Construction Document Dimensioning
I am having a hard time with the construction documents that our architects prepared, and wanted to get a sanity check on what is reasonable to expect.
Attached is a portion of the floor plan that they prepared. In my mind, there are a number of obvious dimensions that I'd want to see that are missing, I showed them in red - what is the width of the hallway, how far apart are the exterior walls, where are the interior doors placed?
Perhaps this can be backed out by looking at all the interior dimensions, subtracting thicknesses of drywall and wall studs, etc. And perhaps the county will approve this.
But my concern is that we are building a slab on grade home, so all the exterior walls and drain lines have to be located accurately before the slab is even poured. And it seems to me that to that end, I'd want all dimensions to be pretty obvious, without the builder needing to do much math in the field.
Full disclosure, I come from old school mechanical engineering background of pencil and paper drafting. If I had drawn a part with dimensioning like this, the machinist would laugh at me. But I realize that architecture is not meant to be as precise, which is why I wanted to ask for a sanity check on this issue. At the same time, I just read a post here from someone whose walls are off by 4" from what was expected, and I can just see the same thing happening to us.

Comments (64)
tupi2020
Original Author4 years ago@3onthetree On their title sheet, there is probably a general note stating to the effect "discrepancies should be clarified with the architect.
It does say that:"DIMENSIONS TAKE PRECEDENCE OVER DRAWINGS. DO NOT SCALE DRAWINGS. NOTIFY ARCHITECT OF ANY DISCREPANCIES PRIOR TO PROCEEDING WITH THE WORK"
I interpret that as meaning the builder should read the dimensions instead of scaling from drawing (obviously), I'm just not sure how this works when some dimensions are missing. I guess builder will call the architect.Related Professionals
Westminster Architects & Building Designers · Platteville Architects & Building Designers · Sacramento Architects & Building Designers · Jacksonville Design-Build Firms · Westminster Design-Build Firms · Lawrenceburg Design-Build Firms · Sugar Land Design-Build Firms · Eugene Design-Build Firms · Gillette Design-Build Firms · Toronto Design-Build Firms · Mansfield Home Builders · Bennington Home Builders · Marinette Home Builders · Chula Vista Home Builders · Del Rio Home Builderstupi2020
Original Author4 years ago@res2architect The drawings appear to be prepared for the owner rather than the contractor. The owner may never see the actual construction doucments.
The architects said they are only making one document set, to serve for both permitting and bidding/construction. So this is all there is.- 4 years agolast modified: 4 years ago
I guess builder will call the architect.
My builder partner once discovered on-site that the plan had two corners that didn't meet. He called the architect, who advised him to use some "on-site ingenuity".
**
An architect I employed visited the finished house and was impressed with the curved staircase. "I drew it, but I wasn't sure they could do it or not."
**
I was taught, as a general rule, to have as many dimensions outside of the building's footprint as possible, in four strings of dimensions
Exactly! Just one of the problems I have looking at a current plan. The first string is missing. To figure the width of the foundation, you have to add seven separate sizes (in metric and Imperial).
tupi2020 thanked worthy tupi2020
Original Author4 years ago@Mark Bischak, Architect your sketch is exactly what I would hope and expect, it makes everything very clear. And yes, I was taught the same thing for dimensioning when I was in high school, way before desktop computers :).
Our architects' drawings are nothing like this, which is why I am concerned about having to use ingenuity in the field - that does not bode well for me.- 4 years ago
I took some liberties with the definition of 'a couple years ago'.
tupi2020 thanked Mark Bischak, Architect tupi2020
Original Author4 years ago@Mark Bischak, Architect I took some liberties with the definition of 'a couple years ago'.
I figured so :).- 4 years agolast modified: 4 years ago
And don't forget that with CAD it's impossible to have a wrong dimension. The drawing is done at full scale (12"=12"). If the house is 50' wide, I'm actually doing a drawing 50' wide although it's zoomed out on my monitor so the dimension number will be whatever distance apart the two clicks of the curser are which typically "grabs" the closest wall edge to where it's hovering. Which leads me to believe, with all those fractions, that whoever laid out the walls in the OP's house didn't do a very good job of locating the walls.
