AquaDefense applied properly?

4 years ago

My tile guys say this is fine. I’m losing sleep thinking this is not applied thick enough to be truly waterproof? I’d love someone to tell me I’m wrong. Or right… before they move forward with tile.

Comments (14)

  • 4 years ago

    Need to determine if the mil thickness is enough. They make a gauge for that as it is tough to tell with the eye and no guarantee one way or the other. What is the substrate the AquaDefense is applied to? And the screw holes should be also be covered with thinset if I am not mistaken.

  • 4 years ago

    It’s on Hardiebacker. I feel like I shouldn’t see white in there. Or is this a “good enough” type of thing?

  • PRO
    4 years ago

    The credit card thickness should be the min thickness after a 2-coat application.

  • 4 years ago

    Get a mil thickness gauge. Not proper mils will mean no product warranty, but that may already be out the window.

  • 4 years ago

    Ok. This looks like one coat. So maybe it just needs another coat. Does it need a lot of dry time before placing tile.

  • 4 years ago

    ….and thanks so much for all the quick feedback. I appreciate. I’m not thrilled having to babysit when we decided to not do this one diy to save us time and headaches.

  • 4 years ago
    last modified: 4 years ago

    The fastener schedule was not followed for the substrate. How was the preslope created? It should not be a pan liner flat on the floor and screwed into the curb with sloped mud on top in the shower. Which is what it appears to have been done. When a topical liquid waterproofing membrane is done, its done as a whole, over a properly constructed preslope.

  • 4 years ago

    I’ll have to talk to them when they get here this morning. How long do they have to let it dry when they put another coat before they can lay tile?

  • PRO
    4 years ago

    I think you have to let it dry for 12hr before testing the pan and until completely dry before 2nd coat around 1hr give or take and about the same time before installing tiles, it should be completely dry.

  • PRO
    4 years ago

    Usually, about 1 hour give or take, specs should be on the bucket.

  • 4 years ago

    The edges of the backer board on your pony walls have not been taped and covered with thin set. If the gaps are less than 1mm you can use tape and AquaDefense to fill them. Also the corners of your curb don't seem to have been waterproofed. How was the pan constructed? Is there a liner? Will the AquaDefense go over the floor too? I see blue board, so will you be plastering the walls and ceiling?

  • PRO
    4 years ago

    Build error at the entrance. Both pony walls should have been framed with angled returns. The vertical faces should be parallel to each other allowing for the glass door hinge to fasten and function properly.

  • PRO
    4 years ago

    Not an industry / mfg compliant install. If they have used a Pan liner and a clamp drain its a failure on multiple levels


    if they HAD used a bonding flange drain it could have worked.



    Theyve failed you here in numerous ways. Do you have a contract? a plumbing permit? flood test inspection?

  • 4 years ago

    I’m having someone else come out to make sure everything is done legit. Thank you everyone for your input!