Project 002 - Old Greenwich, CT
Driveway 1: 3.833 sqft
Driveway 2: 860 sqft.
Project duration: 1 week.
ISSUES:
Common Road: Potholes everywhere
Driveway #1: Worn out stone aprons (the stone patterns at the entrance), cracks, weeds on surrounding stones, old walkway needed to be redone with flat stone.
Driveway #2: Cracks and potholes.
Our Solutions:
Common Road: Ripped out old asphalt and graded the surface. Added new asphalt and flattened it with a ton roller.
Driveway #1: Installed new Stone Aprons with cement joints, repaved driveway eliminating cracks, all weeds on surrounding stones were removed, created a new flat stone walkway.
Driveway #2: Repaved driveway eliminating cracks and potholes.
Driveway 1: 3.833 sqft
Driveway 2: 860 sqft.
Project duration: 1 week.
ISSUES:
Common Road: Potholes everywhere
Driveway #1: Worn out stone aprons (the stone patterns at the entrance), cracks, weeds on surrounding stones, old walkway needed to be redone with flat stone.
Driveway #2: Cracks and potholes.
Our Solutions:
Common Road: Ripped out old asphalt and graded the surface. Added new asphalt and flattened it with a ton roller.
Driveway #1: Installed new Stone Aprons with cement joints, repaved driveway eliminating cracks, all weeds on surrounding stones were removed, created a new flat stone walkway.
Driveway #2: Repaved driveway eliminating cracks and potholes.
Project Year: 2019
Project Cost: $10,001 - $25,000