The only way to have a dimension reading different than the actual distance being measured is to "explode" that dimension, breaking it into its components like extension lines, hash marks and the dimension number itself and then manually editing the number. Something I rarely if ever need or like to do but I know other architects do on a regular basis which can lead to errors.
Also, in CAD everything is put on its own layer. I have like 40 of them, walls, fixtures, doors, windows, cabinets and yes dimensions. So, if I wanted to give the client a drawing of the house without the dimensions, I just turn off that layer and print out a PDF.
tupi2020
Original Author4 years ago@Architectrunnerguy Which leads me to believe, with all those fractions, that whoever laid out the walls in the OP's house didn't do a very good job of locating the walls.
That's an interesting point - my first thought is that if I'm designing a house, I would lay things out in reasonably round numbers. If not in round feet, then certainly in round inches. But with CAD, there is no incentive to do that, is there? You just draw a line where it looks good, then backfill the dimension, be it 3', 3'-2", or 3'-2-1/16", all the same to me.
I've designed many mechanical assemblies in the past, and even when using CAD, I would draw something that looked right, then adjusted the dimension to a reasonably round number - maybe not 3.000", but 3.200". I would not let the part be 3.213" unless there was some reason for it.
Maybe it's just an aesthetics thing, but I agree, it makes me chuckle to see a room dimensioned with 7/8" precision.
So, if I wanted to give the client a drawing of the house without the dimensions, I just turn off that layer and print out a PDF.
That may be the answer, we'll see next week. At this point my understanding is that there is only one drawing set, and we're looking at it. But wonders never cease!tupi2020
Original Author4 years ago@Joseph Corlett, LLC This is a house, not a space telescope. Relax, it will be fine.
That's fair, if you mean that it does not need to be accurate to 1/8". And I agree with that - I don't think I ever said on this thread that want the drawings to be more accurate; if anything, I tried to say the opposite.
I just want them to have enough detail for the builder to build the house without guessing, that never ends well. How will the builder locate the windows if their location is not shown on the drawings?
Again, I'll refer to the other thread with the poster whose kitchen ended up 4" smaller than s/he expected, and so many responses are that the plans should have been more clear. I don't want a "relax, it'll be fine" attitude to get me to the same end point :).- 4 years ago
Not an expert and many of them have commented here but in our build I noticed there were multiple versions of plans depending on what they were used for. So the permit package with all the architectural drawings had way more details and notes on it than the floor plans we worked with for basic discussion of layout and even lighting overlay and what not.
tupi2020 thanked WestCoast Hopeful - 4 years agolast modified: 4 years ago
That's an interesting point - my first thought is that if I'm designing a house, I would lay things out in reasonably round numbers. If not in round feet, then certainly in round inches. But with CAD, there is no incentive to do that, is there?
Yes, there is an incentive to do that. You want the walls laid out accurately and then dimension to that. As I said above, a CAD drawing is done at full scale. The drawing I posted above is actually 52'6" long. It's just printed out at a reduced size (usually 1/4"=1' instead of 1'=1'). And everything should be in round inches, at least going around the exterior. The only reason I have some 1/2" dimensions in the interior is all dimensions go to face of stud and those are either 3 1/2" or 5 1/2". If studs were actually 4" and 6" then there wouldn't even be those 1/2" interior dimensions.
tupi2020 thanked Architectrunnerguy tupi2020
Original Author4 years agoYes, there is an incentive to do that. You want the walls laid out accurately and then dimension to that.
Absolutely, I should have said that there may be no incentive to the architect to make the dimensions round numbers. There is definitely an incentive to the builder and the trades to work with round numbers. Who wants to be walking around the jobsite adding up 21' 3-7/8", 37' 11-5/16", etc. Sure, it can be done, but why? The chance of a mistake goes up, for no reason other than laziness. And as we agree, no framer is going to lay out studs with 1/8" accuracy, nor should he have to.
Just for fun, I googled "proper dimensioning for construction documents". Without fail, all the guidelines are to use string dimensions as you guys said (and as I was taught in school).
