Unethical billing practices?

9 years ago

Have a builder who I have caught billing on the monthly draws for things that have not been done and or is charging partial payments.


I was charged over $6000 of a $9500 total cost for before the work was even started. I believe this was hidden under a generic breakdown as "roof". $9500 was for gutters and downspouts. Half round gutters. The gutters where installed on June 1st and I was charged $1913.00 for Flashing/Gutters on the May draw which I got on June 9th. Interesting as no flashing work was done at the time. The downspouts were back ordered and finally installed Monday June 12th. The same day the builder updated the May draw adding $2000 for finishing the work. The Subcontractor billed the GC $9500 June 12th mid afternoon.


The only money left in the whole house build is what the builder has told me is for the last work that needs to be done, building a stairway.



Is this common practice to or is it as I contend unethical at best.



Comments (7)

  • 9 years ago

    My bank inspects before issuing a draw to ensure particular milestones are met and that they don't get ahead of the actual work.

    Make sure you are getting lien waivers too - to ensure that all the subs are paid and you don't end up with any mechanic's liens on your house.

  • PRO
    9 years ago

    What does your construction contract stipulate for payments? A lot depends on the type of construction contract you signed.

  • 9 years ago

    Check the contract - our stipulates ON COMPLETION of work, at the STATED DRAWS.

    That said, our builder has tried invoicing for change orders before work was complete (DENIED, again, not as per contract == no money), and for work that wasn't fully complete (in some cases we allowed with a note and subtract ton that draw, as it was a suppliers' issue and we new he needed some funds to continue work, in others we told him to ask again in 2 weeks when the work was done).

    So no, likely not kosher. Keep tabs on him.

  • PRO
    9 years ago

    In our area, for new construction, it is typical to bill only for work that has been completed, but it depends on the specific contract terms. Exceptions include deposits paid for cabinetry, tops, etc. in advance of installation. It is the typical practice to require payment in full for change orders upon change order approval--not completion. Again, it would depend on the specific terms in your contract.

  • 9 years ago

    It's vital that one keeps tabs on raw materials delivered and used, plus all work completed. All payments after work is verified and completed only.

    In our home construction project, currently under way. I entirely monitor and verify all work in an extremely critical fashion to precisely match my requirements, material used and my design; it's the closest I could get to building it entirely myself since I can, except this is a massive project not suitable for a one man show. Not a simple task since one needs first hand knowledge of engineering, contruction methods and raw materials to validate nitty gritty details, something most folks may not be familiar with or would even be interested in doing. Heck, I'm spending a decent sum and need to track where it is going; I'm a wee bit crazy and spend five to six hours on site four days and a couple of hours on Fridays (my bowling day). I work from 2am-11am then I'm on site from noon to 6pm, yeah sleep 4-5 hours at night if I'm lucky.

    Funnily enough, earlier today, I had a meeting with my GC/Building company owner, when he came over to review progress and my level of satisfaction. He then furnished a very detailed invoice for work/change orders I asked for (significantly over and above agreed estimates and allowances) for foundation, drainage, water proofing, massive grading, increasing stem walls height from 3' to 4' and laying a full 4" concrete rat slab in crawl space. Sure it was a massive bill (almost a month after the work was completed) but all within reason for a job done to my standards and satistaction; coming from me it speaks volumes for the GC, I'm very hard to please.

  • 9 years ago
    last modified: 9 years ago

    My contractor has a plan where payment is like this: "windows and doors: 20k" and then "windows and doors completed: 10k." These payments are not just for windows and doors, but also include other milestones expected to be finished at that time. (I called because I was alarmed at the price for windows and doors, and he reassured me it included other work as well.) My contractor seems trustworthy and has a good reputation, so I am good with this payment method.

    I guess it would all come down to your contract and how payments are stipulated. I'm not sure it would bother me so much if the contractor has been doing a good job and the $9500 is what you had agreed to anyway.