Hi all... first time posting. What a great site!

We are planning on building a new home and we've never worked with a general contractor before. When you interview prospective contractors they present their estimates and I would assume you choose one to work with based on their price, the quality of their work and the "chemistry" to work well together between you and him or her.

My question is.... What would cause the final price to go higher than what the original estimate was. I realize you may make changes and/or request more expensive-or-less expensive items than what were quoted in the estimate.... but can people please share their experiences about what else might drive a change in estimated build costs.

Thanks a lot.

Comments (4)

  • 18 years ago
    last modified: 11 years ago

    Sometimes the prospective builder only gives an educated estimated based on his experience with other projects. These are not hard bids. The final numbers can really vary depending on how much it costs to develop your land, utility hookups, allowances can be too little etc....You need to already have an idea of what finishes you want as that will help the contractor bid more accurately.
    comfortdog

  • 18 years ago
    last modified: 11 years ago

    Several people here have run into significant cost overruns because of excavation surprises. This happened with us as well. I would be as specific as you can on all finishes and still plan on a 10% cost overrun. It seems that many prices go up in January.

    Teresa

  • 18 years ago
    last modified: 11 years ago

    There are just things they can't predict, like with our excavation, we went over his estimate by a lot with the amount of fill it took to get our grade up. There were things we forgot to get a bid for (I am GC-ing my own and my builder gave me a good estimate for most of it, but not all), like gutters and well hook up. We went under on things, also, though. In the end (we are about 2 weeks from closing), we are just about at our budget.

  • 18 years ago
    last modified: 11 years ago

    pearl

    There are at least 3 ways that the cost to you will go up - allowance items, schedule delays, and forgotten items.

    On the allowances - these are builder estimates of costs. You should assume that all builder allownaces are wrong! I am not kidding - you need to verify as many of the variable costs as humanly possible with real bids. Go out an make selections of cabinets, tops,plumbing fixtures etc. before you sign on the dotted line. Then add 4% inflation on top of these preliminary bids because by the time you get around to ordering - prices will probably go up. Note that you don't have to make final selections yet - the goal is to just mamke sure that the $5000 allowance the builder puts in there for cabinets will allow you to buy something that will meet your expectations. We made selections early - and also drove up the allowance wedges significantly. In the end - we were within 1% of these budget wedges - but had we gone with the orginal builder estimates we would have been screwed!!!

    There are some varibale costs that are difficult to nail down precisely (like excavation, well, septic). However - my builder just pulled these numbers out of his rear end - never even got bids from the excavation contractors - and he was way off! You should get bids from these contractors assuming all goes perfectly (i.e. you hit no rock, you hit water on the first shot and it is X feet deep - talk to neighbors to see how deep there wells are). Then add a significant reserve to these numbers - at least a 20% - to cover the ooopes that you may encounter. 20% reserve may be too little depending on where you are building. If your lot is in a rocky area - you might need to add more.

    On the schedule - read all of the other posts on the GC's who promised that they would be done within 9 or 12 months and they weren't. When the builder slips the schedule - you continue to pay interest on the draws he has made. You are also paying either rent or even worse - another mortgage (not recommended!!!).

    I would ask all prospective builders for a hard copy of some schedules for houses they are either working on right now or have just completed. Ask them how they manage to the schedule - and where the key milestones are not only for the house but by when your selections must be finalized. If the GC can't produce a real schedule within a day or 2 (most won't) - then eliminate that person from the list. If a GC says he manages the schedule in his head - RUN!!!

    I am at the very end of a 16 month build that was supposed to take 9 months. Even with all of our planning and selecting things early - we had cost & schedule issues. The good news is that the quality of the house is exceptional. However - we have very long memories and what the builder told us during the sales pitch as far as cost & schedule never panned out - not even close. It has been very painful.

    The last area to consider are the forgotten items - like water treatment. My builder simply forgot to add in a factor for treating the well water. Turns out that we have hard water & some iron. The initial cost estimate (note this was just a month before the house was supposed to be done!) was 8 THOUSAND DOLLARS! I was bale to fix the problem for 1 thousand - but that was still a cost we never expected.

    You have to do your homework - once you are on contract - you are at the mercy of seomone who you will probably know very little about (no matter how many references you check). It's a big risk - proceed with caution.