Here's a good link, and starting at 7:15, the gentleman says that most CAD programs have a continuing dimensioning ability, which would spit out the dimension strings like we're talking about. https://www.youtube.com/watch?v=SsId08gmqhY&ab_channel=BoxShell- 4 years ago
In my experience, there are times when working out all the components and desires that go into designing a home, I have found it necessary at times to dimension to a 32nd of an inch, particularly when centering a window in a wall. On my drawings I draw and dimension to the rough window openings, and I draw by hand so there is no computer determining the dimensions.
tupi2020 thanked Mark Bischak, Architect - 4 years ago
You should have a ton of pages in your construction docs - a specific foundation drawing, framing drawings, window and door openings, etc.
I don't think this drawing is the "main" one in your construction docs - ours didn't have ANY beds / furniture in them
And as you go through construction, get a variety of tape meaures - get the 25' fatmax, a 50' tape, and the longer 150'+ verson - check "everything"tupi2020 thanked just_janni tupi2020
Original Author4 years agoI wish I could post the entire package here, but I don't think I can. The drawing I posted is the one with the most dimensions on it. The roof plan and the slab drawing have no dimensions to speak of, nor do the interior room closeups.
That may all change in the final set, so I will sit patiently and wait (not my strong suit, just ask Mrs. Tupi). At least now I have an idea of what I should be expecting or asking for.- 4 years ago
My construction doc package was 20-ish pages....
For example - here was our foundation plan - probably too small to see - but there's a lot of dims on there...
tupi2020 thanked just_janni tupi2020
Original Author4 years agolast modified: 4 years agoOur package has just one page for the slab, and I posted that earlier. To be fair, our architects punted much (all) of the structural design to a Structural Engineer, and we just received their preliminary package. However, while they do detail the rebar and holddown schedule (snip attached), there are no dimensions, they say to reference the architectural drawings.

- 4 years ago
"they say to reference the architectural drawings."
If I did that, I would fear for my life if I visited the site when the excavator was on site.
- 4 years ago
IMO that's unacceptable. We had a third party structural engineer who worked in lock step with the architects - but the plans and dimensions were the responsibility of the architect to ensure proper execution.
Excavating that and pouring it and them copying the dimensions from the main page seems like a way to end up with some frustrating errors, and frustrating your foundation guys.tupi2020 thanked just_janni - 4 years ago
Has your contractor worked with this architect previously? Did you have any client references for the architect? I've not seen an architect leave so much work to the structural engineer.
tupi2020 thanked Kelley Dockrey - 4 years ago
Do you have full sets? Likely won't get a GC, framer or foundation contractor to bid unless it has what you are seeking but these are just pieces at this time.
Your posted pieces have enough interior dimensions to communicate the design to a homeowner at this point.tupi2020 thanked Jeffrey R. Grenz, General Contractor tupi2020
Original Author4 years ago@just_janni IMO that's unacceptable. We had a third party structural engineer who worked in lock step with the architects - but the plans and dimensions were the responsibility of the architect to ensure proper execution.
I wish we had the same situation, but our architects did the entire schematic design in a bubble of their own, without a builder, structural, or HVAC involved. Only when the design was almost finished and I asked them where the HVAC will go, they said "that's up to your HVAC designer to figure out". So now I have a $4000 HVAC designer trying to fit an HVAC system into a design with no provisions for ductwork.
And I have a $10000 Structural Engineer who does not return emails and refuses to work with me; apparently he only works with the architects. His contract said that work includes "discussion of structural system options", "discussion of alternative systems to reduce costs", etc. I emailed him asking if we can use TJIs instead of a bunch of steel beams across the clerestory, and I got nothing back. Maybe that's his definition of discussion?
And the architects are taking a week or more to reply to our emails, because they are focusing on getting the final package done for submittal. Which would be fine if I thought that they were on the right path, but I don't. I guess the only leverage I have is to use their level of "responsiveness" when I receive their billing statements.tupi2020
Original Author4 years agolast modified: 4 years ago@Kelley Dockrey Has your contractor worked with this architect previously? Did you have any client references for the architect? I've not seen an architect leave so much work to the structural engineer.
