Subpanel needed?

19 years ago

I know that it needs to be calculated. But my electrician is claiming he did not "anticipate/plan" for a subpanel, so needs to charge more. Everything I can find about garage and bedroom additions seems to indicate a subpanel is MORE likely needed than not. The addition is 500sf bedrroms, 1000sf garage, 110 feet from the existing main panel.

Should an addition of this size been expected to need a subpanel?

Thanks

Comments (7)

  • 19 years ago

    It depends on how many spaces are available in the main panel and what economies can be had by running fewer circuits to the new area. The other option if spaces aren't available is to just put a bigger main panel (depending on the situation).

  • 19 years ago

    Sub panel is only NEEDED if you don't have enough spaces in your existing panel to add the required circuits.
    Sub panel can be advantagess sometimes if running one large circuit from the main to a central location is easier then running multiple circuits from the main panel.

  • 19 years ago

    Well if the main is not maximum sized (40 OCDs) you can always upgrade the main as well. Especially if it is something bogus like an FPE or something hard to get breakers for.

  • 19 years ago

    If you plan on using the garage as a shop, I would go with a sub if I were you. Much easier and more sanitary to add 240V circuits, etc. I wish my garage were that way...and I may just do that some day. How much more is he quoting you? I'm thinking the price of the panel and the wire to the sub should be it. Well worth it in my opinion.

  • 19 years ago

    Did he look at the job before he quoted the job. If so he should of known. If you had him quote it without looking at the job(and probably hinted that there would be room in the panel). Then it is as much your fault as his.

  • 19 years ago

    I would think it's going to be a lot more work and a lot more cable used to run all circuits back to the main panel, you are going to have a number of runs back there, as opposed to one heavier one, not to mention the attendant hassles of running cable through existing walls etc.

    You might point these facts out to the electrician and see if he/she still thinks it's going to cost YOU more, considering he/she will be using a ton more wire, assuming it's already factored into his price.

  • 19 years ago

    The bid was off of plans, GC was who described the job, got the original bid. So I don't know what was said as far as what the existing panel had. I do know the electrician did look at it before he began to lay any wire. At the inspection, the electrician was told to calculate/provide voltage drops to pass. When he did, he presented my husband with a bill for 2500$ to add a subpanel. (We did not feel comfortable paying since the job and distance had not changed, and he did not have a good explanation about why he "missed" the need for a subpanel in his original quote. In fact, he told me I should have had an electrical engineer look at the plans and specify wire sizes, which I have since been told is only required for large scale commercial jobs here) He should have not been billing us anyway since the contract was between him and the GC. (GC did end up agreeing to split the cost with him, and not charge us more for that part)
    In reading about additions, it seems most garages get a subpanel. I was just trying to figure out if it is true that most garages do get a subpanel, and the electrician should have planned for it from the beginning. Or if he was more correct in not planning for it if most garages/additions do not get a subpanel.

    In the end, he messed up in other areas too and tried to demand more money to fix his own mistakes/things he forgot that are in the original quote, and again got angry and rude when asked to explain. We asked that he not be allowed to finish the job. Which the contractor agreed to. But he has been paid for more than what he did, and supplies he did not use yet. So we are still sorting out how to get it all finished up to code and who pays to finish the job.......