Contractor estimate way off.

5 years ago

We had a landscaper come in and do some work and provided an estimate.


The work was completed in 3 days and we recieved a final invoice that was about 35% over the original estimate and his claim was it took longer to do the work than estimated.


We have asked why he didn't notify us or submit a change order and just claimed that a change order doesn't need to be submitted because scope didn't change (no additional work, just extra hours -- odd since I most places of business do consider that a scope change). He also says he didn't tell us because he didn't know until the 3rd day, which doesn't add up since it's about a 15 hour overage and based on the hour report he sent he was over the estimated hours by Day 2.


We have already pushed back and got some discounts, but he refuses to do more because our contract is just an estimate that can change and he had no duty to notify us.


It seems to give the contractor an incentive to underestimate to get the work and than make it up on the back end.