole weeks of high 30's mid 40's and no precipitation where next to nothing happened, and I just would like to know why? We are now a month behind on our build (half from weather, half unexplained delays) and it is frustrating.