We haven't chosen a builder yet, but the one the architects have worked with before and recommended does not return emails (I see a pattern here), so he's our last choice at this point.
And I agree about leaving all this work to the Structural Engineer (especially at this late stage), that was a very unpleasant surprise for me.
- 4 years ago
16" deep TJIs max out at 32' without a snow load. Most engineers won't use steel unless needed. You're building a non conventional project. If you're using a thin flat roof profile, you have an HVAC challenge.
Some architects or designers only price their portion. Detailed HVAC design is rarely required in permit submittals & often done by the HVAC contractor in conventional builds.
$10K is not much for engineering this home. Unless the engineers contract is with you, (s)he may not respond immediately and may be a "night job" while engineer works salary job elsewhere or a part time job for a retired engineer who may be on vacation. These are low cost, but not high service options. Not my preference as a builder. All engineers have been swamped for the past few years.tupi2020 thanked Jeffrey R. Grenz, General Contractor - 4 years ago
If you are a good architect, and have a portfolio of modernist homes that are long / low / flat roofed, etc - and you are not engaging with or know a decent HVAC person to help provide provisioning, then you are not doing a god job. Taking a $1M+ modern home and just leaving to chance both the aesthetics and the functionality of all the systems is, IMO, not cool for the amount of $ I am guessing the OP is investing.
My architect went into design - build because he wanted to see his and his clients' vision executed well. I believe it also informed how he developed his designs (since he was often in change of getting a good result out of them in real life!). His interns all worked on the build sites to solve the problems of execution in a way that fit the program.
IMO it's disappointing to see anything less than a holistic approach from the architectural field - especially if we're talking about the kind if full service that appears to be in play here. tupi2020
Original Author4 years agolast modified: 4 years ago@Jeffrey R. Grenz, General Contractor
16" deep TJIs max out at 32' without a snow load. Most engineers won't use steel unless needed.
The ones I've worked with tend to err on the very conservative side unless I push back. I've had an engineer propose 4'x4'x3' concrete pads with steel I-beams, and when I asked why can't we use 2x framing over a continuous foundation, his reply was "well you could do that".
Our great room span is about 32', if I add up all the 1/8" correctly.

I believe that 16" 560 TJI's can span up to 36' with a 25 lb snow load. The engineer specified steel. I'm not looking to argue with him, I just want to ask if he considered TJIs before jumping to steel.You're building a non conventional project. If you're using a thin flat roof profile, you have an HVAC challenge.
Yes, and we are now adding soffits all over the place to accommodate ducting. Had I known that they were not even considering HVAC during schematic design, I would have asked for 10 ft ceilings so we end up with 9 ft soffits. Good thing we didn't order the 8 ft doors they specified, that would not work well with 8 ft soffits.
Detailed HVAC design is rarely required in permit submittals & often done by the HVAC contractor in conventional builds.
Absolutely, I agree, But they have to design a house to accommodate HVAC, not to dump it onto a homeowner as an afterthought.
$10K is not much for engineering this home. Unless the engineers contract is with you, (s)he may not respond immediately and may be a "night job" while engineer works salary job elsewhere or a part time job for a retired engineer who may be on vacation. These are low cost, but not high service options. Not my preference as a builder. All engineers have been swamped for the past few years.
This is a structural engineering firm that we contracted, not a moonlighter. I know that he prefers to work with the architects instead of us, but the architects are not asking him the questions I'd like them to ask. And when I ask the architects any questions, they say "it's whatever is in your contract with the structural engineer".
tupi2020
Original Author4 years ago@just_janni IMO it's disappointing to see anything less than a holistic approach from the architectural field - especially if we're talking about the kind if full service that appears to be in play here.
We signed up for a full service approach, which is why it is so disappointing to not just have to correct many really bad design ideas but to also find out that we have to engage HVAC, Structures, etc, all after the fact. I guess $130K doesn't buy what it used to....
