alison_erickson90

General Contracting Costs for Kitchen

5 years ago
last modified: 5 years ago

I'll start off by saying that I understand that GC costs can vary wildly.

I want to get some opinions on what seems to me to be a high estimate from the GC my KD works with. I am now waiting on more estimates to compare. I was prepared for ~$15K for this work but was quoted $23K. I am in the Chicago area.

The work: Demo 150 sq ft kitchen including a soffit, install porcelain tile flooring, update kitchen wiring, add lights and outlets, patch drywall and prime, install cabs/shelves, minor work to gas line and hood vent to move to the right a few inches, minor trim work in kitchen, update baseboard in the ~300sq/ft connecting room, and rewire the 5 outlets in the connecting room. Appliances remaining in same locations.

The estimate: $2300 demo (OK), $1500 flooring (OK), $3300 electrical (OK), $8000 carpentry/install (??seems high), and $5500 PM fee/$1000 overhead/$750 5% profit/$450 insurance.

So the subs are $15K and the GC fees/O&P are $7250. I guess I was expecting GC fees of maybe $3000-$4000.

There is nothing like a kitchen remodel to make you feel so lonely and clueless :)

Comments (8)

  • 5 years ago
    last modified: 5 years ago

    This actually sounds about normal to me (sorry! I wish I could say differently). That's a lot of trades involved that you've listed. The best way though to see if these costs are average or high is to get several bids, as you are doing.

    Where are the cabinets coming from, and who drew up the kitchen design? Does the KD you mentioned work with this particular GC, or is working for you? I am asking because if you want to compare apples to apples, you need to provide the same kitchen design to all the GCs who are providing estimates.

  • 5 years ago

    Oof- thanks for the honesty :) I purchased the cabinets from my designer. The GC would be working for me but has an ongoing relationship with my designer and was highly recommended by them (and can do the job soon, as I need!). I like the GC, I was just unprepared for this to be the situation. It is very hard to budget for something you've never done, even with endless research.

  • 5 years ago
    last modified: 5 years ago

    While you can get a lot of good, helpful information on GW/Houzz (and some that is neither good nor helpful), you might also want to ask this question locally if you can, since estimates can vary sooo widely geographically. If you have a neighborhood email list, FB group, subreddit, NextDoor, etc., you might get more applicable feedback.

  • PRO
    5 years ago
    last modified: 5 years ago

    I am in the Chicago suburbs. The average kitchen remodel in this area is $75k, including appliances, materials, labor and designer fees. Many kitchen remodels I do are well over $100k. I very rarely work on any below $50k anymore. Also, qualified labor is in high demand right now so we are seeing an increase in prices from GCs, subs and architects. I raised my rates at the start of the year too. Finally, material prices are increasing across the board. Both my cabinet lines had price increases this month. Lumber is out of control.

    Beware the too-good-to-be-true lowball contractor bids. We're seeing a lot of unqualified contractors trying to take advantage of the busy market. You should adjust your budget in consideration of the increased prices instead of trying to find a contractor who will meet it. An unqualified contractor can cost you more in the end.

    Edited to add...there is no such thing as "minor" in the scheme of a larger remodel. If a specialty trade has to work in your home all day, it doesn't matter the type of work they are doing. You are still being charged for their time.

  • 5 years ago

    Kristin- Thank you! This is what I was looking for. I know that the cost for everything has gone way up in the last year and I can tell that everyone is in very high demand; "we're not taking on any more projects" is something I've been hearing.


    That is what makes it so difficult for a homeowner (especially one that hasn't remodeled before, like me) to have a good idea of what to realistically budget at the start.


    It sounds like my estimate is in the zone and also I am lucky to have someone that has me slotted into their schedule.

  • 5 years ago
    last modified: 5 years ago

    There are general guides out there as to what percent of a home's total value to figure for a kitchen remodel. You don't want to over improve for your area, but you don't want to cheap out either, if resale/home value is a concern for you.

    Also, @User has a great breakdown of what proportion of your budget should go for which thing (cabinets, counters, etc.) - not a hard and fast rule, but a good guide. I'll dig around see if I can find it if she doesn't see this and post it.

  • 5 years ago

    I paid $50k for labor only for a kitchen remodel in the Los Angeles area 3 years ago. I think your quote is a bargain!

  • 5 years ago

    Oh yiiiikes! Okay, I am feeling better!