Project 201909-010
Project 201909-010
Project 010- Greenwich, CT
Driveway: 2.814 SQFT
Curbing (sides of the driveway): 185 linear ft of Belgium Blocks and 64 ft of 45 grades Belgium Blocks.
Entrance: Aprons
Project duration: 5 days.
Issues:
It was an ancient property with a driveway in not good condition. The builder made demolition of the whole property and built a new house and therefore a new driveway with luxurious designs.
Our Solution:
We regraded the existing base of the driveway and compacted it. We made the aprons installation process in both sides of the driveway linearly and at a certain point, we changed the way to install them. Specifically, the new way was flat (you can see the contrast in our Pictures). It according to the owner’s preferences. Finally, we made the paving process.
Project 010- Greenwich, CT
Driveway: 2.814 SQFT
Curbing (sides of the driveway): 185 linear ft of Belgium Blocks and 64 ft of 45 grades Belgium Blocks.
Entrance: Aprons
Project duration: 5 days.
Issues:
It was an ancient property with a driveway in not good condition. The builder made demolition of the whole property and built a new house and therefore a new driveway with luxurious designs.
Our Solution:
We regraded the existing base of the driveway and compacted it. We made the aprons installation process in both sides of the driveway linearly and at a certain point, we changed the way to install them. Specifically, the new way was flat (you can see the contrast in our Pictures). It according to the owner’s preferences. Finally, we made the paving process.
Project Year: 2019
Project Cost: $10,001 - $25,000
Country: United States
Zip Code: 06830