I'm sorry, I don't mean this thread to turn into "bash the architect", it's just so frustrating when on most of my threads here (house layout, HVAC, dimensioning) I keep hearing the same "your architect doesn't seem to know what he's doing" responses.- 4 years ago
I get 31'-6 1/2", minus two wall thicknesses for the great room span.
tupi2020 thanked Mark Bischak, Architect - 4 years agolast modified: 4 years ago
The OP is not the builder, so most of these issues would or should be worked out between the builder, architect and various consultants.
As a former licensed builder--who never got beyond a sympathy pass in 9th grade algebra--the structural details I leave to the engineers. The 81 P. eng. sealed pages of floor and roof plans we provided to the City for the latest build--and that's only part of the required package--are a mystery to me! Detailed HVAC and structural details have been a required part of the building permit submission for decades in our area.
[For the nitpickers, building for your own occupation does not require licensing in Ontario.]
tupi2020 thanked worthy - 4 years ago
Again not an expert but we never expected an architect/designer to do anything but design. Of course other professionals are needed to work with our team to make the house a reality. I didn’t want a designer doing HVAC or structural engineer work. I wanted those who are experts in those fields to do with it. Everyone should work together but doesn’t it make more sense to have experts for the different aspects provide it?
tupi2020
Original Author4 years ago@WestCoast Hopeful Everyone should work together but doesn’t it make more sense to have experts for the different aspects provide it?
Of course the experts should handle their specialty areas, but the bolded part above is missing in our case. There was no involvement from these specialty disciplines throughout schematic design. So at this point we have an HVAC designer trying to snake ducts through a design that did not leave any provisions for ducting.- 4 years ago
We had same. HVAC was decided on site with us, builder and HVAC guy. We worked together to focus on what we needed to make the house clean as possible. But it was already framed by then.
Structural engineer did an overlay of what what needed to the plans and it was submitted in addition to our plans to our city for approval.
I do recall in your initial thread several people asking about HVAC and indicating the importance of planning this for your unique build…
- 4 years ago
I think part of having an architect - who can (at least in my state?) sign and stamp drawings for the permittting package - is that they can create something that is BOTH functional and aesthetically pleasing. A well DESIGNED home needs to work for the inhabitants - not just look pretty.
I don't want them designing an HVAC system, but I want them to know one is going to be needed, plan some space for the equipment, the ductwork, etc. I know that might be asking a lot - but I don't think it's out of line for a professional and at 10% of build costs in some instances - seems reasonable!tupi2020 thanked just_janni tupi2020
Original Author4 years agolast modified: 4 years agoGetting back to my original question - we heard from the architects yesterday, they said they plan to give us the final document set on Feb 10, and then submit the plans on Feb 11. Hoping to avoid too much back and forth and the associated delays, I wrote back that while they most likely already did this, I would like to request that final set has string dimensioning that clearly shows locations of all walls and openings, with dimensions as close to 1" increments as possible, unless required otherwise. This is my attempt at an ounce of prevention.
tupi2020
Original Author4 years agolast modified: 4 years agoUpdating this thread - we received the updated drawings, where the architects added more dimensions like I asked them (see attached).
But digging in further, I think there is still some critical information missing, if I tried to use the drawings to build the house (which the builder is going to have to do). For instance, looking at window Z in the attached blow-up - that window spans the entire north/south wall; the span is shown to be 3'-9". It is not clear what that dimension refers to - I would assume that is distance between stud faces, not finished wall. Should that be clearly stated?
Assuming it's the dimension between stud faces, the available width for the window will become smaller after we add siding to the exterior wall, and drywall to the interior wall. But the window schedule calls out 3'-9" for window Z RO. So if the window manufacturer supplies a window made for a 3'-9" RO (which will be about 1" narrower than the RO), is that going to fit properly into this space?
I'm just wondering if these are the kind of details that the architects need to figure out and address, or something that the builder typically deals with?


- 4 years ago
Those dimensions are typically stud edge to edge aka "rough opening" and in the case of that window it may be best to measure the remaining opening after framing and shear panels are applied as they are often overlooked.
tupi2020
Original Author4 years agoThey have a number of similar windows that span the entire wall. And like you said, I don't think the details of shearwall sheathing, drywall, and siding, have been thought through in terms of how that might affect the RO.
I'm attaching another detail that concerns me. That 4'-7 1/2" width is from stud to the perpendicular window edge, which does not make clear what the stud to stud distance should be. And they specify window H as 4'-3", leaving 4 1/2" for drywall, post, etc. I think if I were the framer, I would have no idea how to frame it.
I hear you that it's best to frame first, and then order the windows. The problem is that with a 20 week lead time for windows, we need to order windows soon, still months from framing. Otherwise we end up with months of downtime. So I am looking at these details to ensure the windows we order will fit into the openings. In most cases, where a window is framed in a portion of a wall, that is not a problem. But in the cases I showed where the window spans the entire wall, this seems like a potential problem. I wonder if I should have them make the openings smaller, so they don't span the entire wall and thus the opening can be framed to suit the window size?
- 4 years ago
Can you post the window schedule that corresponds to the letters in the diamond shape at each window on the plan? They sometimes show rough opening sizes.
tupi2020
Original Author4 years agolast modified: 4 years agoSure, see below. I'm not sure you'll be able to make out the callouts on the plan, I can post larger pictures.




- 4 years ago
As long as the architect's coordination between the plan and the schedule are correct, and the manufacturer makes the windows for those rough openings, and the builder makes the rough openings those sizes, you have nothing to worry about. But don't stop praying for it to work out all right.
- 4 years ago
Ordering windows early is a major key to keeping a home on schedule. Clients resist this but if you trust the process and it appears you were involved in window design, it is viable, but rare with aluminum window homes coupled with storefront type openings.
Suggest you get a builder involved as well as a framing contractor competent in this level of home construction. They can figure out the layers involved and come up with realistic sizes, check the structural plans for "cooperation" with the windows for post sizes, hardware locations.
This is not a traditional assembly with lots of margins and room to build a window rough opening precisely even when the foundation is off. My aluminum window dealer/installer works with very tight margins (and smaller than typical nailing fins) requiring him to measure as built window openings. My wood & vinyl dealers will order from lists allowing us to install once the home is framed. tupi2020
Original Author4 years ago@Mark Bischak, Architect As long as the architect's coordination between the plan and the schedule are correct, and the manufacturer makes the windows for those rough openings, and the builder makes the rough openings those sizes, you have nothing to worry about. But don't stop praying for it to work out all right.
In other words, if all the stars line up and I've done my fair share of praying to the right gods, it'll all work out? :)tupi2020
Original Author4 years agolast modified: 4 years ago@Jeffrey R. Grenz, General Contractor we do have a builder involved, and we had a meeting last week to go over the plans with the builder and the window rep. At that time the window rep said they simply undersize their windows by about 1" total compared to the RO, which seemed to satisfy the builder.
But as I am looking deeper at the details, I am finding the issues that I mentioned above, such as not being able to frame an opening within a wall to meet the required RO - the RO is not framed within a wall, but is defined by a number of parallel or perpendicular walls, and does not account for siding or drywall. And like you said, that leaves no margin, which means that the window installation needs to be very clearly detailed (i.e. where the studs are, how the siding and DW overlap the window, etc). I don't see that on the plans, and I think the architects haven't thought it through enough.
My question is whether it is reasonable of me to push on the architects to get this properly thought out and detailed, or is it typical for this to be dumped onto the builder to figure out?
- 4 years ago
Windows are installed prior to siding and drywall, which are butted up to the window frames.
Drawings can be detailed infinitely but it is not necessary.
And yes it is typically "dumped" on the builder along with a pile of disclaimers. tupi2020
Original Author4 years ago@Jeffrey R. Grenz, General Contractor Thanks, that's helpful. I just want to make sure we don't order windows that won't fit into the openings :). I'll be sure to bring this up again to the builder and the window rep before we finalize the sizes.
I was just hoping for something like the attached plan, which makes it clear what the reference plane is ("face of stud"), what the R.O. is, etc, all in one place. But we'll make ours work out, one way or another.












Mark Bischak